Semans is a manufacturer that produces bracket assemblies. Demand for bracket assemblies (X) is 128 units. The following is the BOM in indented form:
| ITEM | DESCRIPTION | USAGE |
| X | Bracket assembly | 1 |
| A | Wall board | 3 |
| B | Hanger subassembly | 2 |
| D | Hanger casting | 3 |
| E | Ceramic knob | 2 |
| C | Rivet head screw | 4 |
| F | Metal tong | 4 |
| G | Plastic cap | 2 |
Below is a table indicating current inventory levels:
| Item | X | A | B | C | D | E | F | G |
| Inventory | 30 | 21 | 62 | 24 | 189 | 270 | 1,200 | 105 |
b. What are the net requirements for each item? (Leave no cells blank - be certain to enter "0" wherever required.)
| Item | Net Requirements |
| X | |
| A | |
| B | |
| C | |
| D | |
| E | |
| F | |
| G | |
Based on the given data, we prepare a product structure tree as shown below:

Based on the usage given and current inventory levels, we find the requirement of each part as shown below:

The on-hand inventory is subtracted as shown in red. Hence,
| Item | Net Requirements |
| X | 98 |
| A | 273 |
| B | 134 |
| C | 368 |
| D | 213 |
| E | 0 |
| F | 272 |
| G - 631 |
-----------------------------------------------------------------------------------------------------------------------
In case of any doubt, please ask through the comment section before Upvote/downvote.
If you liked the answer, please give an upvote. This will be quite encouraging for me, thank-you!!!
Semans is a manufacturer that produces bracket assemblies. Demand for bracket assemblies (X) is 128 units....
Semans is a manufacturer that produces bracket assembles. Demand for bracket assemblies (X) is 128 units. The following is the BOM in indented form: DESCRIPTION Bracket assembly Wall board Hanger subassembly Hanger casting amic knob Rivet head rew Matal tong Plastic cap ITEM USAGE X A B 2 2 5 G Below is a table indicating current inventory levels: Item Inwentory F 1,220 G 95 69 196 145 17 26 17 b. What are the net requirements for each item?...
Semans is a manufacurer that produces bracket assemblies Demand for bracket ssembles0)is 1 units The fllowing is the BOM in indented form Bracket assemby A Wall board B Hanger subassembly Hanger casting Ceramic kno C Rivet head screw F Metal tog G Plastic cap Below is a table indicating aunent iventory lvls hem Inventory25 16 6620 193 290 1,100 110 b. What ane the net requirements of each item in the MPS? (Leave no cels blank-be certain to wherever required
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
Assume that Product Z is made of two units of A and three units of B. A is made of four units of C and four of D. D is made of two units of E Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty one units of Product Z are required in Period 10. (Assume that...
One unit of A is made of one unit of B and one unit of C. B is
made of four units of C and one unit each of E and F. C is made of
two units of D and one unit of E. E is made of three units of F.
Item C has a lead time of one week; Items A, B, E, and F have
two-week lead times; and Item D has a lead time of...
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...
Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty units of Product Z are required in Period 10. (Assume that there...
Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and three of D. D is made of three units of E Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty seven units of Product Z are required in Period 10. (Assume that...