Q1. 58 %
% complete = Actual area of carpet installed / budgeted area
= 1500/2600
= 58 %
-------------------------------
Q2. 3,450
BCWP = Actual area of carpetinstalled * budgeted unit cost
= 1500*2.30
= $ 3,450
-------------------------------
Q3. 3,150
ACWP = Actual cost incurred till date
= $ 3,150
-------------------------------
Q4. 2,392
BCWS = Area of carpet as per schedule * budgeted unit cost
= 2600*4/10 * 2.3
= $ 2,392
-------------------------------
Q5. 300
CV = BCWP - ACWP
= 3450 - 3150
= $ 300
-------------------------------
Q6. 1,058
SV - BCWP - BCWS
= 3450 - 2392
= $ 1,058
-------------------------------
Q7. 1.095
CPI = BCWP / ACWP
= 3450 / 3150
= 1.095
-------------------------------
Q8. 1.44
SPI = BCWP / BCWS
= 3450/ 2392
= 1.44
-------------------------------
Q9. 517
FCV = CV / % complete
= 300/58%
= 517
-------------------------------
Q10. 1,824
FSV = SV / % complete
= 1058/58%
= 1,824
-------------------------------
Q11.
CV is positive and CPI is greater than 1, which means that the project is under budget
SV is positive and SPI is greater than 1, which means that the project is ahead of schedule
Aflooring subcontractor has to install 2,600sq ft of carpet for an existing building for unit cost...
A flooring subcontractor has to install 2,600sq ft of carpet for an existing building for unit cost of $2.30 per sq ft. The subcontractor was given 10 days to finish all the work. Four days after the start of the work, he found out 1,500sq ft of the carpet is installed and its actual cost was $3,150 to that date. Perform EV (earned value) analysis on the task above Q1- What is the BCWS? Q2-What is the CV? Q3-What is...
A flooring subcontractor has to install 2,600sq ft of carpet for an existing building for unit cost of $2.30 per sq ft. The subcontractor was given 10 days to finish all the work. Four days after the start of the work, he found out 1,500sq ft of the carpet is installed and its actual cost was $3,150 to that date. Perform EV (earned value) analysis on the task above Q1- What is the % complete? Q2-What is BCWP? Q3- What...
what is the % complete?
what is the BCWP?
what is the ACWP?
what is the BCWS?
what is the CV?
what is the SV?
what is the CPI?
what is the SPI?
what is the FCV?
what is the FSV?
A flooring subcontractor has to install 2,600sqft of carpet for an existing building for unit cost of $2.30 per sq ft. The subcontractor was given 10 days to finish all the work. Four days after the start of the...
Your company was hired as a subcontractor for a client's "Destiny project and awarded two main work packages within that project. Your company refers to this project internally using the cost code "P2 2019". You're given the table below that lists the work packages, their cost code, their budget, and their scheduled start day and end day (as agreed upon with the main contractor). The start and end days are measured in working days after the main project's start. So,...
QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...