Question
please solve excel solver and to.excel file
WORKFORCE PLANNING-BUS SCHEDULING MODEL Example 2.4.5 on page 68 of Tahas book Number of busses as a function of the time of
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Set up Excel model as follows:

H ㄴ с X2 E X4 F X5 1 X3 X6 Required 1 4 1 8 1 1 Available =SUMPRODUCT(B3:G3,$B$11:$G$11) =SUMPRODUCT(B4:G4,$B$11:$G$11) =SUMP

Set up Solver Parameters as follows:

Solver Parameters X Set Objective: $B$14 1 To: Max Min Value Of: 0 By Changing Variable Cells: $B$11:$G$11 1 Subject to the C

Click Solve to generate the solution.

After that, values appear automatically in variable (yellow colored) cells

A H K L M N B X1 с X2 D X3 E X4 F. X5 G X6 1 1 1 1 1 1 1 Available 4 8 10 7 12 11 Required 4 8 10 7 12 4 1 1 1 1 1 > 2 3 12AM

Click OK

Optimal schedule of buses is :

Starting time Number of buses
12:01 AM 4
4:01 AM 4
8:01 AM 6
12:01 PM 1
4:01 PM 11
8:01 PM 0

Total number of buses = 26

Add a comment
Know the answer?
Add Answer to:
please solve excel solver and to.excel file WORKFORCE PLANNING-BUS SCHEDULING MODEL Example 2.4.5 on page 68...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • please solve the excel solver and please SHARE excel file or pdf excel file share inside...

    please solve the excel solver and please SHARE excel file or pdf excel file share inside excel file WORKFORCE PLANNING-BUS SCHEDULING MODEL Example 2.4.5 on page 68 of Taha's book Number of busses as a function of the time of the day: AM Variable Number of waste totam *Number of starting com Number of sing alom

  • Solve with excel solver and share in excel file MULTI-PERIOD PRODUCTION-SMOOTHINGG MODEL Example 2.4.4 on page...

    Solve with excel solver and share in excel file MULTI-PERIOD PRODUCTION-SMOOTHINGG MODEL Example 2.4.4 on page 65 of Taha's book A company will manufacture a product for the next four months: March, April, May, and June The demands for each month are 520, 720, 520, and 620 units, respectively. • The company has a steady work force of 10 employees but can meet fluctuating production needs by hiring and firing temporary workers at the beginning of each month, if necessary...

  • please solve this question excel solver and to excel file MULTI-PERIOD PRODUCTION-SMOOTHINGG MODEL Example 2.4.4 on...

    please solve this question excel solver and to excel file MULTI-PERIOD PRODUCTION-SMOOTHINGG MODEL Example 2.4.4 on page 65 of Taha's book • A company will manufacture a product for the next four months: March, April, May, and June. The demands for each month are 520, 720, 520, and 620 units, respectively. • The company has a steady work force of 10 employees but can meet fluctuating production needs by hiring and firing temporary workers at the beginning of each month,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT