You have gathered the following information about a company you are analyzing:
If the company follows a residual dividend policy, what is the company’s payout ratio this year?
| after tax cost of debt | cost of debt*(1-tax rate) | 8*(1-.3) | 5.60% | |
| cost of equity | 13% | |||
| WACC =(weight of debt*after tax cost of debt)+(weight of equity*cost of equity) | (.5*5.6%)+(.6*13%) | 10.60% | ||
| Project | Investment | IRR of project | WACC | Accept if IRR> WACC and Reject if IRR<WACC |
| 1 | A | 12% | 10.60% | Accept |
| 2 | B | 11.50% | 10.60% | Accept |
| 3 | C | 10.75% | 10.60% | Accept |
| 4 | D | 10.15% | 10.60% | Reject |
| 5 | E | 9.75% | 10.60% | Reject |
| total Investment required in three project | 1+1.2+1.2 | 3.4 | ||
| Amount required from equity in millions | 3.4*60% | 2.04 | ||
| Amount required from debt in millions | 3.4*40% | 1.36 | ||
| Amount of EBIT in millions | 3 | |||
| amount of equity financed from net income | 2.04 | |||
| amount of profit left for dividend | 3-2.04 | 0.96 | ||
| Payout ratio = amount left to declare dividend/ebit | .96/3 | 32% |
You have gathered the following information about a company you are analyzing: Expected net income for...
The following information relates to Toronto Ltd: - Net income for the current year is $3 million - The after-tax cost of debt is 4.88% - Target capital structure weightings are 30% debt, 20% preferred, with the remaining amount in equity - The weighted average cost of capital for the firm is 9% - Below is a list of possible capital projects and the company has $15 m of available funds: Project Name Project Size Project IRR YG $3.1 million...
Harris Company must set its investment and dividend policies for the coming year. It has three independent projects from which to choose, each of which requires a $5 million investment. These projects have different levels of risk, and therefore different costs of capital. Their projected IRRs and costs of capital are as follows: Project A: Cost of capital = 15%; IRR = 18% Project B: Cost of capital = 14%; IRR = 9% Project C: Cost of capital = 7%;...
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 16% IRR = 18% Project M (medium risk): Cost of capital = 13% IRR = 12% Project L (low risk): Cost of capital = 7% IRR = 10% Note that the projects' costs of capital vary because the projects have...
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 15% IRR = 22% Project M (medium risk): Cost of capital = 11% IRR = 13% Project L (low risk): Cost of capital = 7% IRR = 8% Note that the projects' costs of capital vary because the projects have...
Problem Walk-Through RESIDUAL DIVIDEND MODEL Walsh Company is considering three independent projects, each of which requires a $6 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Project M (medium risk): Project L (low risk): Cost of capital-17% Cost of capital-15% Cost of capital = 8% IRR 22% IRR-11% Note that the projects' costs of capital vary because the projects have different levels of risk. The...
Sandwich Company is considering five independent projects, each of the project will require a $10 million investment. The estimated IRR and cost of capital for these projects are presented as follows: Project A Cost of capital = 12% RR = 14% Project B Cost of capital = 14% IRR = 12% Project C Cost of capital = 8% IRR = 10% Project D Cost of capital = 9% IRR = 10% Project E Cost of capital = 16,5% IRR =...
RESIDUAL DIVIDEND MODEL Walsh Company is considering three independent projects, each of which requires a $6 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 15% IRR = 19% Project M (medium risk): Cost of capital = 13% IRR = 10% Project L (low risk): Cost of capital = 7% IRR = 9% Note that the projects' costs of capital vary because...
eBook Problem Walk-Through Walsh Company is considering three independent projects, each of which requires a $3 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 17% IRR = 22% Project M (medium risk): Cost of capital = 13% IRR = 11% Project L (low risk): Cost of capital = 8% IRR = 10% Note that the projects' costs of capital vary because...
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital -15% TRR - 22% Project M (medium risk): Cost of capital -11% IRR = 12% Project L (low risk): Cost of capital - 8% TRR = 7% Note that the projects' costs of capital vary because the projects have different levels...
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented below: Project H (High risk) Cost of capital = 15% IRR = 19% Project M (Medium risk) IRR 13% Cost of capital = 12% IRR 11% Cost of capital = 7% Project L (Low risk): Note that the projects' costs of capital vary because the projects have different levels...