Question

You have gathered the following information about a company you are analyzing: Expected net income for...

You have gathered the following information about a company you are analyzing:

  • Expected net income for the year is $3.0 million
  • The company’s current (and target) capital structure is 40 percent debt and 60 percent equity
  • The company’s cost of debt is 8 percent
  • The company’s cost of equity (and retained earnings) is estimated to be 13 percent
  • The company’s tax rate is 30 percent
  • The company is considering the following capital investment projects for the year (all projects have same risk as the firm):
    • Project 1 requires an investment of $1 million and has an IRR of 12 percent
    • Project 2 requires an investment of $1.2 million and has an IRR of 11.5 percent
    • Project 3 requires an investment of $1.2 million and has an IRR of 10.75 percent
    • Project 4 requires an investment of $1.5 million and has an IRR of 10.15 percent
    • Project 5 requires an investment of $1 million and has an IRR of 9.75 percent

If the company follows a residual dividend policy, what is the company’s payout ratio this year?

0 0
Add a comment Improve this question Transcribed image text
Answer #1
after tax cost of debt cost of debt*(1-tax rate) 8*(1-.3) 5.60%
cost of equity 13%
WACC =(weight of debt*after tax cost of debt)+(weight of equity*cost of equity) (.5*5.6%)+(.6*13%) 10.60%
Project Investment IRR of project WACC Accept if IRR> WACC and Reject if IRR<WACC
1 A 12% 10.60% Accept
2 B 11.50% 10.60% Accept
3 C 10.75% 10.60% Accept
4 D 10.15% 10.60% Reject
5 E 9.75% 10.60% Reject
total Investment required in three project 1+1.2+1.2 3.4
Amount required from equity in millions 3.4*60% 2.04
Amount required from debt in millions 3.4*40% 1.36
Amount of EBIT in millions 3
amount of equity financed from net income 2.04
amount of profit left for dividend 3-2.04 0.96
Payout ratio = amount left to declare dividend/ebit .96/3 32%
Add a comment
Know the answer?
Add Answer to:
You have gathered the following information about a company you are analyzing: Expected net income for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following information relates to Toronto Ltd: - Net income for the current year is $3...

    The following information relates to Toronto Ltd: - Net income for the current year is $3 million - The after-tax cost of debt is 4.88% - Target capital structure weightings are 30% debt, 20% preferred, with the remaining amount in equity - The weighted average cost of capital for the firm is 9% - Below is a list of possible capital projects and the company has $15 m of available funds: Project Name Project Size Project IRR YG $3.1 million...

  • Harris Company must set its investment and dividend policies for the coming year. It has three...

    Harris Company must set its investment and dividend policies for the coming year. It has three independent projects from which to choose, each of which requires a $5 million investment. These projects have different levels of risk, and therefore different costs of capital. Their projected IRRs and costs of capital are as follows: Project A: Cost of capital = 15%; IRR = 18% Project B: Cost of capital = 14%; IRR = 9% Project C: Cost of capital = 7%;...

  • Walsh Company is considering three independent projects, each of which requires a $4 million investment. The...

    Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 16% IRR = 18% Project M (medium risk): Cost of capital = 13% IRR = 12% Project L (low risk): Cost of capital = 7% IRR = 10% Note that the projects' costs of capital vary because the projects have...

  • Walsh Company is considering three independent projects, each of which requires a $4 million investment. The...

    Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 15% IRR = 22% Project M (medium risk): Cost of capital = 11% IRR = 13% Project L (low risk): Cost of capital = 7% IRR = 8% Note that the projects' costs of capital vary because the projects have...

  • Problem Walk-Through RESIDUAL DIVIDEND MODEL Walsh Company is considering three independent projects, each of which requires a $6 million investment. The estimated internal rate of return (IRR) and c...

    Problem Walk-Through RESIDUAL DIVIDEND MODEL Walsh Company is considering three independent projects, each of which requires a $6 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Project M (medium risk): Project L (low risk): Cost of capital-17% Cost of capital-15% Cost of capital = 8% IRR 22% IRR-11% Note that the projects' costs of capital vary because the projects have different levels of risk. The...

  • Sandwich Company is considering five independent projects, each of the project will require a $10 million...

    Sandwich Company is considering five independent projects, each of the project will require a $10 million investment. The estimated IRR and cost of capital for these projects are presented as follows: Project A Cost of capital = 12% RR = 14% Project B Cost of capital = 14% IRR = 12% Project C Cost of capital = 8% IRR = 10% Project D Cost of capital = 9% IRR = 10% Project E Cost of capital = 16,5% IRR =...

  • RESIDUAL DIVIDEND MODEL Walsh Company is considering three independent projects, each of which requires a $6...

    RESIDUAL DIVIDEND MODEL Walsh Company is considering three independent projects, each of which requires a $6 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 15% IRR = 19% Project M (medium risk): Cost of capital = 13% IRR = 10% Project L (low risk): Cost of capital = 7% IRR = 9% Note that the projects' costs of capital vary because...

  • eBook Problem Walk-Through Walsh Company is considering three independent projects, each of which requires a $3...

    eBook Problem Walk-Through Walsh Company is considering three independent projects, each of which requires a $3 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 17% IRR = 22% Project M (medium risk): Cost of capital = 13% IRR = 11% Project L (low risk): Cost of capital = 8% IRR = 10% Note that the projects' costs of capital vary because...

  • Walsh Company is considering three independent projects, each of which requires a $4 million investment. The...

    Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital -15% TRR - 22% Project M (medium risk): Cost of capital -11% IRR = 12% Project L (low risk): Cost of capital - 8% TRR = 7% Note that the projects' costs of capital vary because the projects have different levels...

  • Walsh Company is considering three independent projects, each of which requires a $4 million investment. The...

    Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented below: Project H (High risk) Cost of capital = 15% IRR = 19% Project M (Medium risk) IRR 13% Cost of capital = 12% IRR 11% Cost of capital = 7% Project L (Low risk): Note that the projects' costs of capital vary because the projects have different levels...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT