Question 10
Ans.:- 7.30 , 31.42
Question 11
Ans.:-
0, 44.18
Question 12
Control limits for R chart are given by
Lower control limit = 0
Upper control limit = 44.18
All the R points lies within the control limits of R chart so process is for R-Chart
Ans. in-Control
QUESTION 10 10)-12) A factory supervisor is concerned that the time it takes workers to complete...
2 10-12) A factory supervisor is concerned that the time it takes workers to complete an important production task (measured in seconds) is too erratic and adversely affects expected profits. The supervisor proceeds by randomly sampling 5 individuals per hour for a period of 10 hours. The sample mean and range for each hour are listed below. Hour x R 1 18.4 30 16.9 27 3 14.0 25 21.2. 25 5 21.0 24 33.0 19.3 8 15.8 9 20.0 12...
QUESTION 10 10)-12) A factory supervisor is concerned that the time it takes workers to complete an important production task (measured in seconds) is too erratic and adversely affects expected profits. The supervisor proceeds by randomly sampling 5 individuals per hour for a period of 10 hours. The sample mean and range for each hour are listed below. Hour X R 1 18.4 30 2 16.9 27 3 14.0 25 4 21.2 25 5 21.0 6 33.0 23 7 19.3...
1 QUESTION 11 10)-12) A factory supervisor is concerned that the time it takes workers to complete an important production task (measured in seconds) is too erratic and adversely affects expected profits. The supervisor proceeds by randomly sampling 5 individuals per hour for a period of 10 hours. The sample mean and range for each hour are listed below. Hour X R 18.4 30 2 16.9 27 3 14.0 25 4 21.2 25 5 21.0 24 6 33.0 23 7...
QUESTION 10 10-12) A factory supervisor is concerned that the time takes workers to complete an important production task measured in seconds) is too erratic and adversely affects expected profits. The supervisor proceeds by randomly sampling 5 individuals per hour for a period of 10 hours. The sample mean and range for each hour are listed below. Hou X 1 18.4 30 2 16.9 27 3 14.0 25 4 21.2 25 5 21.0 24 6 33.0 23 7 19.3 18...
A factory supervisor is concerned that the time it takes workers to complete an important production task (measured in seconds) is too erratic and adversely affects expected profits. The supervisor proceeds by randomly sampling 5 individuals per hour for a period of 10 hours. The sample mean and range for each hour are listed below. Hour R 1 18.4 30 2 16.9 27 3 14.0 25 4 21.2 25 5 21.0 24 6 33.0 23 7 19.3 18 8 15.8...
1 QUESTION 11 10)-12) A factory supervisor is concerned that the time it takes workers to complete an important production task (measured in seconds) is too erratic and adversely affects expected profits. The supervisor proceeds by randomly sampling 5 individuals per hour for a period of 10 hours. The sample mean and range for each hour are listed below. Hour X B 18.4 30 2 16.9 27 3 25 21.2 25 21.0 24 6 33.0 23 193 18 15.8 14...
QUESTION 11 10)-12) A factory supervisor is concerned that the time it takes workers to complete an important production task (measured in seconds) is too erratic and adversely affects expected profits. The supervisor proceeds by randomly sampling 5 individuals per hour for a period of 10 hours. The sample mean and range for each hour are listed below. Hour X R 1 18.4 30 2 16.9 27 3 14.0 25 4 21.2 25 5 21.0 24 6 33.0 23 7...
QUESTION 9 8)-9) A local newspaper has delivery boys who each deliver the morning paper to 50 customers every day. The owner decides to record the number of papers that is not delivered on time for a 8-day period and construct a p chart to see whether the percentage is too erratic. Day # of Papers Not Delivered on Time 1 4 2 5 3 4 4 5 5 7 6 2 7 4 8 4 Total: 35 Referring to...
Hello, I need help with the following question. I think that the answer is “Individual outliers” since the central line for X double bar is 20.26, LCL is 8.49 and UCL is 32.03. The range is 20.4. In my graph the majority of the points are outside the control limits. Please help me with this question. Thank you! TABLE Hour Mean of subgroup R (range) 1 18.4 25 2 16.9 27 3 23.0 30 4 21.2 23 5 21.0 24...
Hello, I need help with the following question. I think that the answer is “Individual outliers” since the central line for X bar is 58, LCL is 56.15 and UCL is 59.85. The range is 6.0. In my graph the majority of the points are outside the control limits. Please help me with this question. Thank you! TABLE Day Sample mean (in minutes) R (Range) 1 58.5 5.1 2 47.6 7.8 3 64.3 6.1 4 60.6 5.7 5 63.7 6.2...