Flow time is the cumulative Processing time
Job Tardiness = max (0, Flow Time - Due )
|
Job |
Processing Time |
Days Due from Today |
flow time |
Job Tardiness |
|
A |
16 |
24 |
16 |
0 |
|
B |
20 |
16 |
36 |
20 |
|
C |
22 |
40 |
58 |
18 |
|
D |
12 |
17 |
70 |
53 |
|
E |
10 |
18 |
80 |
62 |
|
80 |
260 |
153 |
Average Tardiness = 153/5 = 30.6 days
You have 5 jobs to process. If you process them in the current order, what will...
You have 5 jobs to process. What is the makespan if you do them in the current order? Job А B с D Processing Time Days Due from Today 16 24 20 16 22 40 12 17 10 18 70 83 79 89 80
What would be the sequence of the following jobs if you did them in Earliest Due Date sequence? Job A B Processing Time Days Due from Today 18 24 16 16 26 10 14 12 21 30 С D E OE,A,D,B,C E,D,A,C,B OC,D,B,A,E, C.B.D.A,E Question 6 (10 points) You have 5 jobs to do. What would be the sequence if you chose to do a Shortest Processing Time Approach? Job Processing Time Days Due from Today А 24 30 B...
Question 7 (10 points) What would be the sequence of the following jobs if you did them in Earliest Due Date sequence? Job Processing Time Days Due from Today 34 A 16 B 23 41 40 22 14 28 E 20 18 E,A,D,B,C E,D,A,C,B C,D,B,A,E C,B,D,A,E U Lu
make sure the answer is
correct 100%
Exercise 1: Suppose that 5 jobs will be processed on a single machine. The jobs are ready for processing at time. The other job characteristics are as shown in the table below. Find the: Mean flow time, Average tardiness and number of tardy jobs using: a. FCFS (30 Points) b. EDD (30 Points) Job Processing Time Due Date 10 20 B 20 30 С 4 10 D 16 24 E 6 8 F...
5. A work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D, and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days...
Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing time dispatching rule, in which order should the jobs be processed? Processing Time (days) Job due date (days) Job A B 4 C 11 D 8 5 8 O A. D, A, E, B, C О в. D. В. Е. А. С О С. С. А, Е, в.р O D. C, E, A, B, D O E. B, D, A,...
a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...
a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...
What would be the change in Average Tardiness if you performed the following five tasks using Earliest Delivery Date instead of completing them in the current sequence? Job Processing Time Days Due from Today Lowers average tardiness by 9.0 Lowers average tardiness by 6.6 Lowers average tardiness by 7.2 Lowers average tardiness by 11.6 Lowers average tardiness by 7.0
Question 20, Math problem
20. The Mowry Machine Shop still has five jobs to be pro- cessed as of 8 A.M. today (day 23) at its bottleneck opera- tion. The day when the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) Job А 11 10 22 10 8 В 13 8...