| Total Overheads of the Plant: | |||||
| Variable Overheads: | |||||
| Molding | (2500*1.40) | 3500 | |||
| Fabrication | (1500*2.20) | 3300 | |||
| Total Variable Overheads | 6,800 | ||||
| Fixed Overheads: | |||||
| Molding | 10,000 | ||||
| Fabrication | 15,000 | ||||
| Total Fixed overheads | 25,000 | ||||
| Total Overheads of the Plant: | 31,800 | ||||
| Divide: Total DLH | 4,000 | ||||
| Plantwide Oh rate per DLH | 7.95 | ||||
| Answer is $ 7.95 per DLH | |||||
I did (21,000+(2,500x1.40+1500x2.20))/4000 and i got $6.95 per MH, but apparently its wrong. Someone plese help....
For P i did (2,300)x(6.95)= 15,985
For q i did (1,700)x(6.95)= 11,815
and apparently its wrong, please help
data and questions relate to the month of March): Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing overhead per machine-hour Molding Fabrication Total 2,500 1,500 4, eee $19, eee $15, eee $25,000 $ 1.40 $ 2.20 Job P $13,000 $21,000 Job $8,000 $7,500 Direct materials Direct labor cost Actual machine-hours used: Molding Fabrication Total 1,700 600 2,380 800...
help me please
Required information The Foundational 15 (L02-1, LO2-2, LO2-3, LO2-4) (The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing overhead...
Required Information The Foundational 15 (LO2-1, LO2-2, LO2-3, LO2-4) [The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March-Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to...
8 Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March); Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing...
The Foundational 15 (LO2-1, LO2-2, LO2-3, LO2-4) [The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the...
5 Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments---Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing...
help please. I would appreciate it
Help Save & Exit Required information The Foundational 15 (LO2-1, LO2-2, LO2-3, LO2-4) (The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March Job P and Job Q. The following additional information is available for the company as a whole and...
Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing overhead per machine-hour Molding Fabrication Total 2,560 1,500 4,680 $10,000 $15,000 $25,000 $ 1.40 $ 2.20 Job P $13,000 $21,000 Job $8,000 $7,500 Direct materials Direct labor cost Actual machine-hours used: Molding Fabrication Total 1,700 600 2,300 900 1,700 Sweeten Company had no underapplied or overapplied manufacturing overhead costs during the month Required: For questions 1-8, assume that Sweeten Company uses a plantwide predetermined overhead rate with machine-hours...
help me please
Required information The Foundational 15 (LO2-1, LO2-2, LO2-3, LO2-4) (The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data...