Question

Boing Companies began operations on January 1, 2020. The company only has one client for whom...

Boing Companies began operations on January 1, 2020. The company only has one client for whom it is building an airplane at a price of $ 2,000,000. The costs incurred during 2020 and directly related to the construction of the aircraft were $ 375,000. The company estimates that the total costs required to complete construction is $ 1,125,000. The following is the partial financial statement of the Boing Company for 2020.

 

BOING COMPANIES

Statement of Financial Position

As of December 31, 2020

ASSETS:

 

 

Current assets:

 

 

Cash

 

$ 100,000

Accounts Receivable

 

 150,000

Inventory:

 

 

Construction in Progreso

 375,000

 

Construction in Progreso

(350,000)

  25,000

Other current assets

 

  225,000

 

 

 

Total Current Assets

 

$ 500,000

 

Based on the information provided, what method is Boing using to account for the construction contract?

Select one: a. Percentage of Completion

b. Can't determine

c. Term Sales

d. Contract Completed

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The mthod followed by the company is Percentage of completion method. Because inventory has been valued till the cost incurred till date

Add a comment
Know the answer?
Add Answer to:
Boing Companies began operations on January 1, 2020. The company only has one client for whom...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In 2020, Cement Inc. began a three year construction contract for $3,500,000. Cement uses the percentage-of-completion...

    In 2020, Cement Inc. began a three year construction contract for $3,500,000. Cement uses the percentage-of-completion method. The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract. The financial statement presentation relating to this contract for calendar 2020 follow: Statement of Financial Position Current Assests: Accounts receivable $150,000 Contract asset/liability 105,000 (Contract costs $425,000 less Billings of $320,000) Income Statement Income (before tax) on the contract recognized...

  • 1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport...

    1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Bridgeport’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. 2- Waterway, Inc. began work on a $7,071,000 contract in 2020 to construct an office building. Waterway...

  • Cheyenne Construction Company began work on a $424,000 construction contract in 2020. During 2020, Cheyenne incurred...

    Cheyenne Construction Company began work on a $424,000 construction contract in 2020. During 2020, Cheyenne incurred costs of $279,500, billed its customer for $204,500, and collected $170,500. At December 31, 2020, the estimated additional costs to complete the project total $150,500. Prepare Cheyenne’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. Cheyenne Construction Company began work on a $424.000 construction contract in 2020. During 2020, Cheyenne incurred costs of...

  • Coronado Construction Company began work on a $407,000 construction contract in 2020. During 2020, Coronado incurred...

    Coronado Construction Company began work on a $407,000 construction contract in 2020. During 2020, Coronado incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Coronado’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.

  • In 2010, Concrete Inc. began a three year construction contract for $3,500,000. Cement uses the percentage-of-completion...

    In 2010, Concrete Inc. began a three year construction contract for $3,500,000. Cement uses the percentage-of-completion method. The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract. The financial statement presentation relating to this contract for calendar 2010 follow: Statement of Financial Position Current Assets: Accounts receivable $150,000 Contract asset/liability 105,000 (Contract cost $425,000 less Billings of $320,000) Income Statement Income (before tax) on the contract recognized...

  • Vaughn Construction Company began work on a $423,000 construction contract in 2020. During 2020, Vaughn incurred...

    Vaughn Construction Company began work on a $423,000 construction contract in 2020. During 2020, Vaughn incurred costs of $295,500, billed its customer for $200,500, and collected $170,000. At December 31, 2020, the estimated additional costs to complete the project total $155,645. Prepare Vaughn’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...

  • Hamilton Construction Company uses the percentage-of-completion method of accounting. In 2020, Hamilton began work on the...

    Hamilton Construction Company uses the percentage-of-completion method of accounting. In 2020, Hamilton began work on the construction of a hospital, which provides for a contract price of $2,195,000. Other details follow: 20XO 20X1 Costs incurred during the year 637,600 1,000,000 Total estimated cost 1,594,000 1,637,600 Billings during the year 427,000 2,195,000 Collections during the year 343,000 1,509,000 What portion of the total contract price would be recognized as revenue in 20x0? 2,195,000 878,000 1,097,500 427,000 343,000

  • Indigo Construction Company began work on a $420,500 construction contract in 2020. During 2020, Indigo incurred...

    Indigo Construction Company began work on a $420,500 construction contract in 2020. During 2020, Indigo incurred costs of $299,000, billed its customer for $202,000, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $151,030. Prepare Indigo’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...

  • Splish Construction Company began work on a $402,000 construction contract in 2020. During 2020, Splish incurred...

    Splish Construction Company began work on a $402,000 construction contract in 2020. During 2020, Splish incurred costs of $252,000, billed its customer for $210,500, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $162,405. Prepare Splish’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...

  • Splish Construction Company began work on a $418,500 construction contract in 2020. During 2020, Splish incurred...

    Splish Construction Company began work on a $418,500 construction contract in 2020. During 2020, Splish incurred costs of $285,500, billed its customer for $233,000, and collected $172,000. At December 31, 2020, the estimated additional costs to complete the project total $155,765. Prepare Splish’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT