Question

During 2020 the Tonka Corp. began construction for which it will invoice a total of $...

During 2020 the Tonka Corp. began construction for which it will invoice a total of $ 600,000. The project ended on December 15, 2021. Additional information related to this project is presented below:

 

2020

2021

Costs incurred in the period

$ 225,000

$ 255,000

Estimated costs to complete the project

225,000

-0-

Customer billing

240,000

360,000

Cash Received from Clients

200,000

400,000

Assuming Tonka uses the CONTRACT COMPLETED method, what will be the gross profit reported in the 2020 Statement of Income and Expenses related to this project?
Select one:
a. $ 75,000
b. $ 345,000
c. $ 0
d. $ 120,000
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Tonka uses the CONTRACT COMPLETED method, the gross profit will be reported in the 2020 Statement of Income

and Expenses related to this project will be $ 0 because under completed contract method, Revenue is recognized in

the year of completion only & gross profit will be reported at the same time.

Correct answer is option C .
Add a comment
Know the answer?
Add Answer to:
During 2020 the Tonka Corp. began construction for which it will invoice a total of $...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Cheyenne Construction Company began work on a $424,000 construction contract in 2020. During 2020, Cheyenne incurred...

    Cheyenne Construction Company began work on a $424,000 construction contract in 2020. During 2020, Cheyenne incurred costs of $279,500, billed its customer for $204,500, and collected $170,500. At December 31, 2020, the estimated additional costs to complete the project total $150,500. Prepare Cheyenne’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. Cheyenne Construction Company began work on a $424.000 construction contract in 2020. During 2020, Cheyenne incurred costs of...

  • Coronado Construction Company began work on a $407,000 construction contract in 2020. During 2020, Coronado incurred...

    Coronado Construction Company began work on a $407,000 construction contract in 2020. During 2020, Coronado incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Coronado’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.

  • 1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport...

    1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Bridgeport’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. 2- Waterway, Inc. began work on a $7,071,000 contract in 2020 to construct an office building. Waterway...

  • Vaughn Construction Company began work on a $423,000 construction contract in 2020. During 2020, Vaughn incurred...

    Vaughn Construction Company began work on a $423,000 construction contract in 2020. During 2020, Vaughn incurred costs of $295,500, billed its customer for $200,500, and collected $170,000. At December 31, 2020, the estimated additional costs to complete the project total $155,645. Prepare Vaughn’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...

  • Indigo Construction Company began work on a $420,500 construction contract in 2020. During 2020, Indigo incurred...

    Indigo Construction Company began work on a $420,500 construction contract in 2020. During 2020, Indigo incurred costs of $299,000, billed its customer for $202,000, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $151,030. Prepare Indigo’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...

  • Cady Construction received a contract to construct a hospital for $2,500,000. Construction began in 2019 and...

    Cady Construction received a contract to construct a hospital for $2,500,000. Construction began in 2019 and ended in 2020. Cost and other data are presented below: 2019 2020 Costs incurred during the year $1,500,000 $1,300,000 Estimated costs to complete 1,200,000 0 Billings during the year 1,200,000 1,300,000 Cash collections during the year 1,000,000 1,500,000 What is gross profit recognized during 2020 if Cady recognizes revenue over time according to percentage of completion? a. $100,000 b. $200,000 c. ($200,000) d. $0...

  • * (Long-Term Contract with an Overall Loss) On June 1, 2020, Roman Construction Company Inc. contracted...

    * (Long-Term Contract with an Overall Loss) On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022:...

  • Splish Construction Company began work on a $402,000 construction contract in 2020. During 2020, Splish incurred...

    Splish Construction Company began work on a $402,000 construction contract in 2020. During 2020, Splish incurred costs of $252,000, billed its customer for $210,500, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $162,405. Prepare Splish’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...

  • n 2021, Short Construction began construction work under a four-year contract. The contract price is $2,000,000....

    n 2021, Short Construction began construction work under a four-year contract. The contract price is $2,000,000. Short recognizes revenue over time according to percentage of completion method. The balance sheet shows the following accounts at the end of 2021: A/R of $40,000, Construction in Progress of $200,000, Less: Billings on Construction Contract of $170,000. The income statement shows Income on the contract of $30,000 at the end of 2021. What was the total estimated cost of the project at the...

  • Hollywood Construction Company recognizes revenue over time according to percentage of completion for its long term...

    Hollywood Construction Company recognizes revenue over time according to percentage of completion for its long term construction contracts. During 2018 Hollywood began work on a $3,000,000 foed-fee construction contract which was completed in 2021. The accounting records disclosed the following data at year-end: Estimated costs to complete at end of year $1,800,000 1,100,000 400,000 Cumulative contract costs incurred S 200,000 1,100,000 2,000,000 2018 2019 2020 For the 2020 year, Hollywood should have recognized gross profit on this contract of

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT