Solution 1:
| Invoice price | 12800 |
| Less: Discount | -256 |
| Net Purchase price | 12544 |
| Transportation cost | 289 |
| Mounting and power connections | 885 |
| Assembly cost | 417 |
| Material used in adjusting | 40 |
| Total cost to be recorded | 14175 |
Solution 2:
| Transaction | General Journal | Debit | Credit |
| 1 | Land | 386287 | |
| Building | 1774300 | ||
| Land Improvements | 111999 | ||
| Cash | 2272586 |
Working:
| Cost of Land | |
| Purchase price of Land | 305000 |
| Tear Down Cost of Old building | 32800 |
| Cost to Fill and level the lot | 48487 |
| Total cost of Land | 386287 |
| Cost of Building | |
| Construction cost of new building | 1774300 |
| Cost of Land Improvements | |
| Construction cost of parking area | 111999 |
Rizio Co. purchases a machine for $12,800, terms 2/10, n/60, FOB shipping point. Rizio paid within...
Rizio Co. purchases a machine for $10,900, terms 2/10, n/60, FOB shipping point. Rizio paid within the discount period and took the $218 discount. Transportation costs of $246 were paid by Rizio. The machine required mounting and power connections costing $754. Another $355 is paid to assemble the machine and $40 of materials are used to get it into operation. During installation, the machine was damaged and $225 worth of repairs were made. Complete the below table to calculate the...
Rizio Co. purchases a machine for $14,900, terms 2/10, n/60, FOB shipping point. Rizio paid within the discount period and took the $298 discount. Transportation costs of $337 were paid by Rizio. The machine required mounting and power connections costing $1,030. Another $486 is paid to assemble the machine and $40 of materials are used to get it into operation. During installation, the machine was damaged and $375 worth of repairs were made. Complete the below table to calculate the...
Rizio Co. purchases a machine for $11,600, terms 2/10,n/60, FOB shipping point. Rizio paid within the discount period and took the $232 discount. Transportation costs of $262 were paid by Rizio. The machine required mounting and power connections costing $802. Another $378 is paid to assemble the machine and $40 of materials are used to get it into operation. During installation, the machine was damaged and $370 worth of repairs were made. Complete the below table to calculate the cost...
Rizio Co purchases a machine for $12,500, terms 2/10,n/60, FOB shipping point. Rizio paid within the discount period and took the $250 discount. Transportation costs of $360 were paid by Rizio. The machine required mounting and power connections costing $895 Another $475 is paid to assemble the machine and $40 of materials are used to get it into operation. During installation, the machine was damaged and $180 worth of repairs were made. Complete the below table to calculate the cost...
Rizio Co. purchases a machine for $13,900, terms 1/10, n/60, FOB shipping point. Rizio paid within the discount period and took the $139 discount. Transportation costs of $314 were paid by Rizio. The machine required mounting and power connections costing $961. Another $453 is paid to assemble the machine and $40 of materials are used to get it into operation. During installation, the machine was damaged and $315 worth of repairs were made points Complete the below table to calculate...
Rizio Co. purchases a machine for $11,500, terms 1/10, n/60, FOB shipping point. Rizidpaid within the discount period and took the $115 discount. Transportation costs of $260 were paid by Rizio. The machine required mounting and power connections costing $795. Another $375 is paid to assemble the machine and $40 of materials are used to get it into operation. During installation, the machine was damaged and $350 worth of repairs were made. Complete the below table to calculate the cost...
10 Rizio Co. purchases a machine for $13,600, terms 2/10, n/60, FOB shipping point. The seller prepaid the $307 freight charges, adding the amount to the invoice and bringing its total to $13.907. The machine requires special steel mounting and power connections costing $940. Another $443 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting $260 in damages occurred. Materials costing $40 are used in adjusting the machine to produce...
Rizio Co. purchases a machine for $12,200, terms 2/10, n/60, FOB shipping point. The seller prepaid the $276 freight charges, adding the amount to the invoice and bringing its total to $12,476. The machine requires special steel mounting and power connections costing $843. Another $398 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting, $285 in damages occurred. Materials costing $40 are used in adjusting the machine to produce a...
Rizio Co. purchases a machine for $9,800, terms 1/10, n/60, FOB shipping point. The seller prepaid the $221 freight charges, adding the amount to the invoice and bringing its total to $10,021. The machine requires special steel mounting and power connections costing $677. Another $319 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting, $305 in damages occurred. Materials costing $40 are used in adjusting the machine to produce a...
Rizio Co. purchases a machine for $14,300, terms 1/10, n/60, FOB
shipping point. The seller prepaid the $323 freight charges, adding
the amount to the invoice and bringing its total to $14,623. The
machine requires special steel mounting and power connections
costing $989. Another $466 is paid to assemble the machine and get
it into operation. In moving the machine to its steel mounting,
$350 in damages occurred. Materials costing $40 are used in
adjusting the machine to produce a...