NPV is calculated as PV of cash inflows minus initial investment
NPV = CF1 / (1 + R)^1 + CF2 / (1 + R)^2 + CF3 / (1 + R)^3 - CF0
When I = 0%
NPV = 7100 / (1 + 0%)^1 + 8400 / (1 + 0%)^2 + 6900 / (1 + 0%)^3 - 16400
= 6000
When I = 10%
NPV = 7100 / (1 + 10%)^1 + 8400 / (1 + 10%)^2 + 6900 / (1 + 10%)^3 - 16400
= 2180.77
When I = 20%
NPV = 7100 / (1 + 20%)^1 + 8400 / (1 + 20%)^2 + 6900 / (1 + 20%)^3 - 16400
= - 656.94
When I = 30%
NPV = 7100 / (1 + 30%)^1 + 8400 / (1 + 30%)^2 + 6900 / (1 + 30%)^3 - 16400
= -2827.40
ollowing cash flows: 0 1 2 3 a) What is the NPV at a discount rate...
A project has the following cash flows: Year Cash Flows 0 $-16,200 1 $6,900 2 $8,200 3 $6,700 a) What is the NPV at a discount rate of zero percent? b) What is the NPV at a discount rate of 10 percent? c) What is the NPV at a discount rate of 20 percent? d) What is the NPV at a discount rate of 30 percent?
b) A project has the following cash flows: Year 0 1 2 Cash Flow -$16,400 7.100 8,400 6.900 3 a) What is the NPV at a discount rate of 0%? b) What is the NPV at a discount rate of 10%? c) What is the NPV at a discount rate of 20%? d) What is the NPV at a discount rate of 30%?
What is the NPV of the following cash flows at a discount rate of zero percent? What if the discount rate is 10 percent? If it is 20 percent? If it is 30 percent? (13,900) Year 0 Year 1 6,400 $ Year 2 8,700 Year 3 5,900 Discount rate 0% 10% Discount rate Discount rate 20% 30% Discount rate Complete the following analysis. Do not hard code values in your calculations. You must use the built-in Excel function to answer...
P9-11 Calculating NPV [LO1] For the following set of cash flows, Year Cash Flow 0 –$7,000 1 6,900 2 5,200 3 5,500 Required: (a) What is the NPV at a discount rate of 0 percent? (b) What is the NPV at a discount rate of 13 percent? (c) What is the NPV at a discount rate of 20 percent? (d) What is the NPV at a discount rate of 25 percent?
Consider the following cash flows: Year Cash Flow 0 –$ 19,400 1 10,400 2 9,320 3 6,900 a. What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. What is the NPV at a discount rate of 10 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) c. What is the NPV at a discount rate...
For the following set of cash flows, Year Cash Flow 0 –$8,400 1 3,600 2 4,900 3 6,200 a. What is the NPV at a discount rate of 0 percent? b. What is the NPV at a discount rate of 8 percent? c. What is the NPV at a discount rate of 18 percent? d. What is the NPV at a discount rate of 23 percent?
What is the discount rate at which the following cash flows have a NPV of $0? Answer in %, rounding to 2 decimals. Year 0 cash flow = -106,000 Year 1 cash flow = 34,000 Year 2 cash flow = 37,000 Year 3 cash flow = 29,000 Year 4 cash flow = 43,000 Year 5 cash flow = 38,000 Year 6 cash flow = 33,000
What is the discount rate at which the following cash flows have a NPV of $0? Answer in %, rounding to 2 decimals. Year 0 cash flow = -160,000 Year 1 cash flow = 45,000 Year 2 cash flow = 31,000 Year 3 cash flow = 34,000 Year 4 cash flow = 30,000 Year 5 cash flow = 33,000 Year 6 cash flow = 38,000
What is the discount rate at which the following cash flows have a NPV of $0? Answer in %, rounding to 2 decimals. Year 0 cash flow = -133,000 Year 1 cash flow = 34,000 Year 2 cash flow = 40,000 Year 3 cash flow = 33,000 Year 4 cash flow = 41,000 Year 5 cash flow = 33,000 Year 6 cash flow = 45,000
What is the NPV of a project with the following cash flows and a discount rate of 12% Initial Investment (1,000,000) Cash Flow Year 1 400,000 Year 2 300,000 Year 3 400,000 Year 4 200,000