JOD NO. 469 Item: White Lion Cages For: Zawadi Company 2,000 Date Requested: 7/2 Date Completed: 7/31 Manufacturing Overhead
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Job Cost sheet

Cost of completed Jobs
Direct material 5026
Direct labor 1270
Manufacturing overhead 1524
Total Cost 7820
Unit cost (7820/2000) 3.91

Predetermine overhead rate = 600/500 = 120% of labor cost

Add a comment
Know the answer?
Add Answer to:
could someone please explain how to do this one JOD NO. 469 Item: White Lion Cages...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Job Cost Sheet |JОB NO. 469 Quantity 2,000 White Lion Cages Date Requested ITEM 7/2 Todd...

    Job Cost Sheet |JОB NO. 469 Quantity 2,000 White Lion Cages Date Requested ITEM 7/2 Todd Company Date Completed 7/31 FOR Manufacturing Direct Direct Materials Labor Overhead Date 7/10 700 12 900 600 15 500 22 300 360 24 1,720 27 1,580 840 31 700 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost (a) Answer the following questions. (1) What are the source documents for direct materials, direct labor, and manufacturing overhead costs assigned...

  • JOB NO. ITEM Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date...

    JOB NO. ITEM Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 2.500 7/2 7/31 Manufacturing Overhead FOR Date 7/10 700 900 600 750 500 400 1,650 1,500 500 625 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Answer the following questions. (1) What are the source documents for direct materials, direct labor, and manufacturing overhead costs assigned to this job? Source Documents Direct materials...

  • Calculate the predetermined manufacturing overhead rate. A job cost sheet of Nilson Company is given below....

    Calculate the predetermined manufacturing overhead rate. A job cost sheet of Nilson Company is given below. Job Cost Sheet Job No. 469 Item: White Lion Cages For: Zawadi Company Quantity: 2,000 Date Requested: 7/2 Date Completed: 7/31 Manufacturing Overhead Direct Labour Date 7/10 12 Direct Materials $800 930 15 $490 350 $539 385 22 24 1,640 1,535 27 31 510 561 Cost of completed job: Direct materials Direct labour Manufacturing overhead Total cost Unit cost

  • JOB NO. ITEM FOR 2.390 7/2 7/31 Manufacturing Overhead Date 7/10 Job Cost Sheet 469 Quantity...

    JOB NO. ITEM FOR 2.390 7/2 7/31 Manufacturing Overhead Date 7/10 Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 708 907 558 342 1,620 1,530 670 692 424 831 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Answer the following questions. (1) What are the source documents for direct materials, direct labor, and manufacturing overhead costs assigned to this job? Source Documents Direct materials...

  • A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469...

    A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469 Quantity 2,500 White Lion Cages Date Requested ITEM 7/2 Todd Company FOR Date Completed 7/31 Manufacturing Overhead Direct Direct Date Materials Labor 700 7/10 12 900 15 400 500 22 300 375 24 1,700 27 1,550 31 500 625 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost *(a) Answer the following questions. (1) What are the source documents...

  • A job cost sheet of Ivanhoe Company is given below. JOB NO. 469 Job Cost Sheet...

    A job cost sheet of Ivanhoe Company is given below. JOB NO. 469 Job Cost Sheet Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor FOR 2.500 7/2 7/31 Manufacturing Overhead Date 7/10 700 900 400 1,675 1,575 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Your answer is partially correct. Try again. Answer the following questions. (1) What are the source documents for direct materials, direct labor, and...

  • A job cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR Job Cost...

    A job cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 2,500 7/2 7/31 Manufacturing Overhead Date 7/10 700 900 12 15 400 400 500 500 22 24 1,625 1,525 27 31 500 625 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost (a) Answer the following questions. (1) What are the source documents...

  • Ajob cost sheet of Sunland Company is given below. JOB NO. ITEM FOR 2.500 7/2 7/31...

    Ajob cost sheet of Sunland Company is given below. JOB NO. ITEM FOR 2.500 7/2 7/31 Manufacturing Overhead Date 7/10 12 15 22 24 27 31 Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor $700 900 $400 300 1,700 1,500 500 $500 375 625 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Answer the following questions. (a) What are the source documents for direct...

  • CES Exercise 2-6 (Video) (Part Level Submission) A job cost sheet of Sandoval Company is given...

    CES Exercise 2-6 (Video) (Part Level Submission) A job cost sheet of Sandoval Company is given below. vel 2.000 JOB NO. ITEM FOR Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 7/2 7/31 Manufacturing Overhead on) Date 7/10 700 900 500 300 600 360 udy. 1,640 1,600 700 840 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost (a) Answer the following questions. (1) What...

  • Ajob cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR 2.500 7/2 7/31...

    Ajob cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR 2.500 7/2 7/31 Manufacturing Overhead Date 7/10 Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 700 900 600 300 1,625 1,525 700 12 750 15 22 24 375 27 31 875 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Answer the following questions. (1) What are the source documents for direct...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT