Question

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,975,000 $ 3,825,000 $ 1,870,000
Estimated costs to complete as of year-end 5,525,000 1,700,000 0
Billings during the year 2,500,000 4,300,000 3,200,000
Cash collections during the year 2,300,000 4,100,000 3,600,000


Assume that Westgate Construction’s contract with Santa Clara County does not qualify for revenue recognition over time.

Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).
3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract.
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

2021 2022 2023
Cost incurred during the year $ 2,450,000 $ 3,825,000 $ 3,250,000
Estimated costs to complete as of year-end 5,650,000 3,150,000 0


5.
Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

2021 2022 2023
Cost incurred during the year $ 2,450,000 $ 3,825,000 $ 3,975,000
Estimated costs to complete as of year-end 5,650,000 4,150,000 0

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000

Check my work mode: This shows what is correct or incorrect for the work you have completed so far. It does not indicate comp

Complete this question by entering your answers in the tabs below. Reg1 Req ZA Reg 20 Rey 2c Req3 Rega Reg In the Journal bel

Reg 1 Req 2A Reg 28 Req 2c Req3 Reg 4 Regs Complete the information required below to prepare a partial balance sheet for 202

Complete this question by entering your answers in the tabs below. Reg 1 Req 2A Reg 26 Reg Reg 3 Reg4 Req5 Calculate the amou

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

1 For 2021 Amount ($)
Revenue recognised = 0
Gross Profit = 0
For 2022
Revenue recognised = 0
Gross Profit = 0
For 2023
Revenue recognised = $10,000,000
Gross Profit :-
Contract Price = $10,000,000
Less: Cost incurred = $8,670,000
(2975000 + 3825000 + 1870000)
Gross Profit recognised = $1,330,000
Note:
As per completed contract method, Gross profit is recognised in the year of completion of contract
But losses will be recognised when the cost incurred & estimated cost exceeds contract price.
2-a Journal Entries - 2021
Year Particulars Debit ($) Credit ($)
2021 Construction in progress Dr. 2975000
To Various accounts 2975000
(To record cost incurred)
Accounts receivable Dr. 2500000
To Billings on construction contract 2500000
(To record billings made during the year)
Cash A/c Dr. 2300000
To Accounts receivable 2300000
(To record cash received from customers)
2-b Journal Entries - 2022
Year Particulars Debit ($) Credit ($)
2022 Construction in progress Dr. 3825000
To Various accounts 3825000
(To record cost incurred)
Accounts receivable Dr. 4300000
To Billings on construction contract 4300000
(To record billings made during the year)
Cash A/c Dr. 4100000
To Accounts receivable 4100000
(To record cash received from customers)
2-c Journal Entries - 2023
Year Particulars Debit ($) Credit ($)
2023 Construction in progress Dr. 1870000
To Various accounts 1870000
(To record cost incurred)
Accounts receivable Dr. 3200000
To Billings on construction contract 3200000
(To record billings made during the year)
Cash A/c Dr. 3600000
To Accounts receivable 3600000
(To record cash received from customers)
Westgate Construction Company
3. Balance Sheet (Partial)
Particulars 2021 2022
Current assets:
Accounts receivable $200,000 $400,000
Construction in progress $2,975,000 $6,800,000
Less: Bllings $2,500,000 $6,800,000
$475,000 $0
Current Liabilities:
Billings in excess of costs $0 $0
4 For 2021 Amount ($)
Revenue recognised = 0
Gross Profit = 0
For 2022
Revenue recognised = 0
Gross Profit = 0
For 2023
Revenue recognised = $10,000,000
Gross Profit :-
Contract Price = $ 10,000,000
Less: Cost incurred = $9,525,000
(2450000 + 3825000 + 3250000)
Gross Profit recognised = $ 475,000
5 For 2021

Amount ($)

Revenue recognised = 0
Gross Profit = 0
For 2022
Revenue recognised = 0
Gross Profit = 0
For 2023
Revenue recognised = $10,000,000
Gross Profit :-
Contract Price = $ 10,000,000
Less: Cost incurred = $10,250,000
(2450000 + 3825000 + 3975000)
Gross Profit recognised = $ (250,000)
Add a comment
Know the answer?
Add Answer to:
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 2023 $2,200,000 0 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,849, eee Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,072,00 5,328,000 2,160, eee 1,880, eee 2022 $2,738,000 2,590,000 2,650, eee 2,700,eee 5,190, eee 5,420, eee Westgate recognizes revenue over time...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2823 $2,475,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $1,875, eee 5.625.000 1,5ee,eee 1,3ee,eee 2022 $3,375,000 2.25e,eee 3,75e,eee 3,100,eee 4,750,000 5,600,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,200,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does not...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $1,797,400 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $3,096,000 5,504,000 2,600,000 2,400,000 2022 $3,870,000 1,634,000 4,366,000 4,200,000 8 0247:45 3,034,000 3,400,000 Skipped Assume that Westgate Construction's contract with Santa...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: during the year $2,100,000 $2,450,000 $2,695,000 Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,900,000 2,450,000 2,200,000 2,350,000 5,450,000 1,900,000 2,300,000 5, 800,000 3 28 Westgate recognizes revenue over time according to percentage of completion Required: ances 1....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT