In 2021, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to
the contract is as follows:
| 2021 | 2022 | 2023 | |||||||||
| Cost incurred during the year | $ | 2,975,000 | $ | 3,825,000 | $ | 1,870,000 | |||||
| Estimated costs to complete as of year-end | 5,525,000 | 1,700,000 | 0 | ||||||||
| Billings during the year | 2,500,000 | 4,300,000 | 3,200,000 | ||||||||
| Cash collections during the year | 2,300,000 | 4,100,000 | 3,600,000 | ||||||||
Assume that Westgate Construction’s contract with Santa Clara
County does not qualify for revenue recognition over time.
Required:
1. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary
journal entries for the year 2021 (credit "Various accounts" for
construction costs incurred).
2-b. In the journal below, complete the necessary
journal entries for the year 2022 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2023 (credit "Various accounts" for
construction costs incurred).
3. Complete the information required below to
prepare a partial balance sheet for 2021 and 2022 showing any items
related to the contract.
4. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete information.
| 2021 | 2022 | 2023 | |||||||||
| Cost incurred during the year | $ | 2,450,000 | $ | 3,825,000 | $ | 3,250,000 | |||||
| Estimated costs to complete as of year-end | 5,650,000 | 3,150,000 | 0 | ||||||||
5. Calculate the amount of revenue and gross profit (loss)
to be recognized in each of the three years assuming the following
costs incurred and costs to complete information.
| 2021 | 2022 | 2023 | |||||||||
| Cost incurred during the year | $ | 2,450,000 | $ | 3,825,000 | $ | 3,975,000 | |||||
| Estimated costs to complete as of year-end | 5,650,000 | 4,150,000 | 0 | ||||||||





Answer
| 1 | For 2021 | Amount ($) |
| Revenue recognised = | 0 | |
| Gross Profit = | 0 | |
| For 2022 | ||
| Revenue recognised = | 0 | |
| Gross Profit = | 0 | |
| For 2023 | ||
| Revenue recognised = | $10,000,000 | |
| Gross Profit :- | ||
| Contract Price = | $10,000,000 | |
| Less: Cost incurred = | $8,670,000 | |
| (2975000 + 3825000 + 1870000) | ||
| Gross Profit recognised = | $1,330,000 |
| Note: |
| As per completed contract method, Gross profit is recognised in the year of completion of contract |
| But losses will be recognised when the cost incurred & estimated cost exceeds contract price. |
| 2-a | Journal Entries - 2021 | ||
| Year | Particulars | Debit ($) | Credit ($) |
| 2021 | Construction in progress Dr. | 2975000 | |
| To Various accounts | 2975000 | ||
| (To record cost incurred) | |||
| Accounts receivable Dr. | 2500000 | ||
| To Billings on construction contract | 2500000 | ||
| (To record billings made during the year) | |||
| Cash A/c Dr. | 2300000 | ||
| To Accounts receivable | 2300000 | ||
| (To record cash received from customers) | |||
| 2-b | Journal Entries - 2022 | ||
| Year | Particulars | Debit ($) | Credit ($) |
| 2022 | Construction in progress Dr. | 3825000 | |
| To Various accounts | 3825000 | ||
| (To record cost incurred) | |||
| Accounts receivable Dr. | 4300000 | ||
| To Billings on construction contract | 4300000 | ||
| (To record billings made during the year) | |||
| Cash A/c Dr. | 4100000 | ||
| To Accounts receivable | 4100000 | ||
| (To record cash received from customers) | |||
| 2-c | Journal Entries - 2023 | ||
| Year | Particulars | Debit ($) | Credit ($) |
| 2023 | Construction in progress Dr. | 1870000 | |
| To Various accounts | 1870000 | ||
| (To record cost incurred) | |||
| Accounts receivable Dr. | 3200000 | ||
| To Billings on construction contract | 3200000 | ||
| (To record billings made during the year) | |||
| Cash A/c Dr. | 3600000 | ||
| To Accounts receivable | 3600000 | ||
| (To record cash received from customers) | |||
| Westgate Construction Company | ||||
| 3. Balance Sheet (Partial) | ||||
| Particulars | 2021 | 2022 | ||
| Current assets: | ||||
| Accounts receivable | $200,000 | $400,000 | ||
| Construction in progress | $2,975,000 | $6,800,000 | ||
| Less: Bllings | $2,500,000 | $6,800,000 | ||
| $475,000 | $0 | |||
| Current Liabilities: | ||||
| Billings in excess of costs | $0 | $0 |
| 4 | For 2021 | Amount ($) |
| Revenue recognised = | 0 | |
| Gross Profit = | 0 | |
| For 2022 | ||
| Revenue recognised = | 0 | |
| Gross Profit = | 0 | |
| For 2023 | ||
| Revenue recognised = | $10,000,000 | |
| Gross Profit :- | ||
| Contract Price = | $ 10,000,000 | |
| Less: Cost incurred = | $9,525,000 | |
| (2450000 + 3825000 + 3250000) | ||
| Gross Profit recognised = | $ 475,000 | |
| 5 | For 2021 |
Amount ($) |
| Revenue recognised = | 0 | |
| Gross Profit = | 0 | |
| For 2022 | ||
| Revenue recognised = | 0 | |
| Gross Profit = | 0 | |
| For 2023 | ||
| Revenue recognised = | $10,000,000 | |
| Gross Profit :- | ||
| Contract Price = | $ 10,000,000 | |
| Less: Cost incurred = | $10,250,000 | |
| (2450000 + 3825000 + 3975000) | ||
| Gross Profit recognised = | $ (250,000) |
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to
the contract is as follows: 2021 2022 2023 Cost incurred during the
year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to
complete as of year-end 5,616,000 2,376,000 0 Billings during the
year 1,200,000 3,624,000 5,176,000 Cash collections during the year
1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s
contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 2023 $2,200,000 0 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,849, eee Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,072,00 5,328,000 2,160, eee 1,880, eee 2022 $2,738,000 2,590,000 2,650, eee 2,700,eee 5,190, eee 5,420, eee Westgate recognizes revenue over time...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2823 $2,475,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $1,875, eee 5.625.000 1,5ee,eee 1,3ee,eee 2022 $3,375,000 2.25e,eee 3,75e,eee 3,100,eee 4,750,000 5,600,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,200,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does not...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $1,797,400 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $3,096,000 5,504,000 2,600,000 2,400,000 2022 $3,870,000 1,634,000 4,366,000 4,200,000 8 0247:45 3,034,000 3,400,000 Skipped Assume that Westgate Construction's contract with Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: during the year $2,100,000 $2,450,000 $2,695,000 Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,900,000 2,450,000 2,200,000 2,350,000 5,450,000 1,900,000 2,300,000 5, 800,000 3 28 Westgate recognizes revenue over time according to percentage of completion Required: ances 1....