Calculation of Revenue and Gross Profit to be
recognised
| 2021 | 2022 | 2023 | |
| Revenue | 2900000 | 3700000 | 3400000 |
| Gross Profit | 841000 | 1073000 | 744600 |
Year 2021
Estimated Total Costs = Cost incurred till date +Estimated cost to complete
Estimated Total Costs = 2059000 +5041000 =7100000
% of completion =2059000/7100000*100 =29%
Revenue =10000000*29% =$2900000
Gross Profit =Revenue - Cost incurred
Gross Profit =2900000 -2059000 =$841000
Year 2022
Estimated Total Costs = Cost incurred till date +Estimated cost to complete
Estimated Total Costs =2059000+ 2627000 + 2414000=$7100000
% of completion =(2059000+2627000)/7100000*100 =66%
Revenue =10000000*66%=$6600000
but $2900000 already recognised in 2021. Hence Revenue recognised
in 2022 will be =6600000-2900000=$3700000
Gross Profit =3700000 -2627000 =$1073000
Year 2023
Estimated Total Costs = Cost incurred till date +Estimated cost to complete
Estimated Total Costs =2059000+2627000+2655400+0 =$7341400
% of Completion =7341400/7341400*100 =100%
Revenue =10000000*100%=$10000000 but $6600000 already recognised in 2021. Hence Revenue recognised in 2023 will be =10000000-6600000=$3400000
Gross Profit = 3400000 -2655400 =$744600
Check my work 5 Required information [The following information applies to the questions displayed below.] Part...
Check my work 8 ! Required information [The following information applies to the questions displayed below.] Part 4 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 6 points 2023 $2,655,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021...
Check my work 9 [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: art 5 of 5 2023 $2,655,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,059,000 5,041,000 2,190,000 1,895,000 2022...
My answers are right!! please help on the 2 blank ones!
Required information [The following information applies to the questions displayed below) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,655,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021...
What is the revenue and gross profit?
Required information (The following information applies to the questions displayed below.) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: ear-end Cost incurred during the year Estimated costs to complete as o Billings during the year Cash collections during the year 2018 $2,059,000 5,041,000 2,190,000 1,895,000 2019 $2,627,000...
pleass help on wrong answers!!!
Required information The following information applies to the questions displayed below) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,655,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,059,000 5,041,000 2,190,000 1,895,000 2022 $2,627,000...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: $2,655,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,059,000 5.041.000 2,190,000 1,895,000 2022 $2,627,000 2,414,000 2,496,000 2,400,000 5,314,000 5.705.000 Westgate recognizes revenue over time according to percentage of completion 4. Calculate...
Check my work mode: This shows what is correct or incorrect for the work you have completed so far. It does not Increate completion. Return to question Required information [The following information applies to the questions displayed below.) Part 4 of In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,655 400 Coat incurred...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,059,000 $ 2,627,000 $ 2,655,400 Estimated costs to complete as of year-end 5,041,000 2,414,000 0 Billings during the year 2,190,000 2,496,000 5,314,000 Cash collections during the year 1,895,000 2,400,000 5,705,000 Westgate recognizes revenue over time according to...
5 Required information (The following information applies to the questions displayed below.) Part 1 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: - 2023 $2,926,000 10 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000...
8 Required information (The following information applies to the questions displayed below.) Part 4 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 10 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000 1,840,000 2022 $2,300,000...