Question

Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies facto
C. Journalize the entries to apply factory overhead to production in each factory for March. Factory 1 Factory 2 d. Determine
0 0
Add a comment Improve this question Transcribed image text
Answer #1

a.

Factory overhead rate for factory 1 = Estimated factory overhead cost / Estimated machine hours

= 368,600/18,430

= $20 per machine hour

b.

Factory overhead rate for factory 2 = Estimated factory overhead cost / Estimated direct labor hours

= 999,600/ 14,700

= $68 per direct labor hour

c.

Overhead applied to factory 1 = Actual machine hours x Factory overhead rate for factory 1

= 1,440 x 20

= $28,800

Overhead applied to factory 2 = Actual direct labor hours x Factory overhead rate for factory 2

= 1,320 x 68

= $89,760

Factory General journal Debit Credit
Factory 1 Work in process inventory $28,800
Factory overhead $28,800
Factory 2 Work in process inventory $89,760
Factory overhead $89,760

d.

Under applied factory overhead in factory 1 = Actual factory overhead in factory 1 - Overhead applied to factory 1

= 29,520-28,800

= $720

Over applied factory overhead in factory 2 = Overhead applied to factory 2- Actual factory overhead in factory 2

= 89,760-86,170

= $3,590

Factory 1 $720 Under applied factory overhead
Factory 2 $3,590 Over applied factory overhead

Kindly comment if you need further assistance. Thanks

Add a comment
Know the answer?
Add Answer to:
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $674,520 $984,900 Estimated direct labor hours for year 14,700 Estimated machine hours for...

  • Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $740,250 $735,000 Estimated direct labor hours for year 9,800 Estimated machine hours for...

  • Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 $381,000 $838,400 13,100 Estimated factory overhead cost for fiscal year beginning March 1 Estimated direct labor hours for year Estimated machine hours for...

  • Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $654,780 $1,100,500 Estimated direct labor hours for year 15,500 Estimated machine hours for...

  • Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $916,180 $907,500 Estimated direct labor hours for year 12,100 24,110 $73,230 $78,480 Estimated...

  • Factory Overhead Rates, Entries, and Account Balance1 Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance1 Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine heurs are as follows: Factory 1 Factory 2 Estimated factery ovemead cost for fiscal year beginning March 1 $371,450 $850,200 Estimated direct labor hours for year 10,930 Estimated machine hours for...

  • Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $12,900,000 $10,200,000 Estimated direct labor hours for year 250,000 Estimated machine hours for...

  • Factory Overhead Rates. Entries and Account Balance Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates. Entries and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct lab Factory 1 $436,800 5739,200 13.200 Estimated factory overhead cost for fiscal year beginning March 1 Estimated direct labor hours for year Estimated machine hours for year Actual factory overhead costs for March Actual direct labor hours for March Actual machine hours for March a....

  • actory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...

    actory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $460,460 $624,000 Estimated direct labor hours for year 10,400 Estimated machine hours for...

  • Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $12,900,000 $10,200,000 Estimated direct labor hours for year 250,000 Estimated machine hours for...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT