*************************************PLEASE SHOW CALCULATIONS************************
1.)
| Throughtput time | Delivery cycle time | Manufacturing cycle efficiency (MCE) | |
| Month 1 | 8.3 days | 33.3 days | 27.7% |
| Month 2 | 8.8 days | 36.2 days | 25.0% |
| Month 3 | 9.6 days | 39.6 days | 21.9% |
| Month 4 | 10.3 days | 42.7 days | 19.4% |
CALCULATIONS:
1-a.) Throughput time = Process time + Inspection time + Move time + Queue time
| Month 1 | (2.3 + 0.4 + 0.7 + 4.9) days | 8.3 days |
| Month 2 | (2.2 + 0.5 + 0.5 + 5.6) days | 8.8 days |
| Month 3 | (2.1 + 0.5 + 0.6 + 6.4) days | 9.6 days |
| Month 4 | (2.0 + 0.4 + 0.6 + 7.3) days | 10.3 days |
1-b.) Delivery cycle time = Wait time + Throughput time
| Month 1 | (25.0 + 8.3) days | 33.3 days |
| Month 2 | (27.4 + 8.8) days | 36.2 days |
| Month 3 | (30.0 + 9.6) days | 39.6 days |
| Month 4 | (32.4 + 10.3) days | 42.7 days |
1-c.) Manufacturing Cycle Efficiency =
| Month 1 | (2.3/8.3)*100 | 27.7% |
| Month 2 | (2.2/8.8)*100 | 25.0% |
| Month 3 | (2.1/9.6)*100 | 21.9% |
| Month 4 | (2.0/10.3)*100 | 19.4% |
2.) Evaluation of company's performance for the last 4 months
| The Throughput Time measure displays | Unfavorable | Trend |
| The Delivery Cycle time-days measure displays | Unfavorable | Trend |
| Manufacturing Cycle Effiiciency - days measure displays | Unfavorable | Trend |
Evaluation is MCE is decreasing every month and throughtput time and delivery cycle time is increasing every month.
3.)
| Month 5 | Month 6 | |
| Throughput Time | 3.0 days | 2.6 days |
| Manufacturing Cycle Effiiciency | 66.7% | 76.9% |
CALCULATIONS:
3-a.) New throughput time for month 5 = Process time + Inspection time + Move time
= (2.0 + 0.4 + 0.6) days
=3 days
New MCE for month 5 =
= (20 / 3) days* 100
= 66.7%
3-b.)
New throughput time for month 6 = Process time + Move time
= (2.0 + 0.6) days
= 2.6 days
New MCE for month 6 =
= (2.0 / 2.6)days* 100
= 76.9%
Please rate positively if this helped you,
Thanks !
*************************************PLEASE SHOW CALCULATIONS************************ DataSpan, Inc., automated its plant at the start of the current year and...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 3 2 ? 4 ? ? ? Throughput...
DataSpan, Inc., automated its plant at the start of the current
year and installed a flexible manufacturing system. The company is
also evaluating its suppliers and moving toward Lean Production.
Many adjustment problems have been encountered, including problems
relating to performance measurement. After much study, the company
has decided to use the performance measures below, and it has
gathered data relating to these measures for the first four months
of operations.
Problem 10-14 Measures of Internal Business Process Performance (LO10-3]...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1. 4. ? 3 ? > Throughput time...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations, Month 34 Throughput time (days) Delivery cycle time (days)...
JUST QUESTION #3 PLEASE
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month m n Throughput time...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month Throughput time (days) Delivery cycle time (days) Manufacturing...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 2 1 Throughput time (days) Delivery cycle time...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 ? Throughput time (days) Delivery...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month ? Throughput time (days) Delivery cycle time (days)...
DataSpan, Inc, automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 2 3 4 Throughput time (days) Delivery cycle...