1.
a. Indirect costs assigned to Product 1 = $125000 x 10% + 675000 x
40% = $282,500
b. Indirect costs assigned to Product 1 = $125000 x 90% + 675000 x
60% = $517,500
2.
a. Indirect costs assigned to Product 1 = 800 x $13 + 70 x $24 =
$12080
b. Indirect costs assigned to Product 1 = 400 x $13 + 90 x $24 =
$7360
3.
Overhead assigned = 8 x $10 + 4 x $150 = $680
Overhead per unit = $680 / 50 = $13.60
a. Total Manufacturing Cost per unit = $30+60+13.60 =
$103.60
b. Gross Profit per unit = $200 - 103.60 = $96.40 per unit
If you have any query, kindly comment with your query and please mark thumbs up.
Your company makes Product 1 and Product 2 using Activity A and Activity B. The cost...
Your company pays $30,000 for the 5,000 megawatts of electricity it used this month. To make your product, your company performs Activity A, Activity B, and Activity C. If Activity A used up 1,250 megawatts of electricity, Activity B used up 2,750 megawatts of electricity, and Activity C used up 1,000 megawatts of electricity, then how much of the electricity bill should be assigned to Activity A cost pool? Activity B cost pool? Activity C cost pool? Your company makes...
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing. The company produces two products, cell phones and tablet PCs, in a single production department. The production department is estimated to require 4,000 direct labor hours. The total indirect labor is budgeted to be $595,200. Time records from indirect labor employees revealed that they spent 40% of their time setting up production runs and 60% of their time supporting actual production. The following information...
Activity-Based Costing and Product Cost Distortion
Digital Storage Concept Inc. is considering a change to
activity-based product costing. The company produces two products,
cell phones and tablet PCs, in a single production department. The
production department is estimated to require 4,000 direct labor
hours. The total indirect labor is budgeted to be $504,000.
Time records from indirect labor employees revealed that they
spent 60% of their time setting up production runs and 40% of their
time supporting actual production.
The...
Activity Level Activity Cost-Driver Base Cost Product A Product B Production setup Number of setups 90,000 11 19 Materials handing & requisition Number of parts per unit 15,000 6 18 Packaging & shipping Number of units shipped 45,000 60,000 120,000 Total overhead 150,000 Paris, Inc, Produces two products, Product A and Product B. If currently allocates overhead costs using direct-labor hours, but the controller has recommended an activity-based costing (ABC) system using the following data: B. Compute the amount of...
Calculator Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing. The company produces two products, cell phones and tablet PCs, in a single production department The production department is estimated to require 4,000 direct labor hours. The total indirect laboris budgeted to be $686,400. Time records from Indirect labor employees revealed that they spent 60% of their time setting up production runs and 40% of their time supporting actual production The following information...
Please show how to work these out. Thanks!
61 Required Information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Part 1 of 3 Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $398,280 Number of machine hours 89,725 Number of design hours 79,413 Number of batches Estimated Cost Driver 99, see 9,250 490 0.07 points eBook Hint Print Required: 1. Compute the activity rate for...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $183,300 Number of machine hours 47,725 Number of design hours 71,150 Number of batches Estimated Cost Driver 61,100 5,750 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...
Exercise 17-10 Using ABC for strategic decisions LO P1, P3 Consider the following data for two products of Gitano Manufacturing (Loss amounts should be indicated with a minus sign. Round "OH rate and cost per unit" answers to 2 decimal places.) Product Products Number of units produced 10,000 units 2,000 units Direct labor cost (e $24 per ) 0.20 DLH per unit 0.25 DLH per unit Direct materials cost $ 2 per unit $ 3 per unit Activity Machine setup...
4.2 Should this information influence company
strategy?
Yes
No
Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with a minus sign. Round your intermediate calculations and "OH rate and cost per unit" answers to 2 decimal places) Product A Number of units produced 11,500 units Direct labor cost (@ $30 per DLH) 0.21 DLH per unit Direct materials cost $ 2.20 per unit Product B 1,300 units 0.25 DLH per unit $ 2.30...
Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with a minus sign. Round your intermediate calculations and "OH rate and cost per unit" answers to 2 decimal places) Number of units produced Direct labor cost (@ $24 per DLH) Direct materials cost Product A 11,500 units 0.20 DLH per unit $ 2.40 per unit Product B 1,500 units 0.27 DLH per unit $ 2.70 per unit Activity Machine setup Materials handling Quality control...