Question

Consider two alternative water resource projects, A and B.•Project A will cost$2,533,000 and will return...

Consider two alternative water resource projects, A and B.

•Project A will cost$2,533,000 and will return $1,000,000 at the end of 5 years and $4,000,000 at the end of10 years. Project A has a life of 10 years.

•Project B will cost $4,000,000 and will return $2,000,000 at the end of 5 and 15years, and another $3,000,000 at the end of 10 years. Project B has a life of 15 years.

Assuming an interest rate of 10%per year:

(a)Compute the net present value of each Project? Which Project is preferred?

(b)What is the annual net benefit for each Project?

(c)Would the preferred Project differ if the interest ratewas5%?

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1
PROJECT A
YEAR CASH INFLOWS(A) PV FACTOR (B) PRESENT VALUE (A*B)
1 0.909                                  -   
2 0.826                                  -   
3 0.751                                  -   
4 0.683                                  -   
5 10,00,000.00 0.621 6,20,921.32
6 0.564                                  -   
7 0.513                                  -   
8 0.467                                  -   
9 0.424                                  -   
10 40,00,000.00 0.386 15,42,173.16
50,00,000.00 6.14 21,63,094.48
NPV PRESENT VALUE - INITIAL COSTS 2533000-2163094.48 3,69,905.52
PROJECT B
YEAR CASH INFLOWS(A) PV FACTOR (B) PRESENT VALUE (A*B)
1                                0.91                                         -  
2                                0.83                                         -  
3                                0.75                                         -  
4                                0.68                                         -  
5                                               20,00,000.00                                0.62                         12,41,842.65
6                                0.56                                         -  
7                                0.51                                         -  
8                                0.47                                         -  
9                                0.42                                         -  
10                                               30,00,000.00                                0.39                         11,56,629.87
11                                                              -                                  0.35                                         -  
12                                0.32                                         -  
13                                0.29                                         -  
14                                0.26                                         -  
15                                               20,00,000.00                                0.24                           4,78,784.10
                                              70,00,000.00                                7.61                         28,77,256.61
NPV PRESENT VALUE - INITIAL COSTS 2877256.61-4000000 -11,22,743.39

A positive NPV means that the sum of the present value of future cash flow is greater than the cash flow.

This indicates that the project is profitable and therefore acceptable.

Negative NPV means that the sum of the future cash flow's present value is less than the cash flow.

SO IT IS ADVISED TO REJECT BOTH projects HAVING NEGATIVE NPV.

ANNUAL NET BENEFIT FOR EACH PROJECT

BC RATIO =

PV OF BENEFITS/ PV OF COSTS

PROJECT A

2163094.48 / 2533000

0.85

PROJECT B

2877256.61/4000000

                               0.72

C)

PROJECT A

YEAR CASH INFLOWS(A) PV FACTOR AT 5%(B) PRESENT VALUE (A*B)
1 0.952                                         -  
2 0.907                                         -  
3 0.864                                         -  
4 0.823                                         -  
5 10,00,000.00 0.784                           7,83,526.17
6 0.746                                         -  
7 0.711                                         -  
8 0.677                                         -  
9 0.645                                         -  
10 40,00,000.00 0.614                         24,55,653.01
                                        -  
50,00,000.00 6.14 32,39,179.18
NPV PRESENT VALUE - INITIAL COSTS 3239179.18-2533000 7,06,179.18
PROJECT B
YEAR CASH INFLOWS(A) PV FACTOR AT 5%(B) PRESENT VALUE (A*B)
1                              0.952                                         -  
2                              0.907                                         -  
3                              0.864                                         -  
4                              0.823                                         -  
5                                               20,00,000.00                              0.784                         15,67,052.33
6                              0.746                                         -  
7                              0.711                                         -  
8                              0.677                                         -  
9                              0.645                                         -  
10                                               30,00,000.00                              0.614                         18,41,739.76
11                                                              -                                0.585                                         -  
12                              0.557                                         -  
13                              0.530                                         -  
14                              0.505                                         -  
15                                               20,00,000.00                              0.481                           9,62,034.20
                                        -  
                                              70,00,000.00                              10.38                         43,70,826.29
NPV PRESENT VALUE - INITIAL COSTS 2877256.61-4000000 3,70,826.29

A positive NPV means that the sum of the present value of future cash flow is greater than the cash flow.

This indicates that the project is profitable and therefore acceptable.

Negative NPV means that the sum of the future cash flow's present value is less than the cash flow.

SO IT IS ADVISED TO SELECT PROJECT A WHICH HAS HIGHER NPV $706179.18


Add a comment
Know the answer?
Add Answer to:
Consider two alternative water resource projects, A and B.•Project A will cost$2,533,000 and will return...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • A contractor is to bid on one of two construction projects, Project A or Project B....

    A contractor is to bid on one of two construction projects, Project A or Project B. If the firm wins project A, its estimated profit is $2,000,000; if the firm wins project B, the estimated profit is $3,000,000. The cost of putting the bid together for the projects is $200,000 for A and $250,000 for B. Due to a difference in the number of qualified competitors, the firm estimates its probability of getting Project A as 0.7 and its probability...

  • (a) Calculate the IRR, NPV, Annual Percentage Rate and Payback Period for the following projects: PROJECT...

    (a) Calculate the IRR, NPV, Annual Percentage Rate and Payback Period for the following projects: PROJECT A B C D Inicial Investment 1,000,000 2,000,000 2,000,000 1,000,000 (b) Consider the cash flow projection for the next four years. Compare the projects and determine what is the best option for an investor that wants a 10% minimum aceptable rate of return. Years Project A Project B Project C Project D 1 300,000 400,000 400,000 1,000,000 2 400,000 200,000 200,000 1,000,000 3 500,000...

  • (b) A company is evaluating between two mutually exclusive projects. The required initial investments and the...

    (b) A company is evaluating between two mutually exclusive projects. The required initial investments and the expected net cash flows from the projects are as follows: Project 1 Project 2 0 -$4,000,000 - $4,000,000 1 $1,900,000 $1,100,000 2 $2,255,000 $1,900,000 3 $2,000,000 $2,000,000 The company accepts any project for which the payback period is within 3 years, Which of these projects should be chosen using the payback period as the capital budgeting measure? (3 marks) An Australian multinational company is...

  • 10 of 15 (7 compl The Silverside Company is considering investing in two alternative projects: Project...

    10 of 15 (7 compl The Silverside Company is considering investing in two alternative projects: Project 1Project 2 $200,000 $260,000 Investment Useful life (years) Estimated annual net cash inflows for useful life Residual value Depreciation method Required rate of return 4 $90,000 $70,000 $20,000 $16,000 Straight- line Straight -line 6% 8% What is the payback period for Project 2? O A. 13.00 years OB. 2.22 years O C. 10.00 years D. 3.71 years

  • This is a cost accounting problem, please show all work. Payback and NPV methods, no income...

    This is a cost accounting problem, please show all work. Payback and NPV methods, no income taxes. (CMA, adapted) Andrews Construction is analyzing its capital expenditure proposals for the purchase of equipment in the coming year. The capital budget is limited to $5,000,000 for the year. Lori Bart, staff analyst at Andrews, is preparing an analysis of the three projects under consideration by Corey Andrews, the company's owner. Insert Page Layout Formulas Data Review View Home A В С D...

  • Consider the following projects: Project A has a cost of 75 and uniform annual benefit of...

    Consider the following projects: Project A has a cost of 75 and uniform annual benefit of 18.8; Project B has a cost of 50 and uniform annual benefit of 13.9; Project C has a cost of 15 and uniform annual benefit of 4.5; Project D has a cost of 90 and uniform annual benefit of 23.8. Using a 5-year analysis with MARR = 10%, which project should be selected using the payback period. Group of answer choices Project A Project...

  • Determine the weighted average cost of capital (WACC) for each of the Table 1                             

    Determine the weighted average cost of capital (WACC) for each of the Table 1                                 Pacific Technology COMPANY Balance Sheet 12/31/2005 Assets Liability & Equity Cash $6,000,000 Account Payable $1,000,000 Account Receivable $8,000,000 Notes Payable $3,000,000 Inventory $3,000,000 Accrued Taxes $1,000,000 Current Asset $17,000,000 Current Liabilities $5,000,000 GFA $40,000,000 Long-term debt $10,000,000 Accumulated Depreciation ($2,000,000) Preferred Stock (0.5 million shares) $15,000,000 Net Fixed Assets $38,000,000 Common Stock (1 million shares) $10,000,000 Returned Earnings $15,000,000 Common Equity $25,000,000 Total Asst $55,000,000 Total...

  • Consider the following projects with life 8 years, Project First cost MARR=8% B C D $800...

    Consider the following projects with life 8 years, Project First cost MARR=8% B C D $800 $600 500 Annual Benefit $120 $97 122 $500 0 Salvage Value $500 The B/C ratio of project B is most nearly less than 1 2.3 1.4 1.5 1.3 No correct answer Next Consider the following projects with life 8 years, Project First cost MARR=8% B C D $800 $600 500 Annual Benefit $120 $97 122 $500 0 Salvage Value $500 The B/C ratio of...

  • Lazy Q Ranches, one of the largest ranching consortiums in the world, is considering two projects....

    Lazy Q Ranches, one of the largest ranching consortiums in the world, is considering two projects. The first project, building a resort on one of its ranches in Montana and the other is to expand into Argentina and raise racehorses. The analysis is being done assuming a 10 year life for both projects. Lazy Q has a corporate tax rate of 25%, a required rate of return of 12% on projects and has a weighted average cost of capital of...

  • A company is considering two short-term projects: Month A B 0 -$1,200 -$1800 1    $0...

    A company is considering two short-term projects: Month A B 0 -$1,200 -$1800 1    $0 $ 400 2 $200 $ 400 3 $300 $ 300 4    $400 $ 500 5 $500 $ 200 6 $600 $ 100 a. Based on the undiscounted payback period, which project is preferred? b. Calculate the benefit-cost ratio for each alternative (use excel) c. Based on the benefit-cost ratio analysis method, which project is preferred?

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT