Predetermined overhead= Estimated overhead/ direct material cost= 124600/89000= $1.4
2. Under/Overapplied overhead
Overhead cost= Indirect labour+property taxes+depreciation+maintainance+insurance+rent= 130600+8900+17000+13000+9200+33000= $211700
| COST OF GOODS MANUFACTURED | Amount |
| Direct material | |
| Opening | 28000 |
| (+) Purchases | 137000 |
| (-) Closing | -16000 |
| Direct material used | 149000 |
| Direct Labour | 85000 |
| Factory Overhead | |
| Indirect Labour | 130600 |
| Property taxes | 8900 |
| Depreciation | 17000 |
| Maintainace | 13000 |
| Insurance | 9200 |
| Rent | 33000 |
| Total Factory overhead | 211700 |
| Total Manufacturing Cost | 445700 |
| Add: Opening WIP | 48000 |
| Less: Closing WIP | -37000 |
| Cost of goods manufactured | 456700 |
COST OF GOODS SOLD
| COST OF GOODS SOLD | Amount |
| Cost of goods manufactured | 456700 |
| Add: Opening Finished goods | 68000 |
| Goods available for sale | 524700 |
| Less: Closing finished goods | -58000 |
| Cost of goods sold | 466700 |
Der Quiz - Chapter 3 Sird Help Save & Exit Check 6 Gitano Products operates a...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $117,000 of manufacturing overhead for an estimated allocation base of $90,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: Purchase of raw materials $ 137,000 Direct...
Problem 3-14 Schedule of Cost of Goods Manufactured; Overhead Analysis [LO3-3, LO3-4] Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $124,600 of manufacturing overhead for an estimated allocation base of $89,000 direct material dollars to be used in production. The company has provided the following data...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $130,200 of manufacturing overhead for an estimated allocation base of $93,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: Purchase of raw materials $ 137,000 Direct...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $124,600 of manufacturing overhead for an estimated allocation base of $89,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: Purchase of raw materials $ 131,000 Direct...
Gitano Products operates a job-order costing system and applies
overhead cost to jobs on the basis of direct materials used in
production (not on the basis of raw materials
purchased). Its predetermined overhead rate was based on a cost
formula that estimated $130,200 of manufacturing overhead for an
estimated allocation base of $93,000 direct material dollars to be
used in production. The company has provided the following data for
the just completed year:
Purchase of raw materials
$
137,000
Direct...
Problem 3-14 (Algo) Schedule of Cost of Goods Manufactured; Overhead Analysis (LO3-3, LO3-4) Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $118,300 of manufacturing overhead for an estimated allocation base of $91,000 direct material dollars to be used in production. The company has provided the following...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $119.600 of manufacturing overhead for an estimated allocation base of $92,000 direct material dollars to be used in production. The company has provided the following data for the just completed year, $ 131,000 $ 88,000 Purchase of raw...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $127,400 of manufacturing overhead for an estimated allocation base of $91,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: Purchase of raw materials $ 139,000 Direct...
Check m Gitano Products operates a job-order costing system and applies Overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $124.600 of manufacturing overhead for an estimated allocation base of $89,000 direct material dollars to be used in production. The company has provided the following data for the just completed year. points eBook Print Purchase of...
Check my work 3 Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $126,000 of manufacturing overhead for an estimated allocation base of $90,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: 5 points $...