Question

MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was co
Required 1 Required 2 Record the preceding transactions in MSKs books assuming it recognizes revenue over time and uses cost
Required 1 Required 2 Record the preceding transactions in MSKs books assuming it recognizes revenue at a point in time when
0 0
Add a comment Improve this question Transcribed image text
Answer #1
1. Journal Entries when revenue is recognise over time.
Year General Journal Debit Credit
20X1 Construction in Progress 290000
   Cash Payable, material, payable etc. 290000
20X1 Accounts Receivables 260000
    Billings on contract 260000
20X1 Cash 240000
     Accounts Receivables 240000
20X1 Construction in Progress 60000
Constructin Expense 290000
    Construction revenue 350000
20X2 Construction in Progress 150000
   Cash Payable, material, payable etc. 150000
20X2 Accounts Receivables 265000
    Billings on contract 265000
20X2 Cash 285000
     Accounts Receivables 285000
20X2 Construction in Progress 25000
Constructin Expense 150000
    Construction revenue 175000
20X2 Billings on contract 525000
    Construction in progress 525000
2. Journal Entries when revenue is recognise at a point in time
Year General Journal Debit Credit
20X1 Construction in Progress 290000
   Cash Payable, material, payable etc. 290000
20X1 Accounts Receivables 260000
    Billings on contract 260000
20X1 Cash 240000
     Accounts Receivables 240000
20X1 -No Entry-
Since the project is incomplete
No revenue is to be recognised
20X2 Construction in Progress 150000
   Cash Payable, material, payable etc. 150000
20X2 Accounts Receivables 265000
    Billings on contract 265000
20X2 Cash 285000
     Accounts Receivables 285000
20X2 Billings on contract 525000
Constructin Expense 440000
    Construction revenue 525000
    Construction in progress 440000
20X1 20X2
Contract Price (a) 525000 525000
Less: Estimated Cost
    Costs incurred to date 290000 150000
    Estimated costs to complete 145000 0
Estimated total costs (b) 435000 150000
Estimated gross profit (a-b) 90000 375000
% of completion 66.67% 100.00%
(Cost incurred till date / Total costs)
Gross profit earned 60000 375000
Less: Gross profit earned in previous year 0 60000
Gross profit recognised 60000 315000
Construction Revenue 350000 525000
Construction Revenue to be recognised over time 350000 175000
Construction Revenue to be recognised at a point in time 0 525000
Add a comment
Know the answer?
Add Answer to:
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and...

    MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows 2019 $290,000 145,000 260,000 240,000 2020 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year $150,000 265,000 285,000 Required 1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent to which its...

  • Saved Help Save & MSK Construction Company contracted to construct a factory building for $525.000. Construction...

    Saved Help Save & MSK Construction Company contracted to construct a factory building for $525.000. Construction started during 20X1 and was completed in 20X2. Information relating to the contract follows: 20x2 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 20x1 $290,000 145,000 260,000 240,000 265,000 285,000 Required: 1. Record the preceding transactions in MSK's books assumingit recognizes revenue over time and uses costs incurred to measure the extent...

  • MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and...

    MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was completed in 20x2. Information relating to the contract follows: 2ex2 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 2ex1 $290,000 145,000 260,000 240,000 265, eee 285, eee Required: 1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent to...

  • Problem 3-3 Revenue recognition over time and at a point in time under ASC Topic 606...

    Problem 3-3 Revenue recognition over time and at a point in time under ASC Topic 606 (LO3-4) MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows: 2020 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 2019 $290,000 145,000 260,000 240,000 265,000 285,000 Required: 1. Record the preceding transactions in MSK's books...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,849, eee Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,072,00 5,328,000 2,160, eee 1,880, eee 2022 $2,738,000 2,590,000 2,650, eee 2,700,eee 5,190, eee 5,420, eee Westgate recognizes revenue over time...

  • Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the...

    Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below 2018 2017 $476,eee $1,030,e0e 884,e00 470,000 Costs incurred during the year Estimated costs to complete Billings during the yearr Cash collections during the year 1,260,00e 1,415,00e 370,000 Assume that Beavis recognizes revenue on this...

  • Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1780,000. T...

    Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1780,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2020 2021 $458,500 $1,080,000 851,500 495.000 1.285.000 395,000 1,385,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all...

  • Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,810,000. The pr...

    Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,810,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2020 $ 447,000 $1,110,000 1,043,000 405,000 1,405,000 305,000 1,505,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2823 $2,475,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $1,875, eee 5.625.000 1,5ee,eee 1,3ee,eee 2022 $3,375,000 2.25e,eee 3,75e,eee 3,100,eee 4,750,000 5,600,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2.630,000 with remaining costs estimated to be $3,795,000.2022 billings were $2,880,000 and $2,605,000 cash was collected. The project was completed in 2023 after additional costs of $3,930,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT