| 1. Journal Entries when revenue is recognise over time. | |||
| Year | General Journal | Debit | Credit |
| 20X1 | Construction in Progress | 290000 | |
| Cash Payable, material, payable etc. | 290000 | ||
| 20X1 | Accounts Receivables | 260000 | |
| Billings on contract | 260000 | ||
| 20X1 | Cash | 240000 | |
| Accounts Receivables | 240000 | ||
| 20X1 | Construction in Progress | 60000 | |
| Constructin Expense | 290000 | ||
| Construction revenue | 350000 | ||
| 20X2 | Construction in Progress | 150000 | |
| Cash Payable, material, payable etc. | 150000 | ||
| 20X2 | Accounts Receivables | 265000 | |
| Billings on contract | 265000 | ||
| 20X2 | Cash | 285000 | |
| Accounts Receivables | 285000 | ||
| 20X2 | Construction in Progress | 25000 | |
| Constructin Expense | 150000 | ||
| Construction revenue | 175000 | ||
| 20X2 | Billings on contract | 525000 | |
| Construction in progress | 525000 |
| 2. Journal Entries when revenue is recognise at a point in time | |||
| Year | General Journal | Debit | Credit |
| 20X1 | Construction in Progress | 290000 | |
| Cash Payable, material, payable etc. | 290000 | ||
| 20X1 | Accounts Receivables | 260000 | |
| Billings on contract | 260000 | ||
| 20X1 | Cash | 240000 | |
| Accounts Receivables | 240000 | ||
| 20X1 | -No Entry- | ||
| Since the project is incomplete | |||
| No revenue is to be recognised | |||
| 20X2 | Construction in Progress | 150000 | |
| Cash Payable, material, payable etc. | 150000 | ||
| 20X2 | Accounts Receivables | 265000 | |
| Billings on contract | 265000 | ||
| 20X2 | Cash | 285000 | |
| Accounts Receivables | 285000 | ||
| 20X2 | Billings on contract | 525000 | |
| Constructin Expense | 440000 | ||
| Construction revenue | 525000 | ||
| Construction in progress | 440000 |
| 20X1 | 20X2 | |
| Contract Price (a) | 525000 | 525000 |
| Less: Estimated Cost | ||
| Costs incurred to date | 290000 | 150000 |
| Estimated costs to complete | 145000 | 0 |
| Estimated total costs (b) | 435000 | 150000 |
| Estimated gross profit (a-b) | 90000 | 375000 |
| % of completion | 66.67% | 100.00% |
| (Cost incurred till date / Total costs) | ||
| Gross profit earned | 60000 | 375000 |
| Less: Gross profit earned in previous year | 0 | 60000 |
| Gross profit recognised | 60000 | 315000 |
| Construction Revenue | 350000 | 525000 |
| Construction Revenue to be recognised over time | 350000 | 175000 |
| Construction Revenue to be recognised at a point in time | 0 | 525000 |
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and...
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows 2019 $290,000 145,000 260,000 240,000 2020 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year $150,000 265,000 285,000 Required 1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent to which its...
Saved Help Save & MSK Construction Company contracted to construct a factory building for $525.000. Construction started during 20X1 and was completed in 20X2. Information relating to the contract follows: 20x2 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 20x1 $290,000 145,000 260,000 240,000 265,000 285,000 Required: 1. Record the preceding transactions in MSK's books assumingit recognizes revenue over time and uses costs incurred to measure the extent...
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was completed in 20x2. Information relating to the contract follows: 2ex2 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 2ex1 $290,000 145,000 260,000 240,000 265, eee 285, eee Required: 1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent to...
Problem 3-3 Revenue recognition over time and at a point in time under ASC Topic 606 (LO3-4) MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows: 2020 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 2019 $290,000 145,000 260,000 240,000 265,000 285,000 Required: 1. Record the preceding transactions in MSK's books...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,849, eee Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,072,00 5,328,000 2,160, eee 1,880, eee 2022 $2,738,000 2,590,000 2,650, eee 2,700,eee 5,190, eee 5,420, eee Westgate recognizes revenue over time...
Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below 2018 2017 $476,eee $1,030,e0e 884,e00 470,000 Costs incurred during the year Estimated costs to complete Billings during the yearr Cash collections during the year 1,260,00e 1,415,00e 370,000 Assume that Beavis recognizes revenue on this...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1780,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2020 2021 $458,500 $1,080,000 851,500 495.000 1.285.000 395,000 1,385,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,810,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2020 $ 447,000 $1,110,000 1,043,000 405,000 1,405,000 305,000 1,505,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2823 $2,475,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $1,875, eee 5.625.000 1,5ee,eee 1,3ee,eee 2022 $3,375,000 2.25e,eee 3,75e,eee 3,100,eee 4,750,000 5,600,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2.630,000 with remaining costs estimated to be $3,795,000.2022 billings were $2,880,000 and $2,605,000 cash was collected. The project was completed in 2023 after additional costs of $3,930,000...