Question



















The following information is available for electricity costs for the last six months of the year: Month Production Volume Ele
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Variable cost = Change in Total cost / Change in Units

We will compare data of May and June for the formula

Change in total cost = 4,050 - 2,400 = $1,650

Change in quantity = 2,100 - 1,200 = 900 units

Variable cost per unit = 1,650/900 = $1.83

In the month of June total cost is $4,050

Variable cost = 2,100*1.83 = 3,850

Fixed cost = Total cost - Variable cost

= 4,050 - 3,850

= $200

Therefore the correct option is 2nd.

If you find the answer helpful please upvote.

Add a comment
Know the answer?
Add Answer to:
The following information is available for electricity costs for the last six months of the year:...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following information is available for electricity costs for the last six months of the year:...

    The following information is available for electricity costs for the last six months of the year: Month Production Volume Electricity Costs January 1.400 $2,200 February 2,800 5,400 March 3,200 5,700 April 1,750 3,900 May 1.200 2.400 June 2.100 4,050 What are the fixed costs? $420 5200 $100

  • CHAPTER THREE 7. The following information is available for electricity costs for the last six months...

    CHAPTER THREE 7. The following information is available for electricity costs for the last six months of the year: Month Production Volume Electricity Costs February 1,000 $1,700 March 2,200 4,000 April 2,000 3,200 May 1,630 3,100 June 1,240 2,600 July 1,340 3,020 Using the high-low method, what is the estimated variable cost per unit of production? (Round your answer to two decimal places.) (4 Points) 1.75 1.92 1.53 1.37

  • peedy Couriers documented the miles driven and total vehicle costs for the past five months as...

    peedy Couriers documented the miles driven and total vehicle costs for the past five months as follows: Number of miles Total vehicle costs January 1,600 $3,600 February 2,000 4,600 March 1,500 3,450 April 1,800 3,900 May 2,200 4,500 Refer to the Speedy Couriers information above. Using the high/low method, if Speedy expects to drive 1,750 miles in June, what will be expected total vehicle costs?  (Select closest number.) $3,825.00 $4,585.00 $8,087.50 $3,855.00

  • Machine hours and electricity costs for Wells Industries for last year were as follows: Machine Electricity...

    Machine hours and electricity costs for Wells Industries for last year were as follows: Machine Electricity Month Hours Costs January 2,000 $ 9,200 February 2,320 10,500 March 1,520 6,750 April 2,480 11,500 May 3,040 14,125 June 2,640 11,000 July 3,280 12,375 August 2,800 11,375 September 1,600 7,750 October 2,960 13,000 November 3,760 15,500 December 3,360 13,875 Required: Show your Calculations! A. Using the high-low method, develop an estimate of variable electricity costs per machine hour. B. Using the high-low method,...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,200 2,600 1,600 2,800 3,500 3,000 3,800 3,200 1,700 3,400 4,400 3,900 Electricity Costs $ 19,050 $22,300 $14,150 $24,300 $28,900 $23,300 $25,400 $23,400 $ 16,800 $27,300 $32,300 $28,400 Summary Output Regression Statistics...

  • Carmen's Beauty Salon has estimated monthly financing requirements for the next six months as January February...

    Carmen's Beauty Salon has estimated monthly financing requirements for the next six months as January February March $ 8,200 April 2,200 May 3,200 June $ 8,200 9,200 4,200 Short-term financing will be utilized for the next six months. Projected annual interest rates are: 6% April 7 May 10 June January 13% 12 12 February March What long-term interest rate would represent a break-even point between using short-term financing and long-term financing? (Round your monthly interest rate to 2 decimal places...

  • The following information is available regarding the total manufacturing overhead of Bursa Mfg. Co. for a...

    The following information is available regarding the total manufacturing overhead of Bursa Mfg. Co. for a recent four-month period. Machine- Hours Manufacturing Overhead January 5,400 $ 310,000 February 3,200 224,000 March 4,900 263,800 April 2,800 190,000 a-1. Use the high-low method to determine the variable element of manufacturing overhead costs per machine-hour. (Round your answer to 2 decimal places.) a-2. Use the high-low method to determine the fixed element of monthly overhead cost. b. Bursa expects machine-hours in May to...

  • The Denver Corporation has forecast the following sales for the first seven months of the year:...

    The Denver Corporation has forecast the following sales for the first seven months of the year: January $ 34,000 February 36,000 March 38,000 April 44,000 May 34,000 June 40,000 July 42,000 Monthly material purchases are set equal to 35 percent of forecast sales for the next month. Of the total material costs, 45 percent are paid in the month of purchase and 55 percent in the following month. Labor costs will run $6,400 per month, and fixed overhead is $14,000...

  • Carmen’s Beauty Salon has estimated monthly financing requirements for the next six months as follows:   ...

    Carmen’s Beauty Salon has estimated monthly financing requirements for the next six months as follows:    January $ 9,400 April $ 9,400 February 3,400 May 10,400 March 4,400 June 5,400 Short-term financing will be utilized for the next six months. Projected annual interest rates are:      January 8 % April 15 % February 9 May 12 March 12 June 12 What long-term interest rate would represent a break-even point between using short-term financing and long-term financing? (Round your monthly interest...

  • Carmen’s Beauty Salon has estimated monthly financing requirements for the next six months as follows:   ...

    Carmen’s Beauty Salon has estimated monthly financing requirements for the next six months as follows:    January $ 10,400 April $ 10,400 February 4,400 May 11,400 March 5,400 June 6,400 Short-term financing will be utilized for the next six months. Projected annual interest rates are:      January 8 % April 15 % February 9 May 12 March 12 June 12 What long-term interest rate would represent a break-even point between using short-term financing and long-term financing? (Round your monthly interest...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT