Answer-
| Cost of goods manufactured schedule | |||
| For the year ended Dec 31, 2020 | |||
| Particulars | Amount | ||
| Work In Process (1/1) | $217,000 | ||
| Direct materials: | |||
| Raw materials inventory (1/1) ($187,000-($167,000-$18,000)) | $38,000 | ||
| Add: Raw materials purchases | $167,000 | ||
| Total raw materials available for use ($38000+$167,000) | $205,000 | ||
| Less: Raw materials inventory (12/31) | $18,000 | ||
| Direct materials used | $187,000 | ||
| Direct labor ($414,200-$187,000-$120,900) | $106,300 | ||
| Manufacturing overhead: | |||
| Indirect labor | $15,400 | ||
| Factory depreciation | $37,000 | ||
| Factory utilities | $68,500 | ||
| Total overhead | $120,900 | ||
| Total manufacturing costs ($631,200-$217,000) | $414,200 | ||
| Total cost of work in process ($550,600+$80,600) | $631,200 | ||
| Less: Work in process (12/31) | $80,600 | ||
| Cost of goods manufactured | $550,600 | ||
Kindly give me thumbs up if u like my answer...Thanks!!!!
Help System Announcements complete the cost or goous manuractured scheduie ror Cepeda Manuracturing company. CEPEDA MANUFACTURING...
An incomplete cost of goods manufactured schedule is presented
below for Cepeda Manufacturing Company for the year ended December
2020:
Complete the cost of goods manufactured schedule for Cepeda
Manufacturing Company.
Complete the cost of goods
manufactured schedule for Cepeda Manufacturing Company.
CEPEDA MANUFACTURING COMPANY Cost of Goods Manufactured Schedule For the Year Ended December 31, 2020 $217,000 Work in process (1/1) Direct materials Raw materials inventory, (1/1) Raw materials purchases 167,000 Total raw materials available for use 18,000 Less:...
An incomplete cost of goods manufactured schedule is presented below for Cepeda Manufacturing Company for the year ended December 2020: Complete the cost of goods manufactured schedule for Cepeda Manufacturing Company. CEPEDA MANUFACTURING COMPANY Cost of Goods Manufactured Schedule For the Year Ended December 31, 2020 $212,500 $ 166,000 Work in process (1/1) Direct materials Raw materials inventory(1/1) Raw materials purchases Total raw materials available for use Less: Raw materials inventory (12/31) Direct materials used 17,800 $188,000 Direct labour Manufacturing...
CEPEDA MANUFACTURING COMPANY Cost of Goods Manufactured Schedule For the Year Ended December 31, 2020 Work in process (1/1) $212,500 Direct materials Raw materials inventory, (1/1) Raw materials purchases Total raw materials available for use Less: Raw materials inventory (12/31) 166,000 17,800 Direct materials used Direct labour Manufacturing overhead $188,000 Indirect labour Factory depreciation Factory utilities Total manufacturing overhead 15,500 36,400 68,000 119,900 Total manufacturing costs Total cost of work in process Less: Work in process (12/31) Cost of goods...
Question 4 View Policies Current Attempt in Progress Cepeda Corporation has the following cost records for June 2020. $4,690 Factory utilities $430 Indirect factory labor Direct materials used 22,410 Depreciation, factory equipment 1,770 Work in process, 6/1/20 3,970 Direct labor 42,100 Work in process, 6/30/20 1.910 4.410 5,650 Maintenance, factory equipment Indirect materials Finished goods, 6/1/20 2,810 Finished goods, 6/30/20 8,030 Factory manager's salary 3,930 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods...
Help 1 System Announcements CALCULATOR PRINTER VERSION BACK NEXT Challenge Exercise 19-02 a-b, c1 (Part Level Submission) An analysis of the accounts of Sheridan Company reveals the following manufacturing cost data for the month ended September 30, 2020. Inventories Raw materials Work in process Finished goods Beginning $12,500 6,800 9,600 Ending $11,000 5,400 11,700 Costs incurred: raw materials purchases $63,700, direct labor $50,800, manufacturing overhead $27,400. The specific overhead costs were: indirect labor $6,900, factory insurance $4,700, machinery depreciation $6,200,...
An analysis of the accounts of KAZ Manufacturing Pty Ltd reveals the following manufacturing cost data for the month ended 30 June 2019. Beginning Ending $ 14000 10000 16 000 $22 200 18000 12 000 Inventories: Raw materials Work in process Finished goods Costs incurred: Raw materials purchases Direct labour Manufacturing overhead Specific overhead costs: Indirect labour Factory insurance Machinery depreciation Machinery repairs Factory utilities Miscellaneous factory costs 128 000 100 000 60 000 31 200 8 000 8 000...
part B)
Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,690 Factory utilities $430 Direct materials used 22,410 Depreciation factory equipment 1,770 Work in process, 6/1/20 3,970 Direct labor 42,100 Work in process, 6/30/20 4,410 Maintenance, factory equipment 1,910 2,810 Finished goods, 6/1/20 Finished goods, 6/30/20 5,650 Indirect materials 8,030 Factory manager's salary 3,930 Your Answer Correct Answer Your answer is correct. Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost...
Cepeda Corporation has the following cost records for June 2020. Indirect factory labor Direct materials used Work in process, 6/1/20 Work in process, 6/30/20 Finished goods, 6/1/20 Finished goods, 6/30/20 $4,750 21,330 3,400 4,540 6,090 8,470 Factory utilities Depreciation, factory equipment Direct labor Maintenance, factory equipment Indirect materials Factory manager's salary $440 1,590 42,300 1,900 2,140 3,360 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule For the Year Ended June 30,...
Uus m uidctueu (LUS, LUD, LUY) The following cost data relate to the manufacturing activities of Black Company during the just completed year: Manufacturing overhead costs: Property taxes, factory Utilities, factory Indirect labour Depreciation, factory Insurance, factory 4,100 6,650 12,200 26,750 8,200 Total actual manufacturing overhead costs 57,900 37,500 47,700 Other costs incurred: Purchases of raw materials. Direct labour cost Inventories: Raw materials, beginning Raw materials, ending Work in process, beginning Work in process, ending 10,209 8,100 7,650 9,700 The...
An incomplete cost of goods manufactured schedule is presented
below.
Complete the cost of goods manufactured schedule for Concord
Company.
CONCORD COMPANY
Cost of Goods Manufactured Schedule
Work in process (1/1)
$215,370
Direct materials
Raw materials inventory (1/1)
$
----------
Add: Raw materials purchases
164,870
Total raw materials available for use
-----------
Less: Raw materials inventory (12/31)
27,100
Direct materials used
$183,400
Direct labor
-----------
Manufacturing overhead
Indirect labor
21,960
Factory depreciation
36,430
Factory utilities
71,750
Total overhead
130,140
Total...