Ans 21. Job order costing system is one of the type of costing system that provides costs to company's product or services.
Job order costing system is used when company provides different product or services to the customers as per their needs. Each custom product or service is considered a job and costs like manufacturing overheads costs, direct labour and direct materials are traced by company to determine the costs of goods manufactured.
In job order costing system, manufacturing overhead is applied to job using a predetermined overhead rate and that rate is calculated by estimating the total factory overhead costs further divided by direct labour hours.
As these are not actual cost but estimated cost, the answer is false.
In a job order costing system manufacturing overhead is applied to jobs using a predetermined overhead cost ( estimated cost ).
Ans 22. A plantwide overhead rate is used when a company allocates all of its manufacturing overhead costs to its production output.
Plantwide overhead rate is an amount per labour hours, an amount per machine-hours or a percentage of direct costs of product.
So the plantwide overhead rate is based on labour costs and labour hours.
So the first three options are not correct as it is not based on only one.
So the correct option is : it is often overly simplistic and incorrect to assume that direct labour-hours is a company's only manufacturing overhead cost driver.
Question 21 5 pts In a job order costing system manufacturing overhead is applied to jobs...
Please help me complete this!
I have been struggling for a while, and mainly I need the
answer!
Thank you for your help!
Question 2 2 pts 3) Which of the following statements about using a plantwide overhead rate based on direct laboris correct? A) Using a plantwide overhead rate based on direct labor-hours will ensure that direct labor costs are correctly traced to jobs B) Using a plantwide overhead rate based on direct labor costs will ensure that direct...
In a job-order costing system that is based on machine-hours, which of the following formulas is correct? A) Predetermined overhead rate = Actual manufacturing overhead ÷ Actual machine-hours B) Predetermined overhead rate = Actual manufacturing overhead ÷ Estimated machine-hours C) Predetermined overhead rate = Estimated manufacturing overhead ÷ Estimated machine-hours D) Predetermined overhead rate = Estimated manufacturing overhead ÷ Actual machine-hours 41. Which of the following statements about using a plantwide overhead rate based on direct labor is correct? A)...
16) Assigning manufacturing overhead to a specific job is complicated by all of the below except: A) Manufacturing overhead is an indirect cost that is either impossible or difficult to trace to a particular job. B) Manufacturing overhead is incurred only to support some jobs. C) Manufacturing overhead consists of both variable and fixed costs. D) The average cost of actual fixed manufacturing overhead expenses will vary depending on how many units are produced in a period. 17) Which of...
Question 23 5 pts In job order costing, the predetermined overhead rate multiplied by a job's actual usage of the allocation base equals: the total estimated overhead for the period the amount of manufacturing overhead applied to the job's cost the total cost of the job O actual manufacturing overhead Question 24 5 pts Which of the following is(are) typical cost drivers that would be used as an allocation base? Choose the best answer sales persons commissions O machine hours...
Parker Corporation uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor-hours. Last year manufacturing overhead and direct labor-hours were estimated at $80,910 and 27,900 hours, respectively, for the year. In June, Job #461 was completed. Materials costs on the job totaled $4,400 and labor costs totaled $1,836 at $5.40 per hour. At the end of the year, it was determined that the company worked 34,400 direct labor-hours for the...
Parker Corporation uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor-hours. Last year manufacturing overhead and direct labor-hours were estimated at $80,910 and 27,900 hours, respectively, for the year. In June, Job #461 was completed. Materials costs on the job totaled $4,400 and labor costs totaled $1,836 at $5.40 per hour. At the end of the year, it was determined that the company worked 34,400 direct labor-hours for the...
Parker Corporation uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor-hours. Last year manufacturing overhead and direct labor-hours were estimated at $73,440 and 27,200 hours, respectively, for the year. In June, Job #461 was completed. Materials costs on the job totaled $4,200 and labor costs totaled $1,664 at $5.20 per hour. At the end of the year, it was determined that the company worked 35,900 direct labor-hours for the...
1. Anderson Company uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. Manufacturing overhead and direct labor hours were estimated at $70,400 and 22,000 hours, respectively. In June, Job 11461 was completed. Ma. terials costs on the job totaled $4,815 and labor costs totaled $2,325 at $7.50 per hour (310 hours worked on this job). At the end of the year, it was determined that the company worked...
5. Irma Corporation uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor-hours. Last year manufacturing overhead and direct labor-hours were estimated at $84,000 and 24,000 hours, respectively, for the year. In June, Job #168 was completed. Materials costs on the job totaled $6,000 and labor costs totaled $3,600 at $6.00 per hour. At the end of the year, it was determined that the company worked 32,000 direct labor-hours for...
Job-Order Costing U-Design-It Furniture Company uses a job-order cost system. The company applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. The estimated MOH was $144,000 for the year and the estimated direct labor hours were 18,000 hours. In March, Job #175 was completed. Direct materials totaled $7,000. Total labor costs were $6,000 at $20 per hour. At the end of the year, it was determined that the company worked 17,000 direct labor hours...