Answer-:
1.) overhead applied
=Predetermined overhead rate * actual machine hours
=$2.60 *83000 machine hours
=$215800
| Manufacturing overhead | work in process | |||||||
| Maintenance | 29,000 | 215800 | (a) | Direct mat | 790,000 | |||
| indirect materials | 8,800 | direct labor | 98,000 | |||||
| indirect labor | 72,000 | OH (a) | 215800 | |||||
| utilities | 40,000 | |||||||
| insurance | 7,800 | |||||||
| Depreciation | 64,000 | |||||||
| Balance |
5,800 |
| 2-a) | under applied | manufacturing overhead | 5,800 |
2-b).
| Event | General Journal | Debit | Credit | |||||
| 1) | Cost of goods sold | 5800 | ||||||
| Manufacturing overhead |
5800 |
Thankyou.......
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. The company's predetermined overhead rate of $2.80 per machine-hour was based on a cost formula that estimates $232,400 of total manufacturing overhead for an estimated activity level of 83,000 machine-hours. Required: 1. Assume that during the year the company works only 78,000 machine-hours and incurs the following costs in the Manufacturing Overhead and Work in Process accounts: Compute the amount of overhead...
Harwood Company uses a job-order costing system that applies
overhead cost to jobs on the basis of machine-hours. The company's
predetermined overhead rate of $2.80 per machine-hour was based on
a cost formula that estimates $249,200 of total manufacturing
overhead for an estimated activity level of 89,000
machine-hours.
Required:
1. Assume that during the year the company works only 84,000
machine-hours and incurs the following costs in the Manufacturing
Overhead and Work in Process accounts: Compute the amount of
overhead...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. The company's predetermined overhead rate of $2.30 per machine-hour was based on a cost formula that estimates $225,400 of total manufacturing overhead for an estimated activity level of 98,000 machine-hours. Required: 1. Assume that during the year the company works only 93,000 machine-hours and incurs the following costs in the Manufacturing Overhead and Work in Process accounts: Compute the amount of overhead...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. The company's predetermined overhead rate of $3.00 per machine-hour was based on a cost formula that estimates $258,000 of total manufacturing overhead for an estimated activity level of 86,000 machine-hours. Required: 1. Assume that during the year the company works only 81,000 machine-hours and incurs the following costs in the Manufacturing Overhead and Work in Process accounts: Compute the amount of overhead...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. The company's predetermined overhead rate of $2.50 per machine-hour was based on a cost formula that estimates $242,500 of total manufacturing overhead for an estimated activity level of 97.000 machine hours. 00:35:41 Required: 1. Assume that during the year the company works only 92,000 machine-hours and incurs the following costs in the Manufacturing Overhead and Work in Process accounts: Compute the amount...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. The company's predetermined overhead rate of $2.40 per machine-hour was based on a cost formula that estimates $225,600 of total manufacturing overhead for an estimated activity level of 94.000 machine-hours. Required: 1. Assume that during the year the company works only 89,000 machine hours and incurs the following costs in the Manufacturing Overhead and Work in Process accounts: Compute the amount of...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. The company predetermined overhead rate of $2.40 per machine-hour was based on a cost formula that estimates $201.600 of total manufacturing overhead for an estimated activity level of 84,000 machine-hours. Required: 1. Assume that during the year the company works only 79,000 machine-hours and incurs the following costs in the Manufacturing Overhead and Work in Process accounts: Compute the amount of overhead...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis of machine hours. The company's predetermined overhead rate of $2.60 per machine-hour was based on a cost formula that estimates $260,000 of total manufacturing overhead for an estimated activity level of 100,000 machine-hours. Required: 1. Assume that during the year the company works only 95,000 machine-hours and incurs the following costs in the Manufacturing Overhead and Work in Process accounts: Compute the amount of...
Harwood Company uses a job-order costing system that applies
overhead cost to jobs on the basis of machine-hours. The company's
predetermined overhead rate of $2.80 per machine-hour was based on
a cost formula that estimates $232,400 of total manufacturing
overhead for an estimated activity level of 83,000
machine-hours.
Required:
1. Assume that during the year the company works only 78,000
machine-hours and incurs the following costs in the Manufacturing
Overhead and Work in Process accounts: Compute the amount of
overhead...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. The company's predetermined overhead rate of $2.60 per machine-hour was based on a cost formula that estimates $228,800 of total manufacturing overhead for an estimated activity level of 88,000 machine-hours. Required: 1. Assume that during the year the company works only 83,000 machine-hours and incurs the following costs in the Manufacturing Overhead and Work in Process accounts: Compute the amount of overhead...