A canal is proposed to run from Lake Isabella, California to Bakersfield, 100 km away. In these semi-desert conditions the water evaporation rate is expected to be 0.8 cm3/s for each m2 of water surface area. The canal is 10 m wide and the water is initially 3 m deep. Assume the initial flow rate of 0.2 m/s is constant throughout the canal. Your objective is to calculate the height of the water in the canal right after Bakersfield where they remove 2 m3/s.
Total length of canal is 1,000,00 meter which is 10 meter wide and 03 meter deep
total volume = 30,000,00 M3 and surface area is = 10,000,00 m2
Evaporation rate is = 0.8 cm3/s
Flow rate is = 0.2m/s
Total Time= 1,000,00m/5,000,00s
= 100km / 8333.33 min.
= 100km/138.88 hrs
Total evaporate water = 4,000,00 cm3 = 0.4 M3 from per square meter area and total area is 1,000,00 square meter, so total evaporate water is 40,000 cubic meter.
Total volume of water after 100km = 29,60,000 cubic meter.
Height of water in canal = 2.96meter
A canal is proposed to run from Lake Isabella, California to Bakersfield, 100 km away. In...
A pipeline to deliver 0.2 m3/s water from a river to a city 30 km away is to have pumps installed to cause the water to flow. The number n of equally spaced pumps is to be determined. The lifetime cost of a pump is $3000 $1.3(hp Kg/Nm)12 where the head rise hp provided by the pump is used to supply the head loss hu of turbulent now /hu ,friction factor f ~ 0.02)and the lifetime cost of the pipe...