Student Name (Print) 11) Estimate the actual bucket load in bank cubic yards for a loader...
Please solve problem 1 and show formulas used
Tables for reference:
Homework 6- Chapter 9 Problem 1: A crawler hoe having a 2 -cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under each of the stated conditions. The maximum digging depth of the machine is 22 ft. Determine the cost per bank cubic yard for each condition. (Condition 1: 315 bey/hr, S0.346/bcy; condition 2: 289 bey/hr, S0.377/bcy;...