Determine the number of cubic feet of concrete needed to pour two sets of the spread footings and piers shown in the figure below. Use a 10 percent waste factor.

Choices for QUESTION 2 :

A) 33 pounds

B) 26 pounds

C) 39 pounds

D) 24 pounds

Determine the number of cubic feet of concrete needed to pour two sets of the spread footings and piers shown in the figure b

0 0
Add a comment Improve this question Transcribed image text
Answer #1

→ 85) volume of footing 30x30x10 2 9000 cuin 25.21 cu.ft volume of piera lxlx 3 T 10 2 3 Cuift. Total volume e 5.21+ 3 2 8.2Length of each tie. 4x10 + 2x1 - 2 42 2 3.5 ft. #3 ties are at 3 oc. : No. of ties required - Total span a spacing 2 3 28

Add a comment
Know the answer?
Add Answer to:
Determine the number of cubic feet of concrete needed to pour two sets of the spread...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 11 (10 points): Determine the volume of concrete in cubic yards needed to complete 10...

    Question 11 (10 points): Determine the volume of concrete in cubic yards needed to complete 10 of the footings and columns shown below. Include 10% waste in the calculated volume of concrete, and express the volume of concrete in quarter-yard increments. You are required to show your work to receive the full credit. - 18" - BEA 6 REBAR 3 -0° #3 TES e 6" OCH - 18" -- 5 EA #STES е" actor AND BOTTOM 18" 3-0 BEA 95...

  • For the figure: Determine the volume of concrete in cubic yards, the square feet of forms and rebar needed to comple...

    For the figure: Determine the volume of concrete in cubic yards, the square feet of forms and rebar needed to complete the beam, only half of the beam shown in the figure with the other half being mirror image of the one shown. Include 5% waste in the calculated volume of concrete and express the volume of concrete in quatter-yard increment, provide 2" of cover for the rebar in the beam. Please answer as soon as possible... Determine the volume...

  • Based on Examples 1 and 3 in the lecture note, the amount of concrete poured, rebar,...

    Based on Examples 1 and 3 in the lecture note, the amount of concrete poured, rebar, and form used in continuous footings and foundation wall can be estimated. Show all your calculations by sending Excel file or hand calculation via Folio email. Determine the amount of rebar needed for the continuous footing shown in Figure above. Allow for two inches of cover. Add 10 percent for lap and waste to the continuous bars. #5 Dowel bar (                ) pounds #4...

  • How many cubic yards of concrete are needed to pour the highway support shown in the...

    How many cubic yards of concrete are needed to pour the highway support shown in the figure? (1 yd3 = 27 ft3.) (Round to nearest cubic yard.) Mathematics for the Trades: A Guided Approach, 10th Edition Problem sets 9 B # 2

  • Need Help explain in Details Determine the total amount of rebar (in pounds) needed for only...

    Need Help explain in Details Determine the total amount of rebar (in pounds) needed for only the spread footing in Figure 1. The dowels extend 24 inched into the column. Allow for three inches of cover. 6 rese "O 2014 O- 2014. NO POWELS OCMW TOPADRONOM The following table can be used in the calculation of reinforcement quantities. (http://www.engineeringtoolbox.com rebar-rods-weight-d 1709.html) Number Size (in) 0.250 = 14 0.375 = 3/8 0.500 = 1/2 0.625 = 5/8 0.750 = 3/4 0.875...

  • 1) Determine the number of 20-foot-long pieces of rebar that are needed to complete a 80-footlong...

    1) Determine the number of 20-foot-long pieces of rebar that are needed to complete a 80-footlong footing. The pieces are spliced with a lap of 2 feet and form a single bar running the length of the footing. Three inches of cover over the rebar is required at each end of the footing. Linear components should be rounded up to the next whole number to make sure that there are adequate materials.   2) Determine the volume of a 150 foot...

  • 3 4657.3 12. 12. How many cubic yards of concrete are needed to pour a slab...

    3 4657.3 12. 12. How many cubic yards of concrete are needed to pour a slab 60' x 80' × 5" thick? 13. 13. How many gallons of paint are required to paint one side of a block wall of the following dimensions: 6'x 172? The paint being used will cover 200 ft per gallon. 14. 14. Compute the gallons of sealer required to seal a floor 120 x 250. The sealer being used will cover 175 ft per gallon....

  • Determine the number of 8-inch-high by 8-inch-wide by 16-inch-long concrete (CMU) blocks required to complete 275...

    Determine the number of 8-inch-high by 8-inch-wide by 16-inch-long concrete (CMU) blocks required to complete 275 feet of the fence whose cross section is shown in Figure below. How many plain blocks and how many lintel blocks are needed for the wall? Show all your calculations by sending Excel file or hand calculation via Folio email. Question 21 options: Plain block: 2756 Linte block: 275 Plain block: 2835 Linte block: 414 Plain block: 2526 Linte block: 414 Plain block: 2526...

  • 5. Determine the number of 8-nch-high by B-inch-wide by I6-inch-long concrete blocks required to complete the...

    5. Determine the number of 8-nch-high by B-inch-wide by I6-inch-long concrete blocks required to complete the wall in Figures 23-2 and 23.3. The overhead doors are l0 feet wide by 12 feet high. If lintel blocks are required many lintel blocks are needed for the wal? wherever the #4 horizontal bars are located and above the doors, how many plain blocks and how 1T e4'0C 174" 17-4 80 Figure 23-2 Elevation Figure 23-3 Wall Section

  • Determine the number of square yards of carpet needed for the residence in Figure 16.15. The...

    Determine the number of square yards of carpet needed for the residence in Figure 16.15. The carpet is 12 feet wide. Figure 16.15. Residential Floor Plan. 4'-0" 32-0" + 5-9" — 8-9" 12-3" 12-6" 19-4" 2'-1" 26-0" 2'-1" 2' 1" -8-4" — 16-4" 13-6" 12'-10" 11'-6" -11'-6" 11-9" 36'-0" — MARK WINDOW SCHEDULE MARK SIZE DESCRIPTION @ 3'-0"x1'-0" VINYL SLIDER 4'-0"x4-0" VINYL SLIDER 5'-0"x4'-0" VINYL SLIDER DOOR SCHEDULE SIZE DESCRIPTION 3'-0"x6f-8" EXT. SOLID 3'-0"x6-8" | WOOD HOLLOW CORE 6'-0"x6'-8" |...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT