Question

E13-24 Direct labor variances Death Valley Bicycle Company manufactures mountain bikes. The following data for Octo- ber of t
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Based on the information available, we can calculate the following for Death Valley Bicycle company:-

a.) Direct Labor Rate variance

Direct labor rate variance = (Actual Rate - Standard Rate) * Actual Hours worked

Direct Labor rate variance = ($18.50 - $19) * 1100

Direct Labor Rate variance = $0.5 * 1100

Direct Labor Rate variance = $550

Because the actual rate of direct labor is lesser than the standard rate of direct labor, there is a favorable variance.

Hence, Direct Labor Rate variance = $550 Favorable.

b.) Direct labor time variance

Direct Labor time variance = (Actual Hours - Standard hours) * Standard Rate per hour

Standard hours for actual output = 3 hours * 350 units = 1,050 hours

Direct Labor time variance = (1,100 hours - 1,050 hours) * 19 per hour

Direct Labor time variance = 50 hours * 19 per hour

Direct Labor time variance = $950

Because the actual hours spent is higher than the standard hours allowed, there is an unfavorable time variance.

Direct Labor time variance = $950 Unfavorable.

Add a comment
Know the answer?
Add Answer to:
E13-24 Direct labor variances Death Valley Bicycle Company manufactures mountain bikes. The following data for Octo-...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Direct Labor Variances Alpine Bicycle Company manufactures road bikes. The following data for September of the...

    Direct Labor Variances Alpine Bicycle Company manufactures road bikes. The following data for September of the current year are available: Quantity of direct labor used 480 hrs. Actual rate for direct labor $10.5 per hr. Bicycles completed in September 230 Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $10.7 per hr. a. Determine the direct labor rate variance and direct labor time variance. Enter a favorable variance as a negative number using a minus sign and...

  • Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data...

    Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 750 hrs. Actual rate for direct labor $11.6 per hr. Bicycles completed in April 350 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $11.8 per hr. b. How much direct labor should be debited to Work in Process?

  • Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following da...

    Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 750 hrs. Actual rate for direct labor $11.6 per hr. Bicycles completed in April 350 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $11.8 per hr.

  • Direct Labor Variances Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for...

    Direct Labor Variances Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October of the current year are available: Quantity of direct labor used 470 hrs. Actual rate for direct labor $12.70 per hr. Bicycles completed in October 220 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $13.00 per hr. a. Determine for October the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a...

  • Direct Labor Variances Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for...

    Direct Labor Variances Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October are available: 5,000 hrs. Quantity of direct labor used Actual rate for direct labor $22.75 per hr. 800 bicycles Bicycles completed in October Standard direct labor per bicycle 6.0 hrs. Standard rate for direct labor $24.00 per hr. a. Determine for October the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a...

  • Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data...

    Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 740 hrs. Actual rate for direct labor $12.7 per hr. 350 bicycles Bicycles completed in April Standard direct labor per bicycle Standard rate for direct labor 2 hrs. $13 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...

  • Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data...

    Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 470 hrs. Actual rate for direct labor $12.6 per hr. Bicycles completed in April 220 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $12.9 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...

  • Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data...

    Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 640 hrs. Actual rate for direct labor $13.7 per hr. Bicycles completed in April 300 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $14 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...

  • Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data...

    Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 470 hrs. Actual rate for direct labor $10.6 per hr. Bicycles completed in April 220 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $10.8 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...

  • Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data...

    Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: 610 hrs Quantity of direct labor ussed $14.4 per hr Actual rate for direct labor 290 bicycles Bicycles completed in April 2 hrs Standard direct labor per bicycle Standard rate for direct labor $14.7 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT