Answer a)
Throughput Time = Time for (Blend + Rest + Cook + Wrap&Box) =
0.75+0.5+1+0.75 = 3 hrs
Answer b)
Wrap & Box process is the bottleneck, because its throughput
rate is lesser than the combined throughput rates of the Baking
lines.
For example, if both baking lines are started simultaneously at 8am
in the morning,
1. The first batches of 350 Biscuits will pass the 'Blend' stage at
8:45 hrs in both the lines.
2. The same batch will pass the 'Rest' stage at 9:15 hrs in both
the lines
3. The same batch will pass the 'Cook' stage at 10:15 hrs in both
the lines
4. Now we have a total of 700 biscuits at the Wrap & Box stage,
out of which only 350 will be processed in next 0.75 hrs.
Answer C) With Cook stage being the slowest within
the Baking process, the hourly capacity will be dependent on how
much the Cook stage produces every hour.
The Cook stage - as we see, can produce a batch of 350 per biscuits
on each individual production line.
So,
Hourly capacity of just the baking process = 2 batches (of
350 biscuits) per hour = 700 biscuits
Answer d)
If the bakery operates 6 days per week and 8 hours per
day.
The total working hours per week will be = 6*8 = 48 hrs per
week.
bottleneck process = Wrap & Box
Capacity of 'Wrap & Box' process = 350 biscuits in every 0.75
hrs
Hourly capacity of 'Wrap & Box' process = 350 / 0.75 =
466.667
Weekly capacity of 'Wrap & Box' process = (Hourly capacity of
'Wrap & Box' process) * (total working hours per week)
= 466.667 * 48 = 22400
Thus , Weekly capacity of entire process = 22400 biscuits
Dear Student,
Please ask, if you have any doubts through the comment section.
Do rate the answer.
Problem 4 (20 points) The diagram below depicts the process for making gourmet biscuits at a...
A diagram of a face-to-face service process is given below. There are four workstations (called "operations"), each performing a different task with a single server at each. The expected demand is λ.-25 units per hour. Clerk B Clerk C Clek D w仍 OPI 40 cistomers bour bout 5. Determine the process times (in seconds per unit) for each of the activities. (2 pts) 6. Identify the bottleneck stage and determine the process capacity. (2 pts) 7. If the expected amount...
1. The process is performed by several resources. 2. Resources are shared across assembly lines (i.e., workers must multitask and perform multiple activities for every flow unit.) 3. The resource that limits hourly production is not the same resource that limits the process lead-time. From 2002 to 2009, Honda’s 1800cc cruiser-style motorcycle, the VTX1800, was assembled in Marysville, Ohio from four major subassemblies. The following is a simplified explanation of the assembly process. All resources are indicated in bold. •...
Problem 4 (16 points) Consider a typical patient's stay in the emergency department (ED). On average, 10 patients arrive to the ED per hour. Triage: Once a patient arrives, he/she is first triaged at the triage station which is staffed with one triage nurse. The triage process takes 5 minutes on average. Initial Consultation: After triage, the patient goes through initial consultation with a nurse who takes information on the patient's demographics, medical history, allergies, etc. On average, initial consultation...