We are evaluating a project that costs $520,000, has a six-year
life, and has no salvage value. Assume that depreciation is
straight-line to zero over the life of the project. Sales are
projected at 65,000 units per year. Price per unit is $45, variable
cost per unit is $30, and fixed costs are $840,000 per year. The
tax rate is 35 percent, and we require a return of 10 percent on
this project. Suppose the projections given for price, quantity,
variable costs, and fixed costs are all accurate to within ±10
percent.
Calculate the best-case and worst-case NPV figures. (A negative
answer should be indicated by a minus sign. Do not round
intermediate calculations and round your answers to 2 decimal
places, e.g., 32.16.)
a. Best-case $584,621, worst case $ –$285,079 b. Best-case
$2,026,176.65, worst case $ –$1,761,593.58 c. Best-case $88,832.77,
worst case –$1,510,000 d. None of the above
When I calculated it myself I got :
worst case -$1,761,594.09
best case $2,026,176.14
If you notice it is very close to answer b so I am asking you to calculate it to see if you get a different answer than I did, or am I correct? Thank you
First we calculate the CF for each scenario:
| Base Case | Best Case | Worst Case | |||
| Particular | Remark | Year 0 | Year 1-6 | Year 1-6 | Year 1-6 |
| Units | Given | $ 65,000.00 | $ 71,500.00 | $ 58,500.00 | |
| SP | Given | $ 45.00 | $ 49.50 | $ 40.50 | |
| Sales | Sp x Units | $ 29,25,000.00 | $ 35,39,250.00 | $ 23,69,250.00 | |
| VC | Given | $ 30.00 | $ 27.00 | $ 33.00 | |
| Total VC | Vc x Units | $ 19,50,000.00 | $ 19,30,500.00 | $ 19,30,500.00 | |
| Fixed cost | Given | $ 8,40,000.00 | $ 7,56,000.00 | $ 9,24,000.00 | |
| EBITDA | Sale-Total VC-Fixed Cost | $ 1,35,000.00 | $ 8,52,750.00 | $ -4,85,250.00 | |
| Depreciation | 520000/6 | $ 86,666.67 | $ 86,666.67 | $ 86,666.67 | |
| EBIT | EBITDA-Depreciation | $ 48,333.33 | $ 7,66,083.33 | $ -5,71,916.67 | |
| tax | 0.35 x EBIT | $ 16,916.67 | $ 2,68,129.17 | $ -2,00,170.83 | |
| EAT | EBIT-tax | $ 31,416.67 | $ 4,97,954.17 | $ -3,71,745.83 | |
| Depreciation | Added Back as non cash | $ 86,666.67 | $ 86,666.67 | $ 86,666.67 | |
| OCF | EAT+Depreciation | $ 1,18,083.33 | $ 5,84,620.83 | $ -2,85,079.17 | |
| Investment | Given | $ -5,20,000.00 | |||
| CF | $ -5,20,000.00 | $ 1,18,083.33 | $ 5,84,620.83 | $ -2,85,079.17 |
Now we will calculate the NPV of each scenario:
Base case:
| Year | CF | Discount Factor | Discounted CF | ||
| 0 | $ -5,20,000.00 | 1/(1+0.1)^0= | 1 | 1*-520000= | $ -5,20,000.00 |
| 1 | $ 1,18,083.33 | 1/(1+0.1)^1= | 0.909090909 | 0.909090909090909*118083.333333333= | $ 1,07,348.48 |
| 1 | $ 1,18,083.33 | 1/(1+0.1)^1= | 0.909090909 | 0.909090909090909*118083.333333333= | $ 1,07,348.48 |
| 3 | $ 1,18,083.33 | 1/(1+0.1)^3= | 0.751314801 | 0.751314800901578*118083.333333333= | $ 88,717.76 |
| 4 | $ 1,18,083.33 | 1/(1+0.1)^4= | 0.683013455 | 0.683013455365071*118083.333333333= | $ 80,652.51 |
| 5 | $ 1,18,083.33 | 1/(1+0.1)^5= | 0.620921323 | 0.620921323059155*118083.333333333= | $ 73,320.46 |
| 6 | $ 1,18,083.33 | 1/(1+0.1)^6= | 0.56447393 | 0.564473930053777*118083.333333333= | $ 66,654.96 |
| NPV = Sum of all Discounted CF | $ 4,042.65 | ||||
Best case:
| Year | CF | Discount Factor | Discounted CF | ||
| 0 | $ -5,20,000.00 | 1/(1+0.1)^0= | 1 | 1*-520000= | $ -5,20,000.00 |
| 1 | $ 5,84,620.83 | 1/(1+0.1)^1= | 0.909090909 | 0.909090909090909*584620.833333334= | $ 5,31,473.48 |
| 1 | $ 5,84,620.83 | 1/(1+0.1)^1= | 0.909090909 | 0.909090909090909*584620.833333334= | $ 5,31,473.48 |
| 3 | $ 5,84,620.83 | 1/(1+0.1)^3= | 0.751314801 | 0.751314800901578*584620.833333334= | $ 4,39,234.28 |
| 4 | $ 5,84,620.83 | 1/(1+0.1)^4= | 0.683013455 | 0.683013455365071*584620.833333334= | $ 3,99,303.90 |
| 5 | $ 5,84,620.83 | 1/(1+0.1)^5= | 0.620921323 | 0.620921323059155*584620.833333334= | $ 3,63,003.54 |
| 6 | $ 5,84,620.83 | 1/(1+0.1)^6= | 0.56447393 | 0.564473930053777*584620.833333334= | $ 3,30,003.22 |
| NPV = Sum of all Discounted CF | $ 20,74,491.91 | ||||
Worst Case:
| Year | CF | Discount Factor | Discounted CF | ||
| 0 | $ -5,20,000.00 | 1/(1+0.1)^0= | 1 | 1*-520000= | $ -5,20,000.00 |
| 1 | $ -2,85,079.17 | 1/(1+0.1)^1= | 0.909090909 | 0.909090909090909*-285079.166666667= | $ -2,59,162.88 |
| 1 | $ -2,85,079.17 | 1/(1+0.1)^1= | 0.909090909 | 0.909090909090909*-285079.166666667= | $ -2,59,162.88 |
| 3 | $ -2,85,079.17 | 1/(1+0.1)^3= | 0.751314801 | 0.751314800901578*-285079.166666667= | $ -2,14,184.20 |
| 4 | $ -2,85,079.17 | 1/(1+0.1)^4= | 0.683013455 | 0.683013455365071*-285079.166666667= | $ -1,94,712.91 |
| 5 | $ -2,85,079.17 | 1/(1+0.1)^5= | 0.620921323 | 0.620921323059155*-285079.166666667= | $ -1,77,011.73 |
| 6 | $ -2,85,079.17 | 1/(1+0.1)^6= | 0.56447393 | 0.564473930053777*-285079.166666667= | $ -1,60,919.76 |
| NPV = Sum of all Discounted CF | $ -17,85,154.35 | ||||
So the correct answer is none of the above
We are evaluating a project that costs $520,000, has a six-year life, and has no salvage...
We are evaluating a project that costs $744,000, has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 45,000 units per year. Price per unit is $60, variable cost per unit is $20, and fixed costs are $740,000 per year. The tax rate is 35 percent, and we require a return of 18 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $788,400, has a nine-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 75,000 units per year. Price per unit is $52, variable cost per unit is $36, and fixed costs are $750,000 per year. The tax rate is 21 percent, and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $569,100, has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 85,000 units per year. Price per unit is $40, variable cost per unit is $26, and fixed costs are $690,000 per year. The tax rate is 24 percent, and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $2,070,000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 93,400 units per year. Price per unit is $38.73, variable cost per unit is $23.85, and fixed costs are $854,000 per year. The tax rate is 23 percent and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $1,160,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 39,000 units per year. Price per unit is $41, variable cost per unit is $20, and fixed costs are $645,000 per year. The tax rate is 35 percent, and we require a return of 20 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $1,120,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight- line to zero over the life of the project. Sales are projected at 64,000 units per year. Price per unit is $50, variable cost per unit is $25, and fixed costs are $620,000 per year. The tax rate is 35 percent, and we require a return of 12 percent on this project. Suppose the projections given for price,...
We are evaluating a project that costs $2,010,000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 89,400 units per year. Price per unit is $38.61, variable cost per unit is $23.75, and fixed costs are $848,000 per year. The tax rate is 21 percent and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $2.130,000, has a 8-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 90,600 units per year. Price per unit is $38.85, variable cost per unit is $23.95, and fixed costs are $860,000 per year. The tax rate is 25 percent and we require a return of 11 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $788,400, has a nine-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 75,000 units per year. Price per unit is $52, variable cost per unit is $36, and fixed costs are $750,000 per year. The tax rate is 21 percent, and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $2,040,000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 89,700 units per year. Price per unit is $38.67, variable cost per unit is $23.80, and fixed costs are $851,000 per year. The tax rate is 22 percent and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...