Ans A) Project B is favourable as per NPV, as Project B has higher NPV.
NPV Project A = 9231.04
NPV Project B = 12092.13
Refer below table for calculation.
| 0 | 1 | 2 | 3 | 4 | 5 | |
| Project A | -50000 | 15625 | 15625 | 15625 | 15625 | 15625 |
| PV Factorat 10% | 1/1.1 | 1/1.1^2 | 1/1.1^3 | 1/1.1^4 | 1/1.1^5 | |
| PV | -50000 | 14204.55 | 12913.22 | 11739.29 | 10672.09 | 9701.896 |
| NPV (Sum of PV) | 9231.043 | |||||
| 0 | 1 | 2 | 3 | 4 | 5 | |
| Project B | -50000 | 0 | 0 | 0 | 0 | 100000 |
| PV Factorat 10% | 1/1.1 | 1/1.1^2 | 1/1.1^3 | 1/1.1^4 | 1/1.1^5 | |
| PV | -50000 | 0 | 0 | 0 | 0 | 62092.13 |
| NPV (Sum of PV) | 12092.13 |
Ans B) IRR of Project A is 16.99% or 17% so this is true if rounded off.
IRR is a point where where PV of inflows is equals to outflows or PV of Inflows minus outflow is zero.
IRR = - 50000 + 15625/ (1+r)^1 + 15625/ (1+r)^2 + 15625/ (1+r)^3 + 15625/ (1+r)^4 + 15625/ (1+r)^5 = 0
solving this equation r = 16.99%
Ans C) IRR of Project B = 14.87%
IRR of B = -50000+ 100000 / (1+r)^5 =
(1+r)^5 * 50000 = 100000 or (1+r)^5 = 2
or (1+0.1487)^5 = 2.00 or r = 14.87%
Ans D) IRR and NPV both are different medium to evaluation a project . NPV look at surpluses flows from a project , while IRR is mostly all about the rate of return getting to breakeven cash flow from a project.
Ans E) Project B should be accepted as Project has higher NPV. Higher NPV projects will create more value to the firm.
Hope this helps, thanks and have a good day. Feel free to share your feedback.
11. Acompany is considering two mutually excdlusive srsjects The frec with these projects are as follows...
A firm is considering two mutually exclusive projects with equal lives, Project A has an NPV of $100,000, an IRR of 12%, and a payback period of 3.1 years. Project B has an NPV of $120,000, an IRR of 14%, and a payback period of 2.8 years. The firm should choose________. Question 34 options: 1) Project A because its NPV is higher than Project B's 2) Project A because its payback period is longer than Project B's 3) Project B...
call U Lise Blueprint Problems Ch 11 Brigham Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all Included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is...
(Risk-adjusted NPV) The Hokie Corporation is considering two mutually exclusive projects. Both require an initial outlay of $13,000 and will operate for 9 years. Project A will produce expected cash flows of $4,000 per year for years 1 through 9 whereas project B will produce expected cash flows of $5,000 per year for years 1 through 9. Because project B is the riskier of the two projects, the management of Hokie Corporation has decided to apply a required rate of...
X Blueprint Problems Ch 11 Brigham 0 Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 12%....
(Risk-adjusted NPV) The Hokie Corporation is considering two mutually exclusive projects. Both require an initial outlay of $12,000 and wil operate for 8 years Project A will produce expected cash flows of $8,000 per year for years 1 through 8, whereas project will produce expected cash flows of 9,000 per year for years through 8. Because project B is the riskler of the two projects, the management of Hokie Corporation has decided to apply a required rate of return of...
(Risk-adjusted NPV)The Hokie Corporation is considering two mutually exclusive projects. Both require an initial outlay of $10,000 and will operate for 7 years. Project A will produce expected cash flows of $5,000 per year for years 1 through 7, whereas project B will produce expected cash flows of $6,000 per year for years 1 through 7. Because project B is the riskier of the two projects, the management of Hokie Corporation has decided to apply a required rate of return...
Newfoundland Vintners Co-operative is considering two mutually exclusive projects: Absinth and Brandy. Project Absinth requires a $20,000 cash outlay today and is expected to generate after-tax cash flows of $11,000 in year 1, $8,500 in year 2, and $7,500 in year 3. Project Brandy requires a $30,000 cash outlay today and is expected to generate after-tax cash flows of $7,000 in year 1, $9,000 in year 2, $11,000 in year 3, and $16,000 in year 4. Neither project can be...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below Depreciation, salvage values, net operating working capital requirements, and tax effects are al ncluded in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC Is 996. 650 250 320 255 270 420 390...
The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $6,500 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $5,750 0.2 $0 0.6 $6,500 0.6 $6,500 0.2 $7,250 0.2 $19,000 BPC has decided to evaluate the riskier project at 11% and the less-risky project at 9%. The...
Thomas Company is considering two mutually exclusive projects. The firm has a 12% cost of capital. Cash inflows Initial investment Year 1 Year 2 Year 3 Year 4 Year 5 Project A Project B $130000 $85000 $25000 $35000 $45000 $50000 $55000 $40000 $35000 $30000 $10000 $5000 Evaluate and discuss the rankings of NPV and IRR of the two projects on the basis of your finding. O A Project B should be chosen because it has a higher IRR than Project...