1)
Predetermined overhead rate =Estimated overhead /Estimated activity(direct labor hours)
| Fixed predetermined overhead rate | 9360/9000=$ 1.04 per DLH |
| Variable predetermined overhead rate | 12330/9000 =$ 1.37 per DLH |
| Total predetermined overhead rate | 2.41 per DLH |
2)
Fixed overhead volume variance =Fixed predetermined overhead rate(Budgeted hours-standard hours)
1.04 (9000-9400)
1.04 *-400
= - 416 F (Enter as 416 F)
Fixed overhead spending variance =Actual fixed overhead -Budgeted fixed overhead
= 9430 - 9360
= 70 U
Variable overhead price variance= Actual variable overhead - (Actual hours*Variable predetermined overhead rate)
= 10870- (10600*1.37)
= 10870 - 14522
= - 3652 F (enter as 3652F)
**variable overhead actual =20300-9430=10870
4)
Variable overhead quantity variance = Variable predetermined overhead rate(AH-SH)
= 1.37 (10600-9400)
= 1.37 *1200
= 1644 U
5)Total variance = -416 F +70U +(-3652F) +1644U
= -2354 F (enter as 2354F)
EWWIELS Helir n Jj , Managerial Accounting, Fifth Canadian Edition Concordia: Managerial Accounting (COMM 305 Practice...
Mercuri Company has gathered the following information:
Variable manufacturing overhead costs
$13,680
Fixed manufacturing overhead costs
$10,710
Normal production level in labour hours
9,000
Standard labour hours
9,500
During the year, 3,050 units were produced, 10,900 hours were
worked, and the actual manufacturing overhead was $21,800. Actual
fixed overhead totalled $10,800.
Mercuri applies overhead based on direct labour hours.
Calculate the total, fixed, and variable predetermined overhead
rates.(Round answers to 2 decimal places, e.g.
15.25.)
Fixed predetermined ovehead rate
$...
Jay Levitt Company budgeted the following cost standards for
the current year:
Direct materials (2 kg of
plastic at $6 per kilogram)
$12.00
Direct labour (2 hours at $12
per hour)
24.00
Variable manufacturing
overhead
11.90
Fixed manufacturing
overhead
6.25
Total standard cost per
unit
$54.15
Actual costs for producing 2,740 units were as follows:
Direct materials used
5,560
kg
Direct materials purchased
(6,780 kg)
$40,002
Direct labour (6,880 hours)
$67,424
Variable manufacturing
costs
$32,600
Fixed manufacturing costs
$17,600
Your...
Question 24 Rondell Company uses standard cost system. Indirect costs were budgeted at $190,800 plus $13 per direct labour hour. The overhead rate is based on 10,600 hours. Actual results were: Standard direct labour hours allowed Actual direct labour hours Fixed overhead Variable overhead 9,070 10,600 $179,000 $174,400 Calculate the fixed overhead production volume variance. Fixed overhead production volume variance Calculate the variable overhead spending variance. Variable overhead spending variance $ Calculate the variable overhead efficiency variance. Variable overhead efficiency...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,600 units. Manufacturing overhead is budgeted at $120,400 for the period (20% of this cost is fixed). The 16,500 hours worked during the period resulted in the production of 8,170 units. The variable manufacturing overhead cost incurred was $97,400 and the fixed manufacturing overhead cost was $28,900. Partially correct answer. ...
Waterways Continuing Problem 12
At the end of June the manager of the B.C. manufacturing plant
was provided with the following variance analysis report:
Budget
Actual
Variance
Favourable (F)/
Unfavourable (U)
Production in units
332,000
347,000
15,000
F
Production costs:
Direct material
$996,000
$1,017,940
$(21,940)
U
Direct labour
1,411,000
1,442,700
(31,700)
U
Variable overhead costs
166,000
172,957
(6,957)
U
Fixed overhead costs
174,300
168,620
5,680
F
Total production costs
$2,747,300
$2,802,217
$(54,917)
U
The manager immediately called the production supervisor,...
show calculations and work
BED Return to Blackboard Weygandt, Managerial Accounting, Fifth Canadian Edition PRINTER VERSION « BACK Question 3 Mozena Corporation manufactures a single product. Monthly production costs incurred in the manufacturing process are shown below for the production of 3,800 units. The utilities and maintenance costs are mixed costs. The fixed portions of these costs are $430 and $270, respectively. Production in Units 3,800 Production Costs Direct materials $7,904 Direct labour 15,124 Utilities 1,798 Property taxes 1,180 Indirect...
Mark: 19 (1 point for each question) 1) The unemployment rate is high in the city in which a company has a factory. The company finds that they are able to pay new employees a lower wage per hour than when the unemployment rate was lower a year ago. Which variance is directly impacted? A) Materials price variance B) Materials efficiency variance C) Labour price variance D) Labour efficiency variance 2) Thomas Corporation produces stopwatches. According to company standards, it...
fill in the missing numbers
Consider the following data provided for each of the following independent cases. For each case assume that the business uses a standard cost system and a flexible budget to control variable and fixed manufacturing overhead, and applies manufacturing overhead on the basis of direct labour hours. Fill in the blanks for each case, and indicate whether the variances are favourable (F) or unfavourable (U). Phi Company Pho Company Number of labour hours budgeted $10,600 hrs...
11.25Overhead variances: manufacturer LO5] standard manufacturing overhead costs per switch are based on direct 1abour hours and are a& follows Bright Spark Ltd is a manufacturer of electrical switches, and uses a standard costing system. The Variable overhead (5 hours$12 per hour) Fixed overhead (5 hours@$18 per hour)* Total overhead $ 60 90 $150 Based on capacity 300000 irect labour hours per month The following information is available for the month of October: 56000 switches were produced, although 60000 switches...
The overhead budget for Hugh Demand Ltd for the year to 30 June 2016 wasestimated on 20,000 direct labour hours. Using this base, the overhead recovery rate per direct labour hour was determined as: Fixed costs ($216,000) $10.80 Variable costs $ 8.10 $18.90 Actual results achieved for the year were: Fixed costs $220,500 Variable costs $170,940 Direct labour hours 21,000 hours Required: Calculate the factory overhead spending (budget) variance and capacity(volume) variance. Specify whether the Spending Variance and the...