P20%A Challenge Prolen NAME De Nat Find the forte thet will ac b) fl the narmal...
What is the probability that the project will be completed within: (a) 21 days? (b) 22 days? (c) 25 days? Activity* a mb АВЗ AC св CD 3 3 3 CE BD 0 0 6 BE DF DE EF 4 4 10 Find: (a) the critical path; (b) all event slacks; (c) critical path to event D; (a) probability of completion in 14 days (e) the effect if CD slips to 6 days, to 7 days; to 8 days.