The Burdell Company is a small manufacturing company that uses gear assemblies to produce four different models of mountain bikes. One of these gear assemblies, the "Smooth Shifter", is used for the two most expensive of Burdell's four models, and has an estimated weekly demand of 7 units. Currently, this assembly is purchased in lots of 100 units. Burdell estimates the cost to place an order is $40, and the holding cost for each assembly is $5/unit/month. The company operates 300 days per year. (Assume 1 year = 12 months = 52 weeks)
a. What is the total annual cycle-inventory cost based on current ordering policy?
Answers to A and B are below
b. What is the economic order quantity for this assembly?
c.What is the total annual cycle-inventory cost based on EOQ policy?
d. What is the time between orders measured in days, if EOQ policy is used?
a:
| Annual demand, D= | 7*52 weeks | 364 |
| Order cost or setup cost, S | $40 | |
| holding cost per year, H= | $60.00 | |
| Order quantity, Q= | 100 | |
| annual holding cost= | Q*H/2 | $3,000.0 |
the total annual cycle-inventory cost based on current ordering policy= $3000
| demand per week | 7 | ||
| Days per year= | 300 | ||
| Annual demand, D= | 7*52 | 364 | |
| Order cost or setup cost, S | $40 | ||
| holding cost per year, H= | $60.00 | ||
| Answer b | Economic Order quantity, Q= | squareroot(2*S*D/H) | 22 |
| #orders per year = | D/Q | 16.52 | |
| Answer c | annual holding cost= | Q*H/2 | $660.9 |
| Answer d | order cycle= | days per year/orders per year | 18.16 |
The Burdell Company is a small manufacturing company that uses gear assemblies to produce four different...
The Boilermakers is a manufacturing company that uses gear assemblies to produce four different models of mountain bikes. One of these gear assemblies, the "Smooth Shifter," is used for the two most expensive models, and has an estimated annual demand of 540 units. The Boilermakers estimates the cost to place an order is $100, and the holding cost for each assembly is $10 per month. a) Currently, not knowing about EOQ, the purchasing manager places an order for the Smooth...
The Talbot Company uses electrical assemblies to produce an array of small appliances. One of its high cost / high volume assemblies, the XO-01, has an estimated annual demand of 8,000 units. Talbot estimates the cost to place an order is $50, and the holding cost for each assembly is $10 per year. The company operates 250 days per year. What is the total annual holding and ordering cost if Talbot orders using the Economic Order Quantity (EOQ)?
The Talbot Company uses electrical assemblies to produce an array of small appliances. One of its high cost / high volume assemblies, the XO-01, has an estimated annual demand of 8,000 units. Talbot estimates the cost to place an order is S50, and the holding cost for each assembly is S20 per year. The company operates 250 days per year.
Eagle Insurance is a large insurance company chain with a central inventory operation. The company’s fastest-moving inventory item has a demand of 80,000 units per year. The cost of each unit is $200, and the inventory carrying cost is $15 per unit per year. The average ordering cost is $60 per order. It takes about 2 days for an order to arrive. This is a corporate operation, and there are 250 working days per year. (Please show all work including...
Thomas Kratzer is the purchasing manager for the headquarters of a large insurance company chain with a central inventory operation. Thomas’s fastest moving inventory item has a demand of 6000 units per year. The cost of each unit is $100.00, and the inventory carrying cost is $10.00 per unit per year. The average ordering cost is $30.00 per order. It takes about 5 days for an order to arrive, and demand for 1 week is 120 units (this is a...
Rudd Company uses 40,000 micro-chips each year in its production of digital cameras. The of placing an order is $75. The cost of holding one unit of inventory for one year is $8. Currenty Rudd places 20 orders of 2,000 units per order. cost Compute: (a) The annual ordering cost. (2 marks) (2 marks) (2 marks) (2 marks) (b) The annual carrying cost. (c) The total cost of Rudd's current inventory policy. (d) The economic order quantity. (e) The order...
4a. A computer company has annual demand of 100,000. They want to determine EOQ for circuit boards which have an annual holding cost (H) of $10/unit, and an ordering cost (S) of $200. What is the EOQ? 2000 4b. A computer company has annual demand of 100,000. They want to determine EOQ for circuit boards which have an annual holding cost (H) of $10/unit, and an ordering cost (S) of $200. What is the total annual inventory cost (setup and...
My Manufacturing is involved in the production of machine parts. The company uses 600,000 pounds of steel annually. The current purchasing cost for steel is $3.20 per pound. The carrying cost for inventory is 10 percent of the purchase price. The cost of ordering steel is $800 per order. The company has decided to maintain a safety stock of 15,000 pounds. The delivery time per order is 6 days. The company works 365 days a year. A) What is the...
Teck is a Canadian metal mining and processing company with new investments in coal and oil. The company has several warehouses in Western Canada that store thousands of parts and supplies for the machines and equipment used in its mines and operations. The stocks in the warehouses are controlled using computers in the Vancouver head office. For spare parts, the EOQ/ROP model is used. The following data is the usage of specific spare part during a nine-month period: Jan Feb...
Joe Henry's machine shop uses 2,450 brackets during the course of a year. These brackets are purchased from a supplier 90 miles away. The following information is known about the brackets: Annual demand Holding cost per bracket per year Order cost per order Lead time Working days per year 2,450 $1.35 $18.00 2 days 250 a) What is the EOQ? 255.60 units (round your response to two decimal places). b)What is the average inventory if the EOQ is used? 127.80...