| 1 | |||
| Maintenance cost in July = 257600-(67500/45000*75000)-49000= 96100 | |||
| 2 | |||
| Machine hours | Maintenance cost | ||
| High level | 75000 | 96100 | |
| Low level | 45000 | 63100 | |
| Change | 30000 | 33000 | |
| Variable cost = 33000/30000= $1.1 | |||
| Fixed cost = 96100-(75000*1.1) = $13600 | |||
| Y = 13600+1.1X | |||
| 3 | |||
| Variable cost | Fixed cost | ||
| Utilities | 1.5 | ||
| Supervisory salaries | 49000 | ||
| Maintenance cost | 1.1 | 13600 | |
| 2.6 | 62600 | ||
| Y = 62600+2.6X | |||
| 4 | |||
| Total overhead cost = 62600+(50000*2.6)= 192600 | |||
Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month...
Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month April May June July Cost Hours 49,000190,590 39,000 $165,490 59,000215, 690 69,000 240,790 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 50,700 49,000 65,790 $165,490 Nova Company's management wants to break down the maintenance...
Nova Company's total overhead cost at various levels of activity are presented below. Month April MAY June July Machine- Hours 51.000 41.000 61,000 71,000 Total Overhead Cost $ 181,310 $ 158,210 $ 204, 410 $227,510 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 49,200 51,000 58,010 $158,210 Nova Company's management...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 46,000 36,000 56,000 66,000 Total Overhead Cost $ 186,020 $ 161,820 $ 210,220 $ 234, 420 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 43, 200 60,000 58,620 $ 161,...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 51,000 41,000 61,000 71,000 Total Overhead Cost $ 208, 040 $ 182,640 $ 233, 440 $ 258, 840 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 53,300 63,000 66,340 $182,640...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 45,000 35,000 55,000 65,000 Total Overhead Cost $ 192,900 $ 166,900 $ 218,900 $ 244,900 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 49,000 60,000 57,900 $ 166,900 Nova Company's...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 53,000 43,000 63,000 73,000 Total Overhead Cost $ 215, 940 $ 189, 140 $ 242,740 $ 269,540 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 43,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 64,500 55,000 69,640 $189, 140...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 50,000 40,000 60,000 70,000 Total Overhead Cost $ 187,300 $ 161,500 $ 213,100 $ 238,900 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 40,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 56,000 45,000 60,500 $161,500 Nova Company's management...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 54,000 44,000 64,000 74,000 Total Overhead Cost $ 196,260 $ 171,860 $ 220,660 $ 245,060 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 57,200 45,000 69,660 $171,860 Nova Company's management...
Nova Company's total overhead cost at various levels of activity are presented below: Total Machine- Overhead Hours 45,000 35,000 55,000 65,000 Month Cost S 185,650 $ 160,350 $ 210,950 $ 236,250 April May June July Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000 machine-hour level of activity is: $ 45,500 54,000 60,850 $160,350 Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost Nova Company's management...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 47,000 $ 192,050 May 37,000 $ 168,550 June 57,000 $ 215,550 July 67,000 $ 239,050 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: Utilities (variable) $ 48,100 Supervisory salaries (fixed) 66,000 Maintenance (mixed) 54,450 Total overhead cost $ 168,550 Nova Company’s...