Nova Companys total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month April May June July Hours Cost 55,000 205,600 45,000179,600 65,000 75,000 ş 231,600 ş 257,600 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 45,000 machine-hour level of activity is Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $67,500 49,000 63,100 $179,600 Nova Companys management wants to break down the maintenance cost into its variable and fixed cost elements Required 1. Estimate how much of the $257,600 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $257600 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) 2. Using the high-low method, estimate a cost formula for maintenance in the form Y=a + bX. 3. Express the companys total overhead cost in the form Y=a + bX. 4. What total overhead cost would you expect to be incurred at an activity level of 50,000 machine-hours?

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1
Maintenance cost in July = 257600-(67500/45000*75000)-49000= 96100
2
Machine hours Maintenance cost
High level 75000 96100
Low level 45000 63100
Change 30000 33000
Variable cost = 33000/30000= $1.1
Fixed cost = 96100-(75000*1.1) = $13600
Y = 13600+1.1X
3
Variable cost Fixed cost
Utilities 1.5
Supervisory salaries 49000
Maintenance cost 1.1 13600
2.6 62600
Y = 62600+2.6X
4
Total overhead cost = 62600+(50000*2.6)= 192600
Add a comment
Know the answer?
Add Answer to:
Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month...

    Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month April May June July Cost Hours 49,000190,590 39,000 $165,490 59,000215, 690 69,000 240,790 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 50,700 49,000 65,790 $165,490 Nova Company's management wants to break down the maintenance...

  • Nova Company's total overhead cost at various levels of activity are presented below. Month April MAY...

    Nova Company's total overhead cost at various levels of activity are presented below. Month April MAY June July Machine- Hours 51.000 41.000 61,000 71,000 Total Overhead Cost $ 181,310 $ 158,210 $ 204, 410 $227,510 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 49,200 51,000 58,010 $158,210 Nova Company's management...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 46,000 36,000 56,000 66,000 Total Overhead Cost $ 186,020 $ 161,820 $ 210,220 $ 234, 420 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 43, 200 60,000 58,620 $ 161,...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 51,000 41,000 61,000 71,000 Total Overhead Cost $ 208, 040 $ 182,640 $ 233, 440 $ 258, 840 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 53,300 63,000 66,340 $182,640...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 45,000 35,000 55,000 65,000 Total Overhead Cost $ 192,900 $ 166,900 $ 218,900 $ 244,900 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 49,000 60,000 57,900 $ 166,900 Nova Company's...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 53,000 43,000 63,000 73,000 Total Overhead Cost $ 215, 940 $ 189, 140 $ 242,740 $ 269,540 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 43,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 64,500 55,000 69,640 $189, 140...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 50,000 40,000 60,000 70,000 Total Overhead Cost $ 187,300 $ 161,500 $ 213,100 $ 238,900 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 40,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 56,000 45,000 60,500 $161,500 Nova Company's management...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 54,000 44,000 64,000 74,000 Total Overhead Cost $ 196,260 $ 171,860 $ 220,660 $ 245,060 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 57,200 45,000 69,660 $171,860 Nova Company's management...

  • Nova Company's total overhead cost at various levels of activity are presented below: Total Machine- Overhead...

    Nova Company's total overhead cost at various levels of activity are presented below: Total Machine- Overhead Hours 45,000 35,000 55,000 65,000 Month Cost S 185,650 $ 160,350 $ 210,950 $ 236,250 April May June July Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000 machine-hour level of activity is: $ 45,500 54,000 60,850 $160,350 Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost Nova Company's management...

  • Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...

    Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 47,000 $ 192,050 May 37,000 $ 168,550 June 57,000 $ 215,550 July 67,000 $ 239,050 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: Utilities (variable) $ 48,100 Supervisory salaries (fixed) 66,000 Maintenance (mixed) 54,450 Total overhead cost $ 168,550 Nova Company’s...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT