can you explain how to fo the mean variance wnd z score and st dev each path
Problem 17-11 The following precedence diagram reflects three time estimates for each activity. Determine: Use Table B1 and T
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The expected time for each activity & variance of activity are calculated in the table below each bi O O Activity optimisticpath 1 + 27 3 8 11 find mean, vañance, & sd for this path we get, vanance Path 172 Mean 8 1378 8 Yll 12 10, 16.7 7.1667 0.25path 1727 4 7 7 4 11 Vanance Path 142 s.d = 10.806 Mean 8 6 13 13 01111 O 0.89 tu Total 0.6944 0.806 Path 14259 + 10 +11 Meanb) The probability that the project will require 49 weelss. than TO NCH, 82) then, १ ll= 46.83 1.12 PC T7,49 ) = (- P(1349) =

Add a comment
Know the answer?
Add Answer to:
can you explain how to fo the mean variance wnd z score and st dev each...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 17-12 A project manager has compiled a list of major activties that will be required...

    Problem 17-12 A project manager has compiled a list of major activties that will be required to nstall a computer Information system in her firm. The st Includes estimated completion times for activties and precedence relationships. Use Table B1 and Table B2. Immediate Est mated Times 6-8-10 7-9-12 2-3-5 3-4-8 2-2-3 2-3-6 3-4-5 4-5-8 S-8-12 H. G, K, O If the project is tinished within 26 weeks of its start, the project manager will recelve a bonus of S1,000; and...

  • A project manager has compiled a list of major activities that will be required to install...

    A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships. (Use Table B1 and Table B2.) (table B1) (table b2) Immediate Predecessor Estimated Times (weeks) A — 2-4-6                    D A 6-8-10                    E D 7-9-12                    H E 2-3-5                    F A 3-4-8                    G F 5-7-9                    B — 2-2-3                    I B 2-3-6                    J I 3-4-5                    K J 4-5-8                    C...

  • Can you please answer this and show the formulas?? Consider the quarterly sales data for Worthington...

    Can you please answer this and show the formulas?? Consider the quarterly sales data for Worthington Health Club shown below: Quarter Total Year 1 2 3 4 Sales 1 4 1 3 7 15 2 6 5 2 18 31 3 13 1 7 18 39 4 14 11 6 18 49 5 20 11 13 30 74 Develop a four-period moving average model and compute MSE for your forecasts. Do not round intermediate calculations. Round your answers to two...

  • HW Score: 62.5%,5 of The estimated times and immediate predecessors for the activities in a projects...

    HW Score: 62.5%,5 of The estimated times and immediate predecessors for the activities in a projects Howard Urinalarning company are given in the following assume that the activity times are independent Question Help Activity . Immediate Predecessor) А 8 Time (weeksi . Predecessors Activity b 8 10 С 7 19 13 4 10 18 D 6 10 14 This exercise contains only parts , bedande a) Based on the activity time estimate the expected times and variance for each of...

  • The accompanying data file contains 10 observations for t and yt. picture Click here for the...

    The accompanying data file contains 10 observations for t and yt. picture Click here for the Excel Data File A 3-period moving average is plotted along with the actual series. 15 14 13 12 11 - 10 LA 9 8- 7- 6 5 0 1 2 3 4 6 7 8 9 10 rk Ch 18 Saved Help Save & Exit su Check my we b-1. Use the 3-period moving average to make in-sample forecasts. (Round intermediate calculations to at...

  • The following table shows estimates of activity times (weeks) for a project: Activity Optimistic Time Most...

    The following table shows estimates of activity times (weeks) for a project: Activity Optimistic Time Most Probable Time Pessimistic Time A 3 4.5 9 B 1.5 2 2.5 C 5 6 7 D 4 4.5 8 E 5 6 7 F 1 2.5 7 G 7 9 11 Suppose that the critical path is A-B-D-F-G. Use Appendix A to answer the questions. Do not round intermediate calculations. Round your answers to three decimal places. What is the probability that the...

  • For each variable of interest, do the following: 1. Find the mean, five-number summary, range, variance,...

    For each variable of interest, do the following: 1. Find the mean, five-number summary, range, variance, and standard deviation. Display these numbers in a format that is easy to understand. 2. For each variable of interest, use its five-number summary to construct a boxplot. Each boxplot must be constructed horizontally, and must be accompanied by a brief descriptive paragraph that assesses whether the data appear to be symmetrical, left-skewed, or right-skewed. Construct a 95% confidence interval for the mean μ...

  • Ross​ Hopkins, president of Hopkins​ Hospitality, has developed the​ tasks, durations, and predecessor relationships in the...

    Ross​ Hopkins, president of Hopkins​ Hospitality, has developed the​ tasks, durations, and predecessor relationships in the following table for building new motels.                                                                                                                                                             Time ​(weeks​) Immediate Time ​(weeks​) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 6 8 10 — G 3 3 5 ​C, E B 2 9 23 A H 1 1 1 F C 8 12 18 A I 7 7 7 F D 4 7 10 A J 4 7 14 ​D, G,...

  • A project manager has compiled a list of major activities that will be required to install...

    A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships. (Z-Table is needed) Activity Immediate Predecessor Estimated Times (weeks) A — 2-4-6 D A 6-8-10 E D 7-9-12 H E 2-3-5 F A 3-4-8 G F 5-7-9 B — 2-2-3 I B 2-3-6 J I 3-4-5 K J 4-5-8 C — 5-8-12 M C 1-1-1 N...

  • The postmaster of a small western town receives a certain number of complaints each day about...

    The postmaster of a small western town receives a certain number of complaints each day about mail delivery. 2 1 4 Number of complaints 3 14 4 8 5 9 6 6 DAY 8 13 7 5 9 14 10 7 11 6 12 4 13 2 14 11 11 a.Determine two-sigma control limits using the above data. (Round your intermediate calculations to 4 decimal places and final answers to 3 decimal places. Leave no cells blank - be certain...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT