(a).A worker completes a job in 6hrs.the allowed standard time for the job in 8hrs.his wage...

(a).A worker completes a job in 6hrs.the allowed standard time for the job in 8hrs.his wage rate is Rs.5 per hour.calculate the total earning of the worker under the following system of payment.
(1)Halsey's 50% plan
(2)Rowan's plan.

(b)state the principles of management as enumerated by Henry fayol .explain any eight of them.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a GIVEN: TIME TAKEN(T) = GHRS ; TIME ALLOWED (TA) = BHRS; WAGE RATE (We) Rs 5/HR. 50% TOTAL EARNINGS BY HALS£YS, PLAN IS GIVyDIVISION OF WORK: THE WORK SHOULD BE DIVIDED AMONG ON THE BASIS Of THEIR EXPERTISE THIS LEADS INDIVIDUALS WHICH EN SURES HIG

Add a comment
Know the answer?
Add Answer to:
(a).A worker completes a job in 6hrs.the allowed standard time for the job in 8hrs.his wage...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A time study analyst observes a worker over a period of time and calculates that the worker requi...

    A time study analyst observes a worker over a period of time and calculates that the worker required 60.0 minutes per unit produced. The worker was rated by the analyst at a 120 percent performance rating, and an 15 percent allowance for personal time and fatigue applies. (1) What is the standard time for this task? (2) If a worker managed to produce 10 units in an eight-hour day, what would their day's pay be if the base rate is...

  • Matthews & Bros. is a local landscape construction company. In analyzing financial performance, the cost accountant compares actual results with a flexible budget. The standard direct labor rates used in the flexible budget are established each year at th

    Matthews & Bros. is a local landscape construction company. In analyzing financial performance, the cost accountant compares actual results with a flexible budget. The standard direct labor rates used in the flexible budget are established each year at the time the annual plan is formulated and held constant for the entire year. The standard direct labor rates in effect for the current fiscal year and the standard hours allowed for the actual output of work for July are shown in the...

  • Fresh out of school, you take a job with a small injection-molding shop with two machines...

    Fresh out of school, you take a job with a small injection-molding shop with two machines (25 ton and 250 ton. On any given shift, there are two workers assigned to each machine one is concerned with setting/loading and unloading while the other packages the final product for shipping. You have been asked to investigate whether you can improve the process, potentially with automation. Having recently re-read The Goal, you are quite aware that adding robots does not necessarily mean...

  • Read article on the minimum wage: To complete this activity: 1. Prepare a response to the...

    Read article on the minimum wage: To complete this activity: 1. Prepare a response to the following discussion prompts, based on the article: Help the Working Poor, but Share the Burden.(see attached) (a) Discuss the costs and the benefits associated with increasing the minimum wage. (b) If you were are congressional member and had to vote on an increase in the minimum wage to say $10 per hour would you? Why or why not? Help the Working Poor, but Share...

  • The job costing system at Shelby's Custom Framing has five indirect cost pools (purchasing, material handling,...

    The job costing system at Shelby's Custom Framing has five indirect cost pools (purchasing, material handling, machine maintenance, product inspection, and packaging). The company is in the process of bidding on two jobs; Job 215, an order of 16 intricate personalized frames, and Job 325, an order of 4 standard personalized frames. The controller wants you to compare overhead alocated under the current simple job-costing system and a newly designed activity-based job-costing system. Total budgeted costs in each indirect cost...

  • Instructions You recently accepted a management position for a home health agency. You directly manage three...

    Instructions You recently accepted a management position for a home health agency. You directly manage three team leads (Registered Nurses with management experience), each with eight Certified Nursing Aides (CNAs) under them. A total of 27 employees. Your first week on the job, you realized there were significant issues with how each team functioned. All three team leads complain about how “the system” is structured, and you’ve heard rumor that several of the CNAs are unhappy with how they are...

  • Instructions You recently accepted a management position for a home health agency. You directly manage three...

    Instructions You recently accepted a management position for a home health agency. You directly manage three team leads (Registered Nurses with management experience), each with eight Certified Nursing Aides (CNAs) under them. A total of 27 employees. Your first week on the job, you realized there were significant issues with how each team functioned. All three team leads complain about how “the system” is structured, and you’ve heard rumor that several of the CNAs are unhappy with how they are...

  • In a period, the labor efficiency variance was $54,000 F. The standard direct labor wage rate is $12.00 per hour and 30 direct labor hours are allowed for each unit of output. Given that 43,500 direc...

    In a period, the labor efficiency variance was $54,000 F. The standard direct labor wage rate is $12.00 per hour and 30 direct labor hours are allowed for each unit of output. Given that 43,500 direct labor hours were worked, how many units of output were actually produced? 150 c. 1,450 d. 1,600 The overhead variance that is a measure of capacity utilization is: a. The overhead spending variance The overhead efficiency variance c. The overhead budget variance d. The...

  • Labor Economics, multiple choice questions 1. In the leisure-income model, the wage constraint shows a. the...

    Labor Economics, multiple choice questions 1. In the leisure-income model, the wage constraint shows a. the points that maximize a worker's utility b. all points that are equally preferred c. the wage rates that affect work decisions d. the available combinations of leisure and income 2. The slope of a wage constraint reflects the: a. rate at which a person is willing to substitute leisure for income c. income effect b. price of leisure d. substitution effect 3. When a...

  • NUMBER OF EMPLOYEES 2013-PRODUCTION 1,000s MONTH January 90 May June September 130 130 100 Octobe...

    Please show how to do a pure chase strategy given this info NUMBER OF EMPLOYEES 2013-PRODUCTION 1,000s MONTH January 90 May June September 130 130 100 October 107 December space was available at the plant, therefore, additional space would have to be rented. In addition, the cost of capital is high because of the company's low credit rating. Taking all of these factors into account, Joan estimated the cost of storing 1,000 pounds of product for one month to be...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT