Question

IM.63 Gs Dairy is trying to determine how to manage their stock of raw milk. They have an average daily demand of 29 gallons

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Safety stock = 16.50 gallons

Reorder point = 132.50 gallons

This is a type of variable demand constant lead time problem and Scifely stock = ZOGJET 7 2 - No. of Standard deviations corrRecorder point (CROP) = JLT + Z ato edol a average daily demand=29 g allone LTE head time - 4 days 2. No. of Standad de viac

please upvote

Add a comment
Know the answer?
Add Answer to:
IM.63 G's Dairy is trying to determine how to manage their stock of raw milk. They...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • IM.61 Demand for Etched Impressions Wood products averages 40 units per day with a standard deviation...

    IM.61 Demand for Etched Impressions Wood products averages 40 units per day with a standard deviation of daily demand being 4. Lead time is 3 days. This IBC company strives for a 93% service level. What is the Z-value for the company's desired service level? (Display your answer to two decimal places.) What is the standard deviation of demand during the lead-time period? (Display your answer to two decimal places.) How many units of wood should Etched Impressions carry for...

  • A dairy company gets milk from two dairies and then blends the milk to get the...

    A dairy company gets milk from two dairies and then blends the milk to get the desired amount of butterfat. Milk from dairy I costs $2.40 per gallon, and milk from dairy Il costs $0.80 per gallon. At most $144 is available for purchasing milk. Dairy I can supply at most 50 gallons averaging 3.9% butterfat, and dairy Il can supply at most 90 gallons averaging 2.9% butterfat. Answer parts a and b. a. How much milk from each supplier...

  • A dairy company gets milk from two dairies and then blends the milk to get the...

    A dairy company gets milk from two dairies and then blends the milk to get the desired amount of butterfat. Milk from dairy I costs ?$2.402.40 per? gallon, and milk from dairy II costs ?$0.800.80 per gallon. At most ?$144144 is available for purchasing milk. Dairy I can supply at most 5050 gallons averaging 3.73.7?% ?butterfat, and dairy II can supply at most 8080 gallons averaging 2.92.9?% butterfat. The company can buy at most 100 gallons of milk. Answer parts...

  • A dairy company gets milk from two dairies and then blends the milk to get the desired l costs S0.80 per gallon. Al most $144 is available for purchasing milk. Dairy I can supply at most 50 80 ga...

    A dairy company gets milk from two dairies and then blends the milk to get the desired l costs S0.80 per gallon. Al most $144 is available for purchasing milk. Dairy I can supply at most 50 80 gallons averaging 29% butterfat Answer parts a-d of butterfat Milk from dairy 1 costs $2.40 per gallon, and milk rod with All supporting written work showing how you derived your final answers for this portion of the problem should be shown on...

  • Boeing orders a small part (component) used in many of its wing assemblies. Below is some...

    Boeing orders a small part (component) used in many of its wing assemblies. Below is some information on this part: Cost per case = $395 Parts per case = 100 Daily usage of parts per day (demand) = 35 Standard deviation of daily demand = 8 Purchasing lead time (in days) = 15 Desired service level = 98% Ordering (administrative) costs = $200 Annual interest earned on cash = 10% What should be the safety stock for this part (in...

  • The supermarket GoodFood orders fresh milk daily directly from Farmer Brigg. The daily demand for milk...

    The supermarket GoodFood orders fresh milk daily directly from Farmer Brigg. The daily demand for milk at the supermarket is normally distributed with an expected demand of 100 gallons and a standard deviation of 20 gallons. GoodFood pays $0.70 per gallon and sells the gallon for $1.00. If GoodFood has milk left over at the end of the day, he cannot keep it and sell it the next day, because it will be sour. However, Farmer Brigg can feed the...

  • Demand for walnut fudge ice cream at the Sweet Cream Dairy can be approximated by a...

    Demand for walnut fudge ice cream at the Sweet Cream Dairy can be approximated by a normal distribution with a mean of 21 gallons per week and a standard deviation of 3.0 gallons per week. The new manager desires a service level of 90 percent. Lead time is two days, and the dairy is open seven days a week. (Hint: Work in terms of weeks.) Use Table B and Table B1. a-1. If an ROP model is used, what ROP...

  • A golf specialty wholesaler operates 350 days per year. Management is trying to determine an inventory...

    A golf specialty wholesaler operates 350 days per year. Management is trying to determine an inventory policy for its 1-irons. The cost to place orders with the supplier is $25/order; the demand averages 12,000 items per day, with a standard deviation of 3,000 item. The annual inventory holding cost is $2.00 per item. The lead time form the supplier is 5 days, with a standard deviation of 2 days. It is important to maintain a 95 percent cycle-service level to...

  • High Tech Inc. is a virtual store that stocks a variety of calculators in its warehouse. Customer orders are placed; the orders are picked and packaged; and then orders are shipped to the customers. A...

    High Tech Inc. is a virtual store that stocks a variety of calculators in its warehouse. Customer orders are placed; the orders are picked and packaged; and then orders are shipped to the customers. A fixed-order-quantity inventory control system (FQS) helps monitor and control these SKUs. The following information is for one of the calculators that High Tech stocks, sells, and ships. Average demand 9.5 calculators per week Lead time 5 weeks Order cost $15/order Unit cost $10.00 Carrying charge...

  • A) A firm has a daily demand of 450 units. The lead time of receiving supplies...

    A) A firm has a daily demand of 450 units. The lead time of receiving supplies is 3 days. If demand has a standard deviation of 100 units per day, what should be their safety stock? The firm plans for a 95% service level. What should be their reorder point? Note: ?0.95 = 1.64. A) This firm decides to increase their service level to 98%. What should be their safety stock? What should be their reorder point? Note: ?0.98 =...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT