Suppose the daily demand of a product follows a normal distribution with the mean of 50 units and the standard deviation of 1

MRP is a technique designed to manage finite capacity None of the above O critical paths O Accounts receivable O dependent de

Sales and operations planning is a technique used to balance the supply and demand of items at the aggregate level None of th

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.

Reorder point, R = d-bar * LT + z*sigma-d * √LT

where d-bar= daily demand = 50

sigma-d= standard deviation of daily demand = 10

LT= lead time = 9 days

z = number of standard deviations corresponding to service level probability

For service level of 95%, z = 1.65

R = d-bar * LT + z*sigma-d * √LT

R = 50*9 + 1.65*10* √9

R = 450 + 1.65*10*3

R = 499.5 ~ 500

Correct answer is 500.

2.

MRP is a technique designed to manage-

Correct answer is " dependent demand items"

Rationale: A dependent demand item is so called because its demand is dependent on customer preferences. MRP is generally practiced on items with dependent demand.

3.

Sales and operations planning is a technique used to balance the supply and demand of

Correct answer is "items at and aggregate level"

Rationale:Sales and operations planning assists the organisations to balance the demand and supply. This process is also called aggregate planning.

Please give thumbs up/ likes if you find this answer helpful. Thank you!

  

Add a comment
Know the answer?
Add Answer to:
Suppose the daily demand of a product follows a normal distribution with the mean of 50...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • ) The demand during the lead time is normally distributed with a méan of 40 and...

    ) The demand during the lead time is normally distributed with a méan of 40 and a standard deviation of 4. If they have calculated a reorder point of 46.60 units, what service level are they assuming? 9505 Service leve 2) The annual demand for a product has been projected at 2,000 units. This demand is assumed constant throughout the year. The ordering cost is $20 per order, and the holding cost is 20 percent purchase cost. The purchase cost...

  • 1 - the annual demand for product 15600 units the weekly demand is 280 units with...

    1 - the annual demand for product 15600 units the weekly demand is 280 units with a standard deviation 90 units the cost to place an order is $31.00 and the time from order to receipt is 4 weeks the annual inventory carrying cost is $0.10 per unit A- what is the EOQ quantity? B- from the information above what is the reorder point maintain a 95% service level? 2 - the weekly demand is 200 units the cost to...

  • The annual demand for a product is 64,000 items and the holding cost is $0.50 item/year....

    The annual demand for a product is 64,000 items and the holding cost is $0.50 item/year. 1) What will be the Economic Order Quantity and the total annual cost if the cost of placing each orde is $250? b) If the company operates 300 days per year and the lead time is 9 days, find the recorder point assuming that the daily demand is constant c) Now suppose that the daily demand is Normal with mean as implied from the...

  • 4) S uppose that lead-time demand is normally distributed with a mean of 100 units and...

    4) S uppose that lead-time demand is normally distributed with a mean of 100 units and a standard deviation of 20 units, If the firm wants to maintain 92% service Jevel, what should the reorder point be? 2-1.88 Pop-137.6units 5) We use 1,500 per year of a certain subassembly that has an annual holding cost of $45 placed costs us $150. We operate 300 days per year and have found that an order must be placed with our supplier 6...

  • A local store sells toilet paper to people in the surrounding communities. The demand for the...

    A local store sells toilet paper to people in the surrounding communities. The demand for the toilet paper has been increasing and management needs to ensure that enough rolls are available to meet the increasing demand. The daily demand for the toilet paper is 400 rolls. The store operates 250 days per year. The following information is also available about the product. The cost of each roll……………………….…..$2. Ordering costs………………………………..……$100 per order Annual holding costs per unit…………… 10% of the costs...

  • - work force level F supply; one of these occurs ol when demand is greater than...

    - work force level F supply; one of these occurs ol when demand is greater than # - none of the other choices is correct all of - the other choices he correct - profits margine is reduced because of price cuts and discounting - cost increase because of overtime and fast freight Q) when supply is greater than demand; one of these occurs - all of the other choices are correct - none of the other choices is correct...

  • Suppose now that the daily demand for the t-shirts is not deterministic. It is random with...

    Suppose now that the daily demand for the t-shirts is not deterministic. It is random with mean 2 and standard deviation 0.5. In addition, the lead time (the time it takes for an order to arrive at the store) is also random. Specifically, the mean lead time is six days and the standard deviation for the lead time is 1 day. The store uses an (s, Q) type inventory control policy. It sets the order quantity using the EOQ formula...

  • Question 29 3 pts Annual demand for an item is 13,000 units with the cost per...

    Question 29 3 pts Annual demand for an item is 13,000 units with the cost per unit at $243. The holding rate is 10% and the order cost is $12.00 per order. The standard deviation of daily demand is 3 units. Assume 260 days in the year and a lead-time of 2 days. If a service level of 97% is desired during the reorder interval, what is the safety stock required? (Note: Due to rounding and your exact choice of...

  • Jake, Inc. begins a review of ordering policies for its continuous review system by checking the...

    Jake, Inc. begins a review of ordering policies for its continuous review system by checking the current policies for a sample of its A items. Following are the characteristics of one item: Demand (D) = 94 units/week (assume 52 weeks per year) Ordering and setup cost (S) = $720/order Holding cost (H) = $23/unit/year Lead time (L) =3 weeks Standard deviation of weekly demand =30 units Cycle-service level =82 percent Develop the best policies for a periodic-review system. a. What...

  • Assume an inventory control system for an independent demand item where the Lead-time is 4 days...

    Assume an inventory control system for an independent demand item where the Lead-time is 4 days and the Review Period is 15 days. The expected demand for the end-item is 20,000 units per year. Assume, further, that the manager wants to achieve a cycle service level of 95% in her Q system and she knows that the daily average demand is 10 units (demand is normally distributed). She has determined that her facility is open 250 days a year; her...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT