Question
please don't solve it in excel
4. A company has a staff of 5, each working 8 hours per day. Payroll cost is $680/day while overhead cost is $350/day. The co
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Output under current system = 23

Productivity of the current system

= Output / Total cost

= 23/3750

= 0.00613 units per $

Total cost under new system

= 680 x 5 + 700

= 3400 + 700

= $4100

Output under new system = 23 + 14 = 37

Productivity under the new system

= 37/4100

= 0.00902 units per $

The new system is more productive since it has a higher value than that of old system

Add a comment
Know the answer?
Add Answer to:
please don't solve it in excel 4. A company has a staff of 5, each working...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • AIT has a staff of 4 cleaners, each working 8 hours per day (for a payroll...

    AIT has a staff of 4 cleaners, each working 8 hours per day (for a payroll cost of GH¢ 640/ day) and overhead expenses of GH¢ 400 / day. The cleaners mop and clean 8 floors each day. The company recently purchased a new machine system that will mop and cleans 14 floors per day. Although the cleaners, their works hours, and pay will be same, the overheads expenses are now GH¢ 800 per day. Compute the following; labour productivity...

  • Bears Unlimited has a staff of 4, each working 8 hours per day (for a payroll...

    Bears Unlimited has a staff of 4, each working 8 hours per day (for a payroll cost of $640 per day) and overhead expenses of $400 per day. This company manufactures 8 wood decorations each day. What is labor productivity ?

  • Collins Title Insurance Ltd. wants to evaluate its labor and multifactor productivity with a new comput-...

    Collins Title Insurance Ltd. wants to evaluate its labor and multifactor productivity with a new comput- erized title-search system. The company has a staff of four, each working 8 hours per day (for a payroll cost of $640/day) and overhead expenses of $400 per day. Collins processes and closes on 8 titles each day. The new computerized title-search system will allow the processing of 14 titles per day. Although the staff, their work hours, and pay are the same, the...

  • A company produces 300 units of a product a day, which costs $12 per unit. It...

    A company produces 300 units of a product a day, which costs $12 per unit. It employs 3 workers who work 8 hours a day at an hourly rate of $12 dollars per hour. The cost for materials is $1,200 and overhead is $260. The company plans to outsource some of its work to the outside suppliers. The administration believes it will allow lay off one of the workers (use only two workers), pay the other two workers an hourly...

  • answer all 4 questions 1) A manufacturing company produced 2300 shoes in one day. Standard price...

    answer all 4 questions 1) A manufacturing company produced 2300 shoes in one day. Standard price is $20 per shoe. Per day labor cost is $5000, material cost is $8000 and overhead costs $10,000. Determine the per day multifactor productivity for this company ? 2) List some of the dimensions (at least six (6)) that organizations strategize along for increased competitiveness ? 3) List at least four (4) types of problems that Manufacturing Planning and Control & Simulation Systems provide...

  • provides housecleaning services to its verhead costs. The company has provided services to its Chients. The...

    provides housecleaning services to its verhead costs. The company has provided services to its Chients. The company uses has provided the following data The Coletti Cleaning Brigade Company provides housecleani an activity-based costing system for its overhead cos from its activity-based costing system. Total Cost Total Activity Activity Cost Pool $302,993 $43,100 hours Cleaning 79,100 Job Support 5,000 jobs 180 clients 3,348 Client Support 150,000 Other $535,441 Total The "Other activity cost pool consists of the costs of idle capacity...

  • QUESTION 4 Alex Company manufactures boats in bottles (to sell to rich people who don't have...

    QUESTION 4 Alex Company manufactures boats in bottles (to sell to rich people who don't have the time to make them themselves). For their standard costing system they allow 5 hours of direct labor per bottle at a wage of $12 per hour. The last batch only took 4.5 hours per bottle. They made 12 bottles. However, they ended up paying employees $12 per hour. What is the standard cost for labor per bottle? (in dollars per bottle) QUESTION 5...

  • Please complete all work in excel. Use excel to make the calculations (cells can be clicked...

    Please complete all work in excel. Use excel to make the calculations (cells can be clicked on to view any formulas used) and be sure to identify your answer, including units. Upload one excel file for your submission. Delights Company is designing a production layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 80,000 units per day. For output to equal forecasted demand, what should the...

  • Based on the case study below, fill out the Excel file and MUST show math appropriate...

    Based on the case study below, fill out the Excel file and MUST show math appropriate calculations in the right column. CASE STUDY DATA Larson Property Management Company Supplemental Case Material Building a Business Case The system that Larson has chosen to support their recruiting process costs $15,000 each quarter for use of the application. The initial implementation costs to the vendor who will help with project management is $50,000 Maintenance fees are included in the quarterly licensing fee, but...

  • Help figuring out this problem show work if you can EXHIBIT 2-5 Dickson Company: An Example...

    Help figuring out this problem show work if you can EXHIBIT 2-5 Dickson Company: An Example Using Multiple Predetermined Overhead Rates Step 1: Calculate the estimated total manufacturing overhead cost for each department. Miling Department Overhead Cost (Y): Assembly Department Overhead Cost (Y): = $390,000 + ($2.00 per MH X 60.000 MHS) = $500,000 + ($3.75 per DLH X 80,000 DLHs) = $390,000+ $120,000 = $500,000 + $300,000 = $510,000 = $800,000 Step 2: Calculate the predetermined overhead rate in...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT