QUESTION 5 (a) Describe, in point form and in the correct sequence, how to centre and...
QUESTION 5 (a) Describe, in point form and in the correct sequence, how to centre and level and orientate a Total Station over a designated survey point. Include keypad entries. (b) Calculate the gradients of the lines BC and CD and the clearance between the ground at point B and the bridge from the following EDM observations. The RL of the ground at Prism pole station B is 201.25m Bearing Zenith Angle Slope Dist(m) Prism Ht. Prism Pt.Remarks 2.13 2.19 2.28 2.38 925 400.50 9300 00" 400.45 00°00 3652 7435'00" 133.04 59056 Ground @ Bridge INVERT on Bridge top of banlk top of bank 7951 30" 114.18 110+11 -21 marks]