Scrutinize the chart below to answer the 5 questions below A. 4 8 10 SD-status date 1. How manyevents are shown? 2. How many activities are shown? 3. Which activity (if any) is (are) completed? 4. As of SD, which activity (if any) is (are) ahead of schedule? 5. As of SD, which activity (if any) is (are) behind schedule?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Events are those activities where a specific action has started or milestone has been achieved. Based on the given figure, 10 events are shwon.

2. There are 5 activities shown in the figure. They are - A, B, C, D and E.

3. Activity A is completed as shown in the figure, the status date division shows on other activities such as B and C are partially completed and ongoing while A has been completed fully.

4. No activities are ahead of scheule.

5. Activity B is behind schedule. As shown in the diagram, the highlighted part should have been ahead of the SD line, Since it is behind we can conclude that the activity is lagging behind and causing dealy to the project

Add a comment
Know the answer?
Add Answer to:
Scrutinize the chart below to answer the 5 questions below A. 4 8 10 SD-status date...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Answer the following questions based on the PERT chart below with task times given in hours....

    Answer the following questions based on the PERT chart below with task times given in hours. [All answer should be given as a single number only without units]. Answer the following questions based on the PERT chart below with task times given in hours [All answer should be given as a single number only without units] A(5) E(5) Start B1) D(8) H(4) End C(6) G(3) 1(7) a. The number of priority lists that can be created for this project is...

  • 10. Study the Pedigree chart below. Answer the questions that follow. 7 * Type A -...

    10. Study the Pedigree chart below. Answer the questions that follow. 7 * Type A - Type B = Type AB - Type o 8 9 10 11 12 13 14 15 16 17 18 19 20 21 a. How many phenotypes are shown? b. What type of inheritance is blood type? c. The genotypes for blood groups are as follows: Type A: AA or Ao Type B: BB or Bo Type AB: AB Type 0:00 d. Using these genotypes,...

  • Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a...

    Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a start date of January 6, 2020. Assume that work can be done 5 days per week. Identify the Critical Path. When will the project be completed? Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a start date of January 6, 2020. Assume that work can be done 5 days per week. Identify the Critical Path. When will...

  • (+10) Answer the following questions in terms of the structure chart below. A. What modules directly...

    (+10) Answer the following questions in terms of the structure chart below. A. What modules directly use the services of module E? a. A C D                                   b. B C                        c. D                            d. None of these B. The services of which modules are directly used by module A? a. C and D                               b. B C D                                  c. B D    d. B C   (+5) Based on the same structure above, in which module does the data item w originate? a. B                               ...

  • .8-6. A project consists of 12 activities, represented by the project network below, where number by each arc repres...

    .8-6. A project consists of 12 activities, represented by the project network below, where number by each arc represents the duration (in days) of the associated activity 4 12 4 12 10 a) Find the earliest time, latest time, and slack for each event as well as the slack for each activity. Also identify the critical path. (b) The project has been scheduled to be completed in the minimum possible time.If all previous activities have begun as early as possible...

  • Q1: Use the network below to answer the following questions: D 7 G 8 E 5...

    Q1: Use the network below to answer the following questions: D 7 G 8 E 5 C H 10 F 3 B 3 i. ii. Assume the duration is given in weeks(numbers shown above), how long will it take to finish this project? Show your work. (4 marks) Determine the critical path. (1 mark) List the activities that could be delayed without affecting the submission of the project and determine the duration of this delay ( 1 Marks) iii.

  • answer the following questions below: Draw a simple flow chart of the cardiac conduction system and...

    answer the following questions below: Draw a simple flow chart of the cardiac conduction system and explain the function of each component . Briefly explain the 3 major waves in the ECG record  in term of the electrical activity and the mechanical events. Why does the QRS complex has greater signal than P wave? What is the isoelectric line of the ECG?

  • Name:melissa Kiemm Date: 124s Picture Data-The Histogram Practice Problems Refer to the histogram below and answer...

    Name:melissa Kiemm Date: 124s Picture Data-The Histogram Practice Problems Refer to the histogram below and answer the following questions. 500 400 200 0-10 1-21 22-32 33-43 444 5-65 66-76 77-87 Salary ( thousands) 1. How many people earned between $11K and $21K? 2. What salary range is the most prevalent? 4+ 5 3. How many people earned at least $44K? 300 4. How many people earned less than $33K? 5. What is the approximate distribution displayed here in this histogram?...

  • Genetics Pedigree Worksheet 1. Use the below pedigree chart to answer the following questions about dimples....

    Genetics Pedigree Worksheet 1. Use the below pedigree chart to answer the following questions about dimples. The Dimple gene controls whether a person has dimples or doesn't have dimples. Dimples is dominant to no dimples. Place the genotypes of each individual below its symbol. O Dimples gene (D) Dimples is dominant to no dimples 12 13 14 A) How many family members have Dimples? B) What is the genotype of individual 3 and 4? C) Can cither individual #8 or...

  • styles Use the chart below to answer the following questions regarding flow chart symbols. DOWS 18)...

    styles Use the chart below to answer the following questions regarding flow chart symbols. DOWS 18) Which symbol would be used in a flowchart to represent the symbol for a file? A) #9 B) #5 C) #6 D) #15 19) Which symbol would be used in a flowchart to represent manually prepared control totais? A) #9 B) #10 C) #4 D) #7 20) Which symbol would be used in a flowchart to represent a purchase order? A) #2 B) #1...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT