Question

In an assembly line where the cycle time is 3 minutes and the sum of the task times is 22 minutes, what is the daily producti
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: 160

Cycle time is the time required to complete one cycle of operation or to complete a task or job from start to finish.

Cycle time = 3 minutes

Total available time = 8 hours or 480 minutes

Daily production rate = Total available time / Cycle time

Daily production rate = 480/3

Daily production rate = 160 units

Add a comment
Know the answer?
Add Answer to:
In an assembly line where the cycle time is 3 minutes and the sum of the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 1...

    An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day. a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.)    Minimum cycle time minutes Maximum cycle time minutes b. What range of daily output is theoretically possible for the line? (Round your answers to 1 decimal place. Enter the...

  • An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes,...

    An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day. a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.)    Minimum cycle time minutes Maximum cycle time minutes b. What range of daily output is theoretically possible for the line? (Round your answers to 1 decimal place. Enter...

  • Compute the takt time for a system where the total time per shift is 480 minutes,...

    Compute the takt time for a system where the total time per shift is 480 minutes, there are two shifts, and workers on each shift are given two 15-minute breaks and 45 minutes for lunch. Daily demand is 650 units. What cycle time would match capacity and demand if demand is 120 units a day, there are two shifts of 480 minutes each, and workers are given two half-hour breaks during each shift, one of which is for lunch or...

  • The operations manager of an instruments company is balancing an assembly line. The company needs to...

    The operations manager of an instruments company is balancing an assembly line. The company needs to build 96 instruments per 24-hour day. The assembly line activities are: a. Draw the precedence diagram. b. If the daily (24-hour) production rate is 96 units, what is the greatest possible cycle time? c. If the cycle time after allowances is given as 10 minutes, what is the daily (24-hour) production rate? d. With a 10-minute cycle time, what is the theoretical minimum number...

  • An assembly line with 17 tasks is to be balanced. The longest task is 2.3 minutes,...

    An assembly line with 17 tasks is to be balanced. The longest task is 2.3 minutes, and the total time for all tasks is 18 minutes. The line will operate for 490 minutes per day. a. What is the minimum number of workstations needed if the output rate is to be 170 units per day? (Round the final answer to the next whole number.) Number of workstation             b. What cycle time will provide an output rate of 126 units per...

  • An assembly line with 17 tas ks is to be balanced. The longest task is 2.4...

    An assembly line with 17 tas ks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 17 minutes. The line will operate for 474 minutes per day. a. What is the OT? minutes minutes b. What is the minimum cycle time? c. What is the maximum cycle time? minutes d. What is the range of output that is theoretically possible for the line? to units e. What is the minimum number...

  • The desired daily output for an assembly line is 540 units. This assembly line will operate...

    The desired daily output for an assembly line is 540 units. This assembly line will operate 729 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK TASK TIME (SECONDS) IMMEDIATE PREDECESSOR A 30 — B 28 A C 18 B D 69 B E 34 A F 36 E G 42 C, D H 24 F, G b. What is the workstation cycle time? Cycle time seconds c. Balance this line using...

  • An assembly line is to operate eight hours per day with a desired output of 160...

    An assembly line is to operate eight hours per day with a desired output of 160 units per day. The following table contains information on this product's task times and precedence relationships: IMMEDIATE PREDECESSOR TASK TIME (SECONDS) 100 TASK A 70 D 50 40 C C. D 70 140 G H b. What is the required workstation cycle time meet the desired output rate? (Round your answer to the nearest whole number.) Workstation cycle time seconds per unit c. Balance...

  • Question d) The idle time for the assembly line per cycle = _____ minute(s) The Mach...

    Question d) The idle time for the assembly line per cycle = _____ minute(s) The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 60 boats. Given the following information: Task Predecessors Performance Time (mins) 2. 1 1 A B...

  • A rider lawn mower is produced on a manual assembly line. Work content time=49.5 min. The...

    A rider lawn mower is produced on a manual assembly line. Work content time=49.5 min. The line has 25 workstations with a manning level = 1.2. Available shift time per day = 8 hr, but equipment downtime during the shift reduces actual production time to 7.5 hr on average. This results in an average daily production of 244 units/day. Repositioning time per worker = 5% of cycle time. Determine (a) line efficiency, (b) balancing efficiency, and (c) repositioning time.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT