Question

2. For the following project draw a node network and a bar chart. Then perform resource leveling trying to reduce the daily r

0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER:

STEP-1: BAR CHART / GANTT CHART AS PER PROBLEM:

11 14 17 20 23 26 December 2019 29 02 05 08 11 14 17 20 23 26 29 January 2020 01 04 07 10 13 16 19 22 25 Task Mode - Task Nam

STEP-2: NODE NETWORK DIAGRAM: IN BOX

s Network Diagr Network Diagram Tools Project18 - Project Professional Sign in -ox Format O Tell me what you want to do Proje

STEP-3: NODE NETWORK DIAGRAM: COLLAPSING BOX: (RED ONES ARE CRITICAL ACTIVITY)s Network Diagr Network Diagram Tools Project18 - Project Professional Sign in -ox Format O Tell me what you want to do Proje

STEP-4: RESOURCE LOADING:

January 2020 01 04 07 Add New C 11 14 17 20 23 December 2019 29 02 05 08 26 11 14 17 20 23 26 29 10 13 to toto to to to totoSTEP-5: RESOURCE LEVELLING OF 113 MAN DAYS TOTAL = NOT MORE THAN 8 LABORERS PER DAY

=2*6+3*2+3*8+5*5+4*3+3*6+2*5+3*2 =113 MAN DAYS

:

19 05 08 11 14 17 20 23 26 29 December 2019 02 05 08 11 14 17 20 23 26 29 January 2020 01 04 2,000% 1,800% 1,600%- 1,400% - 1

STEP-6: RESOURCE USAGE OF 113 MAN DAYS TOTAL:

- 11 14 2 17 December 2019 29 02 64h 160h 20 23 26 20 144h 48h 26 192h 05 88h 08 80h 11 5 6h 17 80h 32h 48h 14 24h 16h 16h 24

Add a comment
Know the answer?
Add Answer to:
2. For the following project draw a node network and a bar chart. Then perform resource...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. In the following network, Draw the AON, calculate the early start and late start schedule,...

    2. In the following network, Draw the AON, calculate the early start and late start schedule, total and free floats, Allocate the resources, and level the resources for the following cases With a maximum of (8) laborer's per day. а. b. Level the resources to follow a normal distribution (start low, increase the resources gradually until it peaks in the middle, and then gradually decrease at the end of the project Duration Activity Predecessors laborers (days) A 2 В 2...

  • For the following, draw the node network, perform the CPM calculations, mark the critical Path, and...

    For the following, draw the node network, perform the CPM calculations, mark the critical Path, and complete the table. IAAB 745 00 ABCDE Make possibility of rejection. Also show procurement activities CHAPTER 4 EXERCISES 1. For the following schedule, draw the node network, perform the CPM tions, mark the critical path, and complete the table. Activity Duration IPA ES EF LS LF TF FF В 8 B, C For the following schedule, draw the node network, perform the CPM tions,...

  • 3. For the following schedule, draw the node network, perform the CPM calcula tions, mark the...

    3. For the following schedule, draw the node network, perform the CPM calcula tions, mark the critical path, and complete the table TF FE LS LF ES IPA Duration Activity 2 A - A 4 A 6 C A 5 F B, C D, E, F 7 F 3 G

  • 5 & 17. For the following schedule, draw the node network, perform the CPM calculations, mark...

    5 & 17. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 5 with an imposed finish date of 26 and then 35 days. Activity Duration IPA ES EF LS LF TF FF A 6 - B 2 - C 9 - D 4 A, B E 7 B F 5 D G 10 D, E H 8 C, F, G I 3 C, G J 2...

  • 10. You are a construction project manager and have identified that you project activities and resources...

    10. You are a construction project manager and have identified that you project activities and resources are: Laborers Activity A в Duration IPA 2 4 ТА 6 A 9 A 5 B В.С D.EF w G Manually level your resources so you may not use more than 9 laborers per day at a time.

  • 3 & 15. For the following schedule, draw the node network, perform the CPM calculations, mark...

    3 & 15. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 3 with an imposed finish date of 15 and then 20 days. Activity Duration IPA ES EF LS LF TF FF A 2 - B 4 A C 6 A D 9 A E 5 B F 7 B, C G 3 D, E, F

  •  Level the resource and schedule the activities based on the optimum resource usage. Then draw...

     Level the resource and schedule the activities based on the optimum resource usage. Then draw the S-curve knowing that the total cost of activities A, B, C, D, E, F and G is 2000$,3000$, 5000$, 6300$, 2500$, 4200$ and 1500$ respectively. Hint: you can use Excel to draw the histogram or S-curve. • Level the resource and schedule the activities based on the optimum resource usage. Then draw the S-curve knowing that the total cost of activities A, B....

  • QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are s...

    QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are shown follow. Time Immediate Activity (weeks) Predecessor 2 5 В 4 C 5 В 6 В.С D,E F What are the slack times of Activities D and E? 0 and 0, respectively 1 and 1, respectively 2 and 0, respectively 0 and 1, respectively 1 and 0, respectively shown follow. A firm is planning a project for the...

  • 1. For the following schedule, Draw the AON network diagram for the project and calculate the...

    1. For the following schedule, Draw the AON network diagram for the project and calculate the schedule. а. Summarize the schedule in a tabular form, showing ES, EF, LS, LF, TF, and FF for each activity b. Denote the critical path on the network. C. d. Perform a cost analysis based on an early start, late start, and target schedule for the project. Plot the cumulative cost distribution for the three S-curves on one graph. e. f. Plot the cumulative...

  • QUESTION 1 Please use the information below to draw and solve the network on a piece...

    QUESTION 1 Please use the information below to draw and solve the network on a piece of paper by: Complete the forward and backward pass Identify the critical path Fill in the requested information (Example: ESA Early Start of Activity A; LFA Late Finish of Activity A, etc) Relationship Activity Contract sign Predecessor Activity ID Duration 3 А Survey В 2 А Target market C Data В,С D 7 collection Presentation 2 FS Lag 3 E В Analyze F 2...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT