LINE BALANCING
Available time per day= 300 minutes
Daily demand= 60 boats
1.Required cycle time (takt time)
=available production time /( required output or demand ) 300/60=5 minutes per boat
2. Number of workstations (theoretical minimum)
=sum of task times/ required cycle time
=1+1+3+1+2+2+1+2+1=14minutes/5 = 2.8 or 3 station
3. rule for tasks arrangement
Other method-Ranked positional weight
4. Starting with first workstation, assign tasks, one at a time, until the sum of the task times is equal to the workstation cycle time ( or till no other tasks can be assigned due to sequence or time restrictions)
5. Repeat for the remaining workstations till all the tasks have been assigned to a station. We try to pack the earliest workstation first with as much as possible tasks before filling the next ones
6. Line efficiency is the time for making one unit divided by allocated time and is determined by the number of workstations
Line efficiency= Sum of all task times/(Actual number of workstations * required cycle time)
7. Idle time at each station = Required cycle time - sum of task times at each station
8. Idle time for the line per cycle= sum of idle times at individual workstations
|
Activity |
Performance time |
number of following tasks |
|
A |
1 |
8 |
|
C |
3 |
5 |
|
E |
2 |
2 |
|
F |
2 |
2 |
|
B |
1 |
2 |
|
D |
1 |
2 |
|
H |
2 |
1 |
|
G |
1 |
1 |
|
I |
1 |
0 |
|
14 |
|
Required cycle time=5 minutes |
|||||
|
Order of allotment |
WS1 |
Order of allotment |
WS2 |
Order of allotment |
WS3 |
|
1 |
A,1 |
3 |
E.2 |
7 |
H,2 |
|
2 |
C,3 |
4 |
F,2 |
8 |
G,1 |
|
5 |
B,1 |
6 |
D,1 |
9 |
I,1 |
|
sum of task times each station |
5 |
5 |
4 |
||
|
Idle time |
=5-5=0 |
=5-5=0 |
=5-4=1 |
||
NOTE
The order of allotment shows how we have ordered the tasks one by one to each station. Note that after F, we allot B to workstation 1 and we try to pack the earliest workstation first with as much as possible tasks before filling the next ones
Line efficiency= Sum of all task times/(Actual number of workstations * required cycle time) = 14/(3*5) =0.93333 or 93.33 %
Idle time for the line per cycle= sum of idle times at individual workstations=0+0+1=1 minute
If 400 minutes are available for production
Required cycle time= 400/60= 6.67 minutes
Theoretical minimum number of workstations = 14 /6.67 = 2.1 or 3 workstations
Theoretical efficiency
= Sum of all task times/(theoretical minimum number of workstations * required cycle time)
=14/(3*6.67)=0.6997 0r 69.97
Note
The Theoretical minimum number of workstations is always rounded up to the next largest integer value
And is not always possible to reach when actually tasks are aligned
A. Answer - Fig 3
Fig 3 is the one that shows 3 works stations and correct precedent relationships
Fig 1- G has B as precedent – wrong
Fig 2- H is in workstation2. It should be in workstation 3
B.93.33%
C.1 minute
D.3 stations
E.69.97%
a. Mach 10 The daily demand is 60 boats Given the following information Task Fig D,...
Question d) The idle time for the assembly line per cycle =
_____ minute(s)
The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 60 boats. Given the following information: Task Predecessors Performance Time (mins) 2. 1 1 A B...
For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A 45 - B 11 A C 9 B D 50 - E 26 D F 11 E G 12 C H 10 C I 9 F, G, H J 10 I 193 b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.) I have not been...
For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A 45 - B 11 A C 9 B D 50 - E 26 D F 11 E G 12 C H 10 C I 9 F, G, H J 10 I 193 b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.) The minimum cycle...
The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 6060 boats. Given the following information: Task Performance Time (mins) Predecessors A 22 minus− B 22 A C 11 A D 11 C E 33 C F 11 C...
a) The correct precedence relationship with one of the
possible assignment of tasks to workstations is shown in ?
b) What is the operating efficiency of the assembly line,
using your answer to (a)?
c) What is the theoretical minimum number of
workstations?
d) What is the idle time per boat produced?
IOIIGWufk. Cny Score: 0 of 1 pt Problem 9.18 Assembly Line Balancing 10 of 11 (6 complete) HW Score: 54.55%, 6 of 11 Question Holp The final assembly...
As explained in the text book, in Figure 19-1 shown above:
task D transfers information to tasks E, F, and L
task D requires information from tasks E, F, and L
task B requires information from tasks C, F, G, J, and K
task A requires information from tasks H and L
As explained in the text book, in Figure 19-1 shown above:
task B transfers information to tasks C, F, G, J, and K
task D transfers information to...
Partial Derivatives
Example (11): Suppose that the daily demand for 3q butter is given by f (p,q)d the daily 1+p2 2p demand for margarine is given by g(p,q) where p and q are the unit prices. Determine whether the two quantities (butter and margarine) are Substitute or Complementary or neither.
Example (11): Suppose that the daily demand for 3q butter is given by f (p,q)d the daily 1+p2 2p demand for margarine is given by g(p,q) where p and q...
QUESTION 2 Given the following information, you are to determine the following Project network. Early, late and slack activity times. Project duration. Critical path Task Predecessor Duration A None 8 B A 5 C A 10 D A 15 E A 10 F B 12 G C, D 12 H E, 7 I G, H 7 J F,G,I 10 K J 12
Question Help Consider the following information: Demand rate (D) = 1,500 units per hour Lead time (T) = 7 hours Container capacity (C)= 220 units Safety factor (x) = 20% a. The number of kanban production cards is (Enter your response rounded up to the next whole number.) b. The cards will represent hours' worth of demand. (Enter your response rounded to one decimal place.) c. Suppose the safety factor is eliminated. The number of kanban production cards is to...
The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST PRECEDE A 18 — B 10 A C 25 B D 15 B E 14 C F 17 D G 12 E, F H 20 G The workday is 6.25 hours long. Demand for completed product is 750 per day. a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.) b. What is the theoretical...