a) Variable efficiency overhead variance: (Standard hours- Actual hours)* Standard Rate
=(500*10-500*8)*20=(5000-4000)*20=1000*20=20000F
b) Variable spending overhead variance: (Standard Rate- Actual Rate)* Actual hours
=(20-18)*4000 = 2*4000 = 8000F
c) Spending variance is appropriate variance for evaluating the manager in charge of set up department because paying a higher / lower average actual overhead price per unit of the activity base than the standard price allowed per unit of the activity base. and. larger / smaller waste and shrinkage associated with the resources involved than expected.
d) Journal entry to record variable overhead set up costs is
Finished goods inventory A/c Dr 28000
To variable overhead eficiency variance 20000
To Variable overhead rate variance 8000
e) Calculation of Expenditure variance for fixed set up overhead costs
Fixed Overhead Expenditure variance= Budgeted hours * Standard rate - Actual hours * Actual rate
=(400*112.5 - 500* 84)= 3000F
This helps the MC for controlling costs
f) Fixed overhead volume variance is Standard hours* Standard rate - budgeted hours* Standard rate
=48000-48000 = 0
Question 3 Magic Corporation (MC) produces special carbon fibre basketball hoops. These hoops are produced in...
Raposa, Inc., produces a special line of plastic toy racing cars. Raposa, Inc., produces the cars in batches. To manufacture a batch of the cars, Raposa, Inc., must set up the machines and molds. Setup costs are batchminus−level costs because they are associated with batches rather than individual units of products. A separate Setup Department is responsible for setting up machines and molds for different styles of car. Setup overhead costs consist of some costs that are variable and some...
Bristol Fabricators, Inc., produces air purifiers in batches. To manufacture a batch of the purifiers, Bristol Fabricators, Inc., must set up the machines and assembly line tooling. Setup costs are batch-level costs because they are associated with batches rather than individual units of products. A separate Setup Department is responsible for setting up machines and tooling for different models of the air purifiers. Setup overhead costs consist of some costs that are variable and some costs that are fixed with...
Really need questions 6 and 7 answered...
8-37Activity-based costing, batch-level varlance analysis. Rae Steven Publishing Company specializes in printing specialty textbooks for a small but profitable college market. Due to the high setup costs for each batch printed, Rae Steven holds the book requests until demand for a book is approximately 520. At that point Rae Steven will schedule the setup and production of the book. For rush orders, Rae Steven will produce smaller batches for an additional charge of...
Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 26 setups and 26,000 machine hours to manufacture 6,500 units for the year. Selected data for 2019 follow Budgeted fixed factory overhead: $ 54,600 178,000 Setup cost Other $232,600 $481,000 Total factory overhead cost incurred Variable factory overhead rate: $ 400 $6.00 30,000 34,500 Per setup Per machine hour Total standard machine hours allowed for the units manufactured Machine hours actually worked Actual total number...
Serene Sound produces a high quality audio tape used in the recording industry. Serene allocates variable overhead to production at a rate of $12 per batch manufactured. The company’s monthly fixed overhead costs average $72,000. An average of 500 batches per month is considered normal. During June, Serene produced 450 batches of audio tape and incurred actual overhead costs of $79,500. 1 Compute the following amounts: a Total overhead applied to production in June amounted to $__________. b Total overhead budgeted in June for the 450 batches...
Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 32 setups and 32,000 machine hours to manufacture 6,400 units for the year. Selected data for 2019 follow: $ 102,400 174,000 $276,400 $496,000 Budgeted fixed factory overhead: Setup cost Other Total factory overhead cost incurred Variable factory overhead rate: Per setup Per machine hour Total standard machine hours allowed for the units manufactured Machine hours actually worked Actual total number of setups Actual number of...
Alden Company uses a three-variance analysis for factory
overhead variances. Practical capacity is defined as 28 setups and
28,000 machine hours to manufacture 5,600 units for the year.
Selected data for 2019 follow:
Budgeted fixed factory overhead:
Setup cost
$
84,000
Other
186,000
$
270,000
Total factory overhead cost incurred
$
490,000
Variable factory overhead rate:
Per setup
$
850
Per machine hour
$
5.00
Total standard machine hours allowed for the units
manufactured
25,000
hours
Machine hours actually worked...
The overhead budget for Hugh Demand Ltd for the year to 30 June 2016 wasestimated on 20,000 direct labour hours. Using this base, the overhead recovery rate per direct labour hour was determined as: Fixed costs ($216,000) $10.80 Variable costs $ 8.10 $18.90 Actual results achieved for the year were: Fixed costs $220,500 Variable costs $170,940 Direct labour hours 21,000 hours Required: Calculate the factory overhead spending (budget) variance and capacity(volume) variance. Specify whether the Spending Variance and the...
Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 34 setups and 34,000 machine hours to manufacture 8,500 units for the year. Selected data for 2019 follow: Budgeted fixed factory overhead: Setup cost $ 85,000 Other 186,000 $ 271,000 Total factory overhead cost incurred $ 485,000 Variable factory overhead rate: Per setup $ 400 Per machine hour $ 5.00 Total standard machine hours allowed for the units manufactured 27,000 hours Machine hours actually worked...
Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 40 setups and 40,000 machine hours to manufacture 8,000 units for the year. Selected data for 2019 follow: Budgeted fixed factory overhead: Setup cost $ 76,800 Other 230,000 $ 306,800 Total factory overhead cost incurred $ 484,000 Variable factory overhead rate: Per setup $ 550 Per machine hour $ 4.00 Total standard machine hours allowed for the units manufactured 28,000 hours Machine hours actually worked...