Question

Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent...

Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent and the maximum allowable payback period is three years. (Round your answer to 2 decimal places. If the project never pays back, then enter a "0" (zero).)

Project B Time: 0 1 2 3 4 5

Cash flow: –$11,300 $3,380 $4,240 $1,580 $0 $1,060

Payback years ___________

Should the project be accepted or rejected? ______________

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Payback period = 0 years.................(since the project never paysback).

The project should be rejected.

initial investment to be recovered = $11,300.

the following is the calculation of payback period:

year cash flow cumulative cash flow
1 3,380 3,380
2 4,240 7,620
3 1,580 9,200
4 0 9,200
5 1,060 10,260

maximum cumulative cash flow is $10,260..

since the initial investment of 11,300 is never recovered, the project never paysback.

Add a comment
Know the answer?
Add Answer to:
Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent...

    Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: Cash flow: -$11,000 $3,350 $4,130 $1,520 $0 $1,000 Payback years Should the project be accepted or rejected? accepted rejected

  • Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent...

    Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: Cash flow: 0 -$12,500 1 $3,500 2 $4,480 3 $1,820 4 $0 5 $1,300 Payback years Should the project be accepted or rejected? accepted rejected

  • Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent...

    Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: 0 1 2 3 4 5 Cash flow: –$11,400 $3,390 $4,260 $1,600 $0 $1,080 Should the project be accepted or rejected? accepted rejected

  • Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent...

    Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: 0 1 2 3 4 5 Cash flow: –$12,800 $3,530 $4,540 $1,880 $0 $1,360 Should the project be accepted or rejected? accepted rejected

  • Compute the payback statistic for Project B if the appropriate cost of capital is 10 percent...

    Compute the payback statistic for Project B if the appropriate cost of capital is 10 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "O" (zero).) Project B Time: Cash flow: -512,900 12 $3,540 $4,560 $1,900 $0 $1,380 Payback years Should the project be accepted or rejected? accepted rejected < Prex 6 of 7 Ners > search OM

  • Compute the payback statistic for Project B if the appropriate cost of capital is 13 percent...

    Compute the payback statistic for Project B if the appropriate cost of capital is 13 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: 0 1 2 3 4 5 Cash flow: −$11,800 $3,430 $4,340 $1,680 $0 $1,160 NPV? Should the project be accepted or rejected?

  • Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent...

    Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent and the maximum allowable payback period is three years. Should the project be rejected or accepted? (If the project never pays back, then enter a "0" (zero). Project B Time: 0 1 2 3 4 5 Cash flow: –$11,700 $3,420 $4,320 $1,660 $0 $1,140

  • Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent...

    Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: 0            1           2             3           4           5 Cash flow: –                      $12,600   $3,510 $ 4,500 $1,840    $0      $1,320 Should the project be accepted or rejected?

  • Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12...

    Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "O" (zero).) Project D Time: Cash flow: 0 -$11,600 1 $3,410 $4,300 34 $1,640 $0 $1,120 Discounted payback period 0 years Should the project be accepted or rejected? accepted rejected...

  • Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent...

    Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: Cash flow: -$2,800 $1,070 $1,020 $889 $660 $460 Payback years Should the project be accepted or rejected? accepted rejected

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT