a)
Optimal weekly production schedule:
Production Student = 325
Production Plus = 100
Production Net = 375
Production Pro = 425
Optimal weekly profit = 143250
b)
Allowable decrease of Production plus is 55 which means minimum profit => lower range of optimality => 80-55 = 25 for which optimal quantity production for Production plus will remain same as calculated in part a)
c)
Yes MVC should do this as shadow price of 17 in monitor total is 25 and this is valid for another 100 17 inch monitors. This means for every additional unit profit will increase by 25 which is more than the cost to do it which is 15
d)
No MVC should not do this as there is slack in production hours total constraint which means that the available production hours is not utilized so no point in increase production hours by hiring additional worker