Question

You are working on a construction site for GDOT, where an embankment will be built on a deposit of soft clay that is 4 ft thick. The clay is drained only at the top of the deposit.

(2a) If the proposed embankment is 30 ft tall and has a bulk unit weight γ = 108 pcf, then determine the initial increase in pore water pressure caused by the construction of the embankment.

(2b) Calculate the time for the clay to reach 90% consolidation, given Cv = 2.5x10-8 ft2 /sec.

100 80 Triangular initial excess porewater pressure 2 60 2 40 Uniform initial excess porewater pressure 20 Arrows show drainage direction 0 0.2 0.4 0.6 0.8 0

0 0
Add a comment Improve this question Transcribed image text
Answer #1

6 Answes Gaven that hickyi embankmentzott tlu İnitial, increase, in pove Hate) Pessuse caused by consthucon ct dam be The lhole presi by pose ates pree 3240 Pct ft

Add a comment
Know the answer?
Add Answer to:
You are working on a construction site for GDOT, where an embankment will be built on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The construction of a new embankment induces a uniform load of 18kN/m^2 on the top of...

    The construction of a new embankment induces a uniform load of 18kN/m^2 on the top of a 12 meter thick layer of saturated clay, whose characteristics are as follows: bulk unit weight γ=16kN/m^3 intial void ratio is 1.8 compression index Cc= 0.7 the water table is at the initial ground level top of the clay laye. Assuming the clay is normally consolidated. a) Estimate the settlement of the clay layer after the realization of the embankment. b) Compare results obtained...

  • Show all work 20-ft thick fill is planned to be placed at a construction site. Ground settlement is of concern due...

    Show all work 20-ft thick fill is planned to be placed at a construction site. Ground settlement is of concern due to high compressibility of the clay layer. A consolidation test was performed on a sample collected from the center of the 15-ft thick clay layer. On the following page, e-logp curve obtained from the test is included. Estimate ground settlement based on the information provided. Hint: Don't forget to correct the curve for field conditions. Ifơ0 is within 10%...

  • Question 5 (Effective Stress & Consolidation) Figure 05 shows the soil profile of a construction site....

    Question 5 (Effective Stress & Consolidation) Figure 05 shows the soil profile of a construction site. The water table is at the ground surface. Saturated unit weight of the sand is 18.8kN/m' and that of the clay is 19.6kN/m. Assume permeability of the clay is very low and unit weight of water is 10kN/m'. Water Table Sand 5m Clay 6m Figure 05 a) Determine the vertical total stress, pore water pressure, and vertical effective stress at the mid-height of the...

  • 1. An 8-m thick normally consolidated clay layer is doubly drained as shown below. (This means...

    1. An 8-m thick normally consolidated clay layer is doubly drained as shown below. (This means that a very pervious layer compared to the clay exists on top of and under the clay layer) The embankment applied an average vertical stress increase of 100 kPa to the clay layer. The water table is located at the mid depth of the sand layer. Assume the sand above the water table is dry 0 Pore water pressure, u (kPa) 20 40 60...

  • The ground profile of a construction site consists of a 3 m thick layer of sand...

    The ground profile of a construction site consists of a 3 m thick layer of sand followed by a 2 m thick layer of clay lying on impervious bedrock. The watertable is at a depth of 2 m below the ground surface. The sand has a dry unit weight of 16 kN/m and a saturated unit weight of 18 kN/m3. The capillary rise in sand is 0.5 m. The clay has a bulk unit weight of 19 kN/m 1. One...

  • An extensive filling project to form a platform for a subdivision housing development is proposed...

    An extensive filling project to form a platform for a subdivision housing development is proposed. Preliminary data based on several site investigation boreholes suggests that the geology of the proposed site is as shown in Figure 1, which implies the fill will be placed over a swampy area of soft saturated normally consolidated clay overlaying a bed of relatively incompressible well-drained dense sand. The water table in the clay layer is at the surface of the clay layer, and it...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT