Frank’s Fine Furniture makes tables, desks, bookcases, and other office furniture. At the North California facility, they make tables. All parts of the table are purchased except for the tabletop that is fabricated at the plant. Tables are made to order for dealers who FAX orders into the sales department. Orders are processed from the order database on FIFO basis.

The first step in the process is to cut the top ¾ pressboard. It takes one worker 20 minutes to cut each top. Four workers work in the cutting work center each with his own cutting equipment. At the same time the plastic laminate that goes on top of the table (the finished surface) is cut from stock. There are four other workers each with their own equipment in this work center. It takes one worker 30 minutes to cut this material.

The next step is to glue the plastic laminate to the pressboard top. The contact cement is applied to the top surface of the pressboard and the bottom surface of the laminate. There is one worker who applies the glue to both surfaces. It takes him 5 minutes to apply the glue. After the glue has been applied the two pieces are lined up and pressed together. There is one worker who does that and it takes her 6 minutes to complete that step. After pressing together, the assembled top must be set aside for 30 minutes to allow the glue to dry. There is unlimited space in this drying area.

The finished tabletop is then attached to the leg assembly that is purchased from a nearby metalworking firm. It takes a team of two workers working together for 10 minutes to attach the leg assembly to the tabletop. There are two such teams in this assembly area.

Finally the table is packed and shipped by one team of two workers working together who take 4 minutes to pack and ship one finished table.

  1. Draw a process flow diagram for the material flow at frank’s manufacturing plant including all work centers and their capabilities, inventory and information flow.

Time for each unit(minutes)

Service rate (units/hour)

# servers

Capacity (units/hour)

Cutting board

20

3

4

12

Cutting plastic

30

2

4

8

Glue

5

12

1

12

Press

6

10

1

10

Dry

30

2

Infinite

Infinite

Assemble

10

6

2

12

Shipping

4

15

1

15

  1. What is the Bottleneck in Frank’s plant? Explain (Short answer)
  2. How many tables can be produced in an 8 hour days?
  3. What are the Cycle and the throughput Times for this process?
  4. If one additional worker and tools were added to the bottleneck, how many tables could the line produce in an 8 hour day?
0 0
Add a comment Improve this question Transcribed image text
Answer #1

--INFLOW box a * % & Press DRYING CINE CAPACITY) for til La ... 15/ar a ASSEMBLY SHIPPING Legend - ...on Material Flow Informa.

b. Bottleneck is the slowest process which has lowest output which is Cutting plastic ( output of 8 per hour)

c Hourly production = 8

Daily production = 8x8 =64.

d Cycle time = 60/8 = 7.5 minutes ( time between successive units)

Thruoughput time = time taken for a unit to move though process = 20+30+5+6+30+10+4 = 105 minutes

If bottleneck is provided wih additional capacity, the next bottlenck will be Press with 10 /unit, and the new output will be 10 per hour

Add a comment
Know the answer?
Add Answer to:
Problem 4 Frank’s Fine Furniture makes tables, desks, bookcases, and other office furniture. At the North...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • S3-3 (book/static) EQuestion Help Kirkland Furniture is a manufacturing plant that makes a variety of tables,...

    S3-3 (book/static) EQuestion Help Kirkland Furniture is a manufacturing plant that makes a variety of tables, benches, and other furniture. Indicate which inventory account(s) would be affected by the following actions that occur at Kirkland's in the process of manufacturing its standard picnic tables. Also indicate whether the inventory account would increase or decrease as a result of the action. (Leave any unused cells blank.) Raw Materials Inventory Work in Process Inventory Finished Goods nventory Action a Lumber is delivered...

  • I AM COMPLETELY CONFUSED! Any help would be greatly appreciated. Chairvana’s Table Assembly Operations: Chairvana Inc....

    I AM COMPLETELY CONFUSED! Any help would be greatly appreciated. Chairvana’s Table Assembly Operations: Chairvana Inc. manufactures metal tables and chairs at its plant in Paxton, Illinois. Recently hired general manager, Bob Behar, is concerned about the large inventories and manufacturing inefficiencies in the plant. The Paxton plant has two separate assembly lines – one for chairs and one for tables. Demand for chairs is significantly larger than tables, so Bob decides to tackle the table assembly process for first....

  • Atlas Inc. is a toy bicycle manufacturing company producing a five inch small version of the...

    Atlas Inc. is a toy bicycle manufacturing company producing a five inch small version of the bike that Lance Armstrong rode to win his first Tour de France. The assembly line at Atlas Inc. consists of seven work stations, each performing a single step. Stations and processing times are summarized here: Step 1 (50 sec.): The plastic tube for the frame is cut to size. Step 2 (40 sec.): The tube is put together. Step 3 (55 sec.): The frame...

  • 1. The process is performed by several resources. 2. Resources are shared across assembly lines (i.e.,...

    1. The process is performed by several resources. 2. Resources are shared across assembly lines (i.e., workers must multitask and perform multiple activities for every flow unit.) 3. The resource that limits hourly production is not the same resource that limits the process lead-time. From 2002 to 2009, Honda’s 1800cc cruiser-style motorcycle, the VTX1800, was assembled in Marysville, Ohio from four major subassemblies. The following is a simplified explanation of the assembly process. All resources are indicated in bold.   •...

  • PowerToys Inc. produces a small remote-controlled toy truck on a conveyor belt with nine stations. Each...

    PowerToys Inc. produces a small remote-controlled toy truck on a conveyor belt with nine stations. Each station has, under the current process layout, one worker assigned to it. Stations and processing times are summarized in the following table: Station Task Processing Times (seconds) 1 Mount battery units 70 2 Insert remote control receiver 80 3 Insert chip 90 4 Mount front axle 60 5 Mount back axle 65 6 Install electric motor 50 7 Connect motor to battery unit 75...

  • 109 CASE STUDY Dream Desk Compary Dream Desk Company is a major supplier of office desks for can ...

    109 CASE STUDY Dream Desk Compary Dream Desk Company is a major supplier of office desks for can profit from this market growth if prices can be held in line home and business. The company has been in existence since 1875. Affler serving an apprenticeship as a cabinet maker in the and quick delivery can be promised. Dream Desk operates a 250,000 sq. ft. manufacturing fa- cast, George Dreamer had a violent disagreement with the shop eility in Casa Petite,...

  • 2. Please refer to the Aprons “R” Us case (starting on the next page), and answer...

    2. Please refer to the Aprons “R” Us case (starting on the next page), and answer the following questions: a) What is ARU’s current production capacity? If ARU is to increase its in-house capacity, where should it invest? b) With the current production rate, what is ARU’s total cost per apron? To do this you need to include material, freight, contractor, and the labor cost per apron*. c) Suppose ARU adds a worker at the bottleneck station, what is the...

  • You work for Thunderduck Custom Tables Inc. This is the first month of operations. The company...

    You work for Thunderduck Custom Tables Inc. This is the first month of operations. The company designs and manufactures specialty tables. Each table is specially customized for the customer. This month, you have been asked to develop and manufacture two new tables for customers. You will design and build the tables. This is a no nail, no screw, and no glue manufacturing ( no indirect materials used). You will be keeping track of the costs incurred to manufacture the tables...

  • You work for Thunderduck Custom Tables Inc. This is the first month of operations. The company...

    You work for Thunderduck Custom Tables Inc. This is the first month of operations. The company designs and manufactures specialty tables. Each table is specially customized for the customer. This month, you have been asked to develop and manufacture two new tables for customers. You will design and build the tables. This is a no nail, no screw, and no glue manufacturing ( no indirect materials used). You will be keeping track of the costs incurred to manufacture the tables...

  • Please fill out the chart using the information below: Step 1 You work for Thunderduck Custom Tables Inc. This is th...

    Please fill out the chart using the information below: Step 1 You work for Thunderduck Custom Tables Inc. This is the first month of operations. The company designs and manufactures specialty tables. Each table is specially customized for the customer. This month, you have been asked to develop and manufacture two new tables for customers. You will design and build the tables. This is a no nail, no screw, and no glue manufacturing ( no indirect materials used). You will...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT